Capital Programme Out-turn 2009/10 and Revisions to the 2010/11-2014/15 Programme
NotedExecutive2 papers
Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 20 July 2010. Below is the council's own wording, with the papers it was decided on.
(i) That the 2009/10 capital out-turn position be noted and that the requests for slippage to and from the 2010/11 capital programme be approved. (ii) That the re-stated 2010/11 to 2014/15 programme, as summarised in Table 4 at paragraph 54 of the report and detailed in Annex 1, be approved. (iii) That the use of £25k contingency to support Strensall Parish Council in seeking to provide youth facilities in Strensall be approved, subject too the receipt by Officers of the business plan showing the scheme and partners. REASON: To allow the continued effective financial management of the capital programme from 2010/11 to 2014/15. (i) That the 2009/10 capital out-turn position be noted and that the requests for slippage to and from the 2010/11 capital programme be approved. 1 (ii) That the re-stated 2010/11 to 2014/15 programme, as summarised in Table 4 at paragraph 54 of the report and detailed in Annex 1, be approved. (iii) That the use of £25k contingency to support Strensall Parish Council in seeking to provide youth facilities in Strensall be approved, subject to the receipt by Officers of the business plan showing the scheme and partners. 2 REASON: To allow the continued effective financial management of the capital programme from 2010/11 to 2014/15.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Consultation
2. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 26 February 2009. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of the 2009/10 Capital Programme
3. The 2009/10 – 2013/14 capital programme was approved by Council on 26th February 2009. Since then a number of amendments have taken place as reported to the Executive in the 2008/09 Capital Programme Monitor 3 report, the 2008/09 Capital Programme Outturn report and the 2009/10 Monitor 1 and 2 and 3 reports. The changes made as result of the above papers have resulted in a current approved capital programme for 2009/10 of £62.956m, financed by £35.095m of external funding, and internal funding of £27.861m. Table 1 illustrates the movements from the start budget to the current approved position at monitor 2.
Gross External Internal Budget Funding Funding £m £m £m Original Budget Approved by 64.255 39.483 24.772 Council at 26 Feb 2009* Amendments from 2008/09 0.702 0.309 0.393 Monitor 3 report Amendments from 2008/09 4.017 (5.256) 9.273 outturn report Amendments from 2009/10 (1.940) 0.166 (2.106) Monitor 1 report Amendments from 2009/10 0.345 1.035 (0.690) Monitor 2 report Amendments from 2009/10 4.423 (0.642) (3.781) Monitor 3 report Current Approved Capital 62.956 35.095 27.861 Programme* Table 1 Current Approved Programme
4. Capital expenditure in 2009/10 totalled £58.480m. The capital programme spend represents the second largest capital programme delivered by the City of York Council marginally behind last years figure of £58.536m. It should be noted that effective management of the capital programme has resulted in the overall level of variance being controlled resulting in minimal variations over the course of the year against the outturn of £58.480m and essentially all the minor variations on specific schemes result in only a small increase in Council resources required (£107k).
5. Figure One illustrates the increase in capital programme size since 1999/00, during which time it has risen from £19.5m to this years outturn of £58.480m. Capital Spend 1999/00 - 2009/10 60 £m 55 50 45 40 35 30 25 20 15 10 5 0 1999/00
2000/01
2001/02
2002/03
2003/04
2004/05
2005/06
2006/07
2007/08
2008/09
2009/10 Figure 1: CYC Capital Programme Expenditure 1999/00-2009/010
6. Figure 2 shows the 2009/10 £58.480m expenditure split by departments.
Capital Expenditure 2009/10 28.626 Children Services
0.020 Economic Development
5.203 Neigh Serv
1.033 Resources 3.427 Chief Execs
0.400 1.804 Corporate 4.625 Admin Accom 0.701 Leisure & Heritage 7.946 4.695 Social Services City Strategy Housing
Figure 2 Capital Outturn by Department 2009/10
Key Outcomes
7. The 2009/10 capital programme has contributed toward the Corporate Strategy. Overall the Council has been successful in the delivery of a large capital programme that including a number of complex schemes. Examples of the success in 2009/10 are shown below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.