Resolved
That the update provided on risks associated with the York Sports Village Swimming Pool be noted. REASON: To provide assurance that risks to the Council are continuously reviewed and managed.
Audit and Governance Committee noted this item on Tuesday 29 June 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
That the update provided on risks associated with the York Sports Village Swimming Pool be noted. REASON: To provide assurance that risks to the Council are continuously reviewed and managed.
2. A&G regularly request reports on specific areas of risk as part of the committee’s governance remit. At the meeting of 15 February 2010 a detailed report on the development of the YSV Swimming Pool was presented by the Director of Adult Children and Education (ACE). Following the presentation A&G specifically requested a representative(s) from the university attended a future session to discuss the financial risk. This paper has been brought specifically in respect of this request.
Risk Associated with the YSV Pool
3. The YSV Swimming Pool forms one of the key risks contained within the council’s corporate risk register in relation to the Capital Programme. Representatives from the university have agreed to attend this evenings session to discuss the financial risk from the universities perspective.
4. The Exhibit below provides an extract from the risk register at the end of quarter 4 2009/10 describing the risk.
Exhibit 1 Net Risk Detail (cause) Implications (consequence) Score Actions - (Owner Due Date Priority)
KCR 0016 - CAPITAL PROGRAMME 0670 - Failure to The University has not yet Delivery of the University Pool is 21 692 - Work with the University to deliver York University set a start date for the dependent on York University Critical submit funding bids to Sport England Pool by 2011 construction of the pool and instigating the building works. This and the Football Foundation. (Charlie have not yet been able to has so far not happened and Croft, 31/03/2011, High) identify all the required therefore it is looking unlikely that it funding. will be complete by 2011. This 740 - University to review their capital means that the council will not be position (University of York, able to fill the gap in swimming pool 31/03/2011, High) provision until 2012. Options
5. Not applicable.
Corporate Strategy
6. The effective consideration and management of risk within all of the council’s business processes will contribute to achieving an ‘Effective Organisation’ and aid the successful delivery of each theme within the Corporate Strategy.
Implications
(a) Financial - There are no implications
(b) Human Resources (HR) - There are no implications
(c) Equalities - There are no implications
(d) Legal - There are no implications
(e) Crime and Disorder - There are no implications
(f) Information Technology (IT) - There are no implications
(g) Property - There are no implications except as included in Exhibit 1 in terms of risks to the capital project.
7. In compliance with the council’s Risk Management strategy, there are no risks directly associated with the recommendations of this report. The activity resulting from this report will contribute to improving the council’s internal control environment.
8. Audit & Governance Committee are asked to consider, comment on the views of the university in relation to this project. .
Reason
To provide assurance that risks to the council are continuously reviewed and managed. Contact Details
Author: Chief Officer Responsible for the report:
David Walker Charlie Croft Head of Financial Procedures Assistant Director of Lifelong learning & Phone No. 01904 552261 Resource Management
Report Approved Date
Specialist Implications Officer(s) Not applicable
Wards Affected Not applicable All
For further information please contact the author of the report
Quarter 4 Risk Monitor 2009/10
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Update: York Sports Village (YSV) Swimming PoolReport | 69 KB | DownloadRead as text |
Follow Audit and Governance Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Oct 2026 | Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... | Decided | Open |
| 21 Oct 2026 | Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... | Approved | Open |
| 21 Oct 2026 | Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... | Noted | Open |
| 21 Oct 2026 | Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... | Noted | Open |
| 21 Oct 2026 | Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.