Kerbside Recycling and Alternate Week Collection Expansion

Refused Executive 4 papers

Executive - for meetings from 03/06/00 to 26/04/11 refused this item on Tuesday 20 July 2010. Below is the council's own wording, with the papers it was decided on.

Item41

Resolved

(i) That the recently revised kerbside recycling and alternate weekly collection arrangements in the Leeman Road, Poppleton Road and Acomb areas be continued, whilst working with residents to improve refuse arrangements, in accordance with Option 2 in paragraph 22 of the report. REASON: To ensure that the Council can provide a service within the available budget that meets the needs of residents and the requirements of the collection service. (ii) That residents of streets off Holgate Road and Poppleton Road be consulted, as per action point (a) in paragraph 22. REASON: To help identify and resolve any problems in these streets. (iii) That the work which will be done for the Communication Plan, as set out in paragraph 29 be noted and that the Communication Plan at Annex C be agreed. REASON: To ensure that the Council is communicating clearly with residents and that they are supportive of the efforts to increase recycling. (iv) That the remaining 16,601 households be provided with full recycling and that the move be made to fortnightly residual waste collection, but that no change be made to collection points except where thee are clear safety concerns, as outlined in Option 1 at paragraph 25 of the report, and that the collection points be reviewed at some time in the future to ensure that services are delivered cost effectively. REASON: So that the Council can meet the requirements of the Household Waste Recycling Act 2003 to provide all households with kerbside collections for at least two recyclable materials by 31 December 2010. (i) That the recently revised kerbside recycling and alternate weekly collection arrangements in the Leeman Road, Poppleton Road and Acomb areas be continued, whilst working with residents to improve refuse arrangements, in accordance with Option 2 in paragraph 22 of the report. 1 REASON: To ensure that the Council can provide a service within the available budget that meets the needs of residents and the requirements of the collection service. (ii) That residents of streets off Holgate Road and Poppleton Road be consulted, as per action point (a) in paragraph 22. 2 REASON: To help identify and resolve any problems in these streets. (iii) That the work which will be done for the Communication Plan, as set out in paragraph 29 be noted and that the Communication Plan at Annex C be agreed. 3 REASON: To ensure that the Council is communicating clearly with residents and that they are supportive of the efforts to increase recycling. (iv) That the remaining 16,601 households be provided with full recycling and that the move be made to fortnightly residual waste collection, but that no change be made to collection points ... view the full minutes text for item 41.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Executive 20 July 2010

Report of the Director of Communities & Neighbourhoods

Kerbside Recycling & Alternate Week Collection Expansion Summary 1. This report requests the Executive to consider options for recycling and residual waste collections in the Leeman Road, Poppleton Road and Acomb areas, and also for other properties in the remainder of the city that do not have full recycling and fortnightly collection of residual waste.

Background 2. The Household Waste Recycling Act 2003 requires all Waste Collection Authorities to provide all households with kerbside collections for at least two recyclable materials by 31 December 2010.

3. In October 2007, Members agreed to the roll out of kerbside recycling to all households from April 2009 to meet the requirements of the Household Waste Recycling Act 2003. The details of the roll out were subject to findings arising from the Groves project that involved terraced properties and flats.

4. In September 2008, Members also approved that provision of full recycling should be supported by the introduction of an alternate weekly collection of residual waste and recyclables across the city.

5. In May 2009, Members approved that the roll out should continue on the basis of the collection model established in the Groves project.

City Wide Expansion Of Kerbside Recycling and Alternative Weekly Collection 6. The first part of the expansion programme involved approximately 1,000 properties (terraced and flats) in the Groves area. Properties receiving no recycling collection, or a limited service, were upgraded to full service. All properties were moved from weekly to alternative weekly collection of residual waste. Recycling and residual waste collections were rolled out in line with the collection model established in the Groves project. 7. Three petitions were received on 6 July 2009 from residents in Neville Street and Stanley Street. Two of the petitions were from residents opposed to storing wheeled bins in front forecourts and with a preference to continue with sack collections. The third petition was from residents opposed to wheeled bins being stored in front forecourts of properties on the opposite side of the street.

8. The main factor behind the petitions was the aesthetics of storing wheeled bins in front forecourts of terraced properties. The service, however, operated well with few problems and the survey work indicated that many residents had generally accepted wheeled bins.

9. It was therefore recommended and approved that the current service and the roll out of kerbside recycling and alternate weekly collection should continue.

10. The planned roll out of the revised recycling and residual waste collections continued in other parts of the city with service expansion firstly being targeted at flats and communal properties.

Leeman Road, Poppleton Road & Acomb Areas 11. In April 2010, the next phase of service expansion included 3,000 properties in the Leeman Road, Poppleton Road and Acomb areas of the city. This was implemented in line with roll out by collection round to free up resources to permit service expansion. These households had generally received waste collections from the lanes to the rear of properties. This phase of work coincided with the installation of gates in some back lanes that had been agreed as part of a separate process. This agreement, following consultation with residents included the change to front of property collection.

12. The service changes were implemented in line with the outcomes of the Groves trial project. These solutions, however, did throw up some challenges for some residents and with delivery of the service. Some residents expressed dissatisfaction with the new collection arrangements. Many residents, however, were pleased to receive a full recycling service. Residents’ concerns prompted consultation and a review of the impact of the service changes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Kerbside Recycling ExpansionAppendix A 53 KB Download
PDF
Kerbside Recycling ExpansionAppendix B 53 KB Download
PDF
Kerbside Expansion Project Communications Plan Annex CAppendix 47 KB Download
PDF
Kerbside Recycling and Alternate Week Collection ExpansionReport 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
AW
Councillor Andrew WallerChair, present
NA
Councillor Nigel AyreCommittee Member, present
SG
Councillor Steve GallowayCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
JM
Councillor Jonathan MorleyCommittee Member, present
AR
Councillor Ann Reid MBECommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
DM
Councillor Dave MerrettAttendee, in attendance
PH
Councillor Paul HealeyAttendee, in attendance
SW
Councillor Sian WisemanAttendee, in attendance

On this subject at York

Search all
  1. Kerbside Recycling and Alternate Week Collection ExpansionThis decision
  2. Kerbside Recycling & Alternate Week Collection Expansion - Petitions.Agreed
  3. Kerbside Recycling & Alternate Week Collection Expansion - Petitions.Approved
  4. Kerbside Recycling: City Wide Expansion 2009 - 2010Noted

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open