( i ) That the contents of the report and the significant progress made since the last report to Executive in October 2017,be noted. (ii) That the proposed York City Knights financial support towards first team playing arrangements at Bootham Crescent be approved, as set out in Table 1 at paragraph 44 of the report and amounting to Council financial support payable up to a net cost of £30,000 for the 2019 Rugby League season, up until the new Stadium is operational. Reason: To ensure the continued progress of the Project. (i) That the contents of the report and the significant progress made since the last report to Executive in October 2017, be noted. (ii) That the proposed financial support towards YCK's first team playing arrangements at Bootham Crescent be approved, as set out in Table 1 at paragraph 44 of the report, amounting to council financial support payable up to a net cost of £30,000 for the 2019 Rugby League season, up until the new Stadium is operational. Reason: To ensure the continued progress of the Project.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The purpose of this report is to update the Executive on the progress of the Community Stadium and Leisure Facilities Project (“Project”) since the last Executive report presented in October 2017.
2. In doing so this progress report sets out an up to date position on the following: A construction progress update on the York Stadium Leisure Complex (“YSLC”); Updates on the latest position with all Community Partners and Sport Clubs. This includes a recommendation to provide further financial support to York City Knights RLFC (“YCK”) first team arrangements for the coming Rugby League season; An updated Project timetable, now that YSLC construction has commenced.
Recommendations
3. The Executive are asked to:
a) Approve the proposed YCK financial support towards first team playing arrangements at Bootham Crescent, as set out at table one of this report, amounting to Council financial support payable up to a net cost of £30,000 for the 2019 Rugby League season, up until the new Stadium is operational, paid from the existing Project budget;
1 b) Note the overall contents of this report and the significant progress made since the last report brought to Executive in October 2017.
Reason for recommendations: To ensure continued progress of the Project.
Overall Project Update:
4. Major milestones have been achieved on the Project since the last full Project report brought to Executive in October 2017. In this time updates on the Project have been provided within Capital Monitor reports to the Executive.
5. As was widely reported at the time, on the 16th November 2017 the Council entered into a minimum 13 year Design, Build, Operate and Maintain Contract (“DBOM Contract”) with Greenwich Leisure Ltd (GLL). 6. This milestone enabled the Project to move forward to its next major phase. Construction works to the YSLC commenced from December 2017, with GLL also taking over operational control of Existing Leisure Facilities, Energise and Yearsley Swimming Pool, at this time. 7. YSLC construction works are on programme, with all construction works scheduled to be complete by May 2019. Subsequent end user fit out, mobilisation periods and Stadium licensing test events will be required before an opening of the New Facilities from July 2019. 8. The Project by its conclusion will have helped deliver:
Regional standard athletics facility at Heslington West Campus – Successfully opened summer 2015.
Long term training arrangements for YCK at York St John’s University Haxby Road sports complex.
New long term leisure contract – GLL now operating and maintaining Energise and Yearsley Swimming Pool.
York Stadium & Leisure Complex – Location of the New Stadium but with so many more other leisure and community facilities present, including new swimming pools, gym, sports hall, Community Hub, NHS outpatient services and many more.
2 YSLC associated commercial offer – Regions first Cineworld IMAX Cinema, up to 5 restaurants, retail and further leisure offers.
York Stadium Leisure Complex 9. The main construction works to the YSLC commenced in December 2017 and are now well under way. Construction progress to date has been significant and has included:
All building foundations complete;
Steel frame complete on the entire Leisure Building, Stadium main East Stand and West Stand;
The main swimming pool and learner pool have been constructed;
Internal block work has commenced within the Leisure Building;
External cladding has started to the Leisure Building. 10. Annex A to this report provides a wide selection of recent construction site progress images.
11. Major upcoming construction milestones on site will see:
External cladding and glazing to start on Stadium main East Stand;
Completion of the steel frame on the North Stand;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.