That the Executive: a. Note the contents of the report and the progress made since the last report brought to Executive in July 2017; and b. Note and accept the new risk highlighted on the Commercial Development Capital Land Receipt, as per the details set out at paragraph 16 of the report. Reason: To progress with the Project and enter into all necessary legal agreements at Financial Close to deliver the New Stadium and Leisure Centre (NSLC) and operation by Greenwich Leisure Ltd of the NSLC and the city’s wider existing leisure facilities. That the Executive: a. Notes the contents of the report and the progress made since the last report brought to Executive in July 2017; and b. Notes and accepts the new risk highlighted on the Commercial Development Capital Land Receipt, as per the details set out at paragraph 16 of the report. Reason: To progress with the Project and enter into all necessary legal agreements at Financial Close to deliver the New Stadium and Leisure Centre (NSLC) and operation by Greenwich Leisure Ltd of the NSLC and the city’s wider existing leisure facilities.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Deputy Chief Executive/Director of Customer and Corporate Services
Portfolio of the Executive Member for Culture, Leisure & Tourism
Community Stadium & Leisure Facilities Update Report Report Summary 1. The purpose of this report is a concluding update to the Executive on the progress of the Community Stadium and Leisure Facilities Project (“Project”) since the last Executive report in July 2017.
2. This report confirms significant progress since July 2017, identifies a new risk highlighted at paragraph 16, and confirms that all necessary legal agreements are expected to be entered into soon.
Report Recommendations 3. The Executive are asked to: a) Note the contents of this report and the progress made since the last report brought to Executive in July 2017;
b) Note and accept the new risk highlighted on the Commercial Development Capital Land Receipt, as per the details set out at paragraph 16. Reason for recommendations: To progress with the Project and enter into all necessary legal agreements at Financial Close to deliver the New Stadium and Leisure Centre (“NSLC”) and operation by Greenwich Leisure Ltd (“GLL”) of the NSLC and the city’s wider Existing Leisure Facilities.
Project Update: 4. Significant progress has been made on the Project since the last report brought to Executive in July 2017. All aspects within the control of the Council that need to be in place before entering into the Design, Build, Operate and Maintain Contract (“DBOM Contract”) are expected to be complete within October 2017.
1 5. This includes the signing of the Community Partner agreements with York Teaching Hospital NHS Foundation Trust (“NHS”) and York Against Cancer. The signing of these Community Partner agreements, along with the existing legal agreements with York City Football Club and York City Knights RFLC, is another significant step forward in the Project and further prepares the Council to enter into the finalised DBOM Contract with GLL.
6. The last Project report presented to the Executive in July 2017 advised that GLL had concluded their re-tender exercise to appoint a new Building Contractor to their consortium team and that they were close to formally appointing its preferred new Building Contractor. It can now be confirmed that GLL have since appointed Buckingham Group Contracting Ltd as their new Building Contractor.
7. Pre construction design works have now been agreed with the Building Contractor and formally started on the 2nd October 2017, this further helping to enable a planned construction site mobilisation in November 2017. 8. The signing of the DBOM Contract is planned within October 2017.
NSLC Commercial Development 9. The Commercial Development outputs proposed at the NSLC site, which are being brought forward by Wrenbridge Sport (the "Developer") and which will ultimately be acquired by Legal and General (the “Investment Fund”), remain in principle the same as those set out in detail in the March 2016 Executive Report. 10. As set out in the July 2017 Executive Report, the Council was expecting to receive in total £10.76m from the Commercial Development. From the £10.76m, £8.7m (funding to the Project) would be paid through Capital Land Receipts in respect of the grant of the long lease of the East Stand Restaurant Units and the freehold transfer of the Southern Block to the Investment Fund. A further £2.06m would be received from the Commercial Development through contributions by the Investment Fund to the cost of the Stadium works, this contribution being used to meet part of the Construction Cost. 11. The Capital Land Receipts are to be received by the Council in two parts. £4.9m to be received at Financial Close (before construction commences) upon the execution of the freehold land transfer from the Council to the Investment Fund of the Southern Block. £3.8m (subject now to possible reductions as set out in paragraph 16 below) to be
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.