(i) That the progress made to date on the Community Stadium Project be noted. (ii) That approval be given to continue with the detailed feasibility work and preparation of the business case and to further explore potential partnerships to achieve wider community benefits. (iii) That a report summarising the business case for the project be brought to the Executive by July 2010. REASON: To ensure that Members are kept informed and updated on the progress of the project. (i) That the progress made to date on the Community Stadium Project be noted. (ii) That approval be given to continue with the detailed feasibility work and preparation of the business case and to further explore potential partnerships to achieve wider community benefits. (iii) That a report summarising the business case for the project be brought to the Executive by July 2010. 1 REASON: To ensure that Members are kept informed and updated on the progress of the project.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive Report of the Director of City Strategy
Community Stadium – Update Report Summary 1. The purpose of this report is to provide the Executive with an update on the progress of the Community Stadium project.
2. The project is on track and proposals with options to take the project forward will be reported to the Executive by July 2010.
3. The feasibility work is being finalised and a range of options is being tested. Development appraisals for the most appropriate sites and uses are underway. The project will have a major capital cost, however the feasibility work has identified an opportunity to lever-in significant funds from commercial development. This may provide the funding required to deliver the stadium, the wider community benefits and the future of the City’s professional sports clubs.
4. Due to the commercial sensitivities of this work it is not possible at this stage to provide specific details regarding sites, costs and uses. This might jeopardise the interests of the council and its partners, as well as the successful delivery of the project.
Background 5. An Outline Business Case which established the vision of a hub of sport, well- being and learning was considered by the Executive on 23rd July 2009. It was agreed that more detailed feasibility be commissioned to develop a robust and deliverable proposal. The following principles have been established to provide a framework as the project’s scope is developed:
§ A shared stadium for York City and York Knights to meet minimum league requirements. § A replacement athletics facility to a minimum of county standards (not inside the main stadium). § A location that maximises access opportunities for the people of York, the wider region and its visitors. § A facility that maximises community use including sport, education and health / well-being. § A viable business venture which is commercially sustainable. § An environmentally sustainable development.
6. It is in its capacity as a community facilitator that the Council is leading this project to improve the range and accessibility of sports / well being facilities and assist York City FC to secure its future. The Council has identified the project as a corporate priority and has allocated resources to assist in its delivery.
Project Progress 7. This is a complex development project that has now reached an important stage in the feasibility. This work is almost complete, but it is not yet possible to draw all the strands of the feasibility together. Due to the commercially sensitive and confidential nature of certain elements, it is not prudent to provide specific details. This information may prejudice the Council’s and its partners’ position and the ability to develop the most cost effective and beneficial option. The information below summarises the work currently underway. A chronology of key actions that have been undertaken since the Executive last consider a report regarding the project is provided in Annex 1.
Need Analysis
8. A full needs analysis has been undertaken for each of the potential component uses identified in the Outline Business Case. These have been assessed and considered in terms of priority, cost benefit and deliverability. The key areas identified were:
§ The size, capacity, format and design of the stadium. Detailed analysis of stadia across the country. Performance of similar teams. Demographic profile of the town / city. Scope for growth and supporter bases etc. The findings have been discussed with the key stakeholders and consideration given to the entry requirements for higher league status. Both teams favour a mix of seats and terracing. This will likely have a minimum capacity of 6,000 which is capable of being extending up to 10,000 if required. There is no support for an athletics track inside the stadium. Plans are now being finalised for the high level design of a core stadium.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.