Highway Maintenance, Advanced Design On Programmes For 2010-2011.

Agreed Executive 1 paper

Decision Session - Executive Member for Neighbourhoods and Housing. agreed this item on Tuesday 17 November 2009. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

That the Executive Members agreed: (i) To note the results of the 2009 condition surveys on the City’s roads and footways. (ii) To approve the split funding between footways and roads on a 50/50 basis. (iii) To approve the provisional programme of work. REASON: To ensure highway maintenance budget is expended in the most cost effective way based on the Council’s assessed priorities and approved policies. That the Executive Members agreed: (i) To note the results of the 2009 condition surveys on the City’s roads and footways. (ii) To approve the split funding between footways and roads on a 50/50 basis. (iii) To approve the provisional programme of work as detailed in annex 3 to 14 of the Officers report. REASON: To ensure highway maintenance budget is expended in the most cost effective way based on the Council’s assessed priorities and approved policies.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Neighbourhoods and Housing.

Executive Member for Neighbourhood 17 November 2009 Services – Decision Session Report of the Director of Neighbourhood Services

HIGHWAY MAINTENANCE, ADVANCED DESIGN ON PROGRAMMES FOR 2010-2011

Summary 1. This report outlines the preparation of the provisional highway maintenance surfacing programmes. It recommends and seeks approval to begin advanced design for a list of schemes in each category of work.

Background 2. With the approval of next year's programme we can begin to carry out advanced design of some of the schemes and minimise any delay at the start of the year. This approach has proved very successful over the last ten years and it is proposed to continue with these arrangements. It is a requirement under the Traffic Management Act (TMA) 2008 to serve a minimum three months notice of intention to carry out major works.

Surveys 3. In order to produce the programmes of highway works for the next year information is drawn from a number of sources:

• Visual safety survey of all our roads and footways.

• Detailed condition survey of all our roads and footways.

• UK PMS visual and machine surveys of all roads and approximately 22% of the footway network.

4. In previous years we carried out a full coarse visual condition survey of all our roads and footways in June – “the June survey”. This allowed us to grade them into three categories, grade 1 (good), grade 2 (average), and grade 3 (poor). By comparing with previous years’ survey results the survey informs us whether the condition of the city's infrastructure is improving or deteriorating and identifies those streets which need to be looked at more closely with regards to future maintenance schemes.

5. A number of modifications to the survey were introduced in 2009 as part of ongoing measures to improve the efficiency of the data collection: • The bulk of the survey was carried out in May to enable the advance programme to be identified earlier, with more time available for design ahead of work starting on the ground in the new financial year.

• To reduce duplication some streets were rated at the same time as the annual inspection.

• Roads on the classified network that scored grade 3 (poor) were then given a more detailed survey.

• The list of streets was updated to include all recently adopted roads.

6. The results of the 2009 survey indicate an increase in the number of grade 1 unclassified roads, including improvement to roads where no major works have been carried out. Changes to the survey method and the introduction of large machine lay patching have contributed to this improvement of the network. Further random inspections of those unclassified roads will be undertaken to reaffirm the condition rating. It is therefore difficult to directly compare the results from this years survey with last years results due to the changes outlined above. However with 82% of all roads being grade 1 or 2, York’s roads have better than average condition when compared to other councils in the Yorkshire and Humberside region. Also the Council’s footways are in the top quartile for condition compared nationally.

7. The results of the 2009 visual survey of the highway network are shown in Annex 1. Comments on trends for each category of road and footway are shown in Annex 2 and a full copy of the survey results is available in the Members library. The exact format for the survey in future years is under consideration in conjunction with the wider reorganization of inspection regimes within the More for York programme.

8. In August and September of 2009 a detailed condition survey was undertaken of all the following highways.

• Streets listed in our LTP 5 year programme of structural maintenance

• Streets identified as grade 3 by June 2009 survey

• Streets where the UK PMS survey showed that sections of them breached national intervention levels

• Requests by Members

• Requests by residents

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Maintenance, Advanced Design On Programmes For 2010-2011.Report 142 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 4 attended
AR
Councillor Ann Reid MBECabinet Member, present
AB
Andy BinnerOfficer, expected
GD
Geoff DerhamOfficer, expected
SM
Stephen MouldsOfficer, expected

On this subject at York

Search all
  1. Highway Maintenance, Advanced Design On Programmes For 2010-2011.This decision
  2. Highways Maintenance, Capital Programme & Major Development Highways Impacts Update, Scheduling & Planning Report [19.13]Decided
  3. Highway Maintenance Delivery Report for 2017/18Noted
  4. Highway Maintenance, Advance Programme for 2015-16Agreed
  5. Annual Highway Maintenance ReportNoted
  6. Annual Highway Maintenance ReportNoted

More from York Decision Session - Executive Member for Neighbourhoods and Housing.

All decisions
MeetingDecisionOutcome
15 Mar 2011 MinutesThat the minutes of the meeting held on 15 February be approved and signed by the Chair as a correct record. Approved Open
15 Mar 2011 Update on Private Sector Strategy.That the Executive Member noted the overall progress made to date in delivering the Private Sector Housing Strategy. ... Noted Open
15 Mar 2011 Removal of Private Sector Renewal Funding - Impact on the York Home Improvement Agency.(i)That the Executive Member noted the impact of the private sector renewal funding on service delivery both within t... Noted Open
15 Mar 2011 Achieving the Decent Homes Standard.(i)That the Executive Member noted that the Council has met the decent homes standard in line with the Governments De... Noted Open
15 Mar 2011 Decoration Voucher & Disturbance Allowance Scheme Allowances.That the Executive Member approved Options 1 & 2 as set out in the report to change the way Decorations and Disturban... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies