Highway Maintenance, Advanced design on programmes for 2011/12

Noted Executive 1 paper

Decision Session - Executive Member for Neighbourhoods and Housing. noted this item on Tuesday 21 December 2010. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

That the Executive Member: (i) Noted the results of the 2010 condition surveys on the city’s roads and footways. (ii) Approved the split in funding between footways and roads on a 40/60 basis. (iii) Approved the provisional programme of work listed in Annexes 3 to 12 of the Officers report. (iv) That Officers prepare a briefing note on the current situation and history of the works in Tranby Avenue in light of the speakers comments. REASON: To ensure the Highway Maintenance budget is expended in the most cost effective way based on the Council’s assessed priorities and approved policies. That the Executive Member: (i) Noted the results of the 2010 condition surveys on the city’s roads and footways. (ii) Approved the split in funding between footways and roads on a 40/60 basis. (iii) Approved the provisional programme of work listed in Annexes 3 to 12 of the Officers report. (iv) That Officers prepare a briefing note on the current situation and history of the works in Tranby Avenue in light of the speakers comments. 1 REASON: To ensure the Highway Maintenance budget is expended in the most cost effective way based on the Council’s assessed priorities and approved policies.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Neighbourhoods and Housing.

Decision Session - Executive Member for 21 December 2010 Neighbourhoods and Housing Report of the Director of Communities and Neighbourhoods

HIGHWAY MAINTENANCE, ADVANCED DESIGN ON PROGRAMMES FOR 2011-2012

Summary 1. This report outlines the preparation of the provisional highway maintenance surfacing programmes. It recommends and seeks approval to begin advanced design for a list of schemes in each category of work.

Background 2. With the approval of next year's programme we can begin to carry out advanced design of some of the schemes and minimise any delay at the start of the year. This approach has proved very successful over the last ten years and it is proposed to continue with these arrangements. It is a requirement under the Traffic Management Act (TMA) 2008 to serve a minimum three months notice of intention to carry out major works.

Surveys 3. In order to produce the programmes of highway works for the next year information is drawn from a number of sources:

• Visual safety survey of all our roads and footways.

• Detailed condition survey of all our roads and footways.

• UK PMS visual and machine surveys of all roads and approximately 22% of the footway network.

4. As in previous years we carried out a full coarse visual condition survey of all our roads and footways in June and July – “the annual condition survey”. This allowed us to grade them into three categories, grade 1 (good), grade 2 (average), and grade 3 (poor). By comparing with previous years’ survey results the survey informs us whether the condition of the city's infrastructure is improving or deteriorating and identifies those streets which need to be looked at more closely with regards to future maintenance schemes.

5. A number of modifications to the survey were introduced in 2010 as part of ongoing measures to improve the quality and efficiency of the data collection:

• The survey was carried out by the highway asset team within highway maintenance services to provide a more consistent assessment of the condition grading.

• The introduction of hand held technology was used to record the surveyed grading. The devices are mapped based and results can be displayed in a GIS format.

• Survey results have been loaded into the computerized highway management system to improved quality and provide reporting functionality.

6. The use of hand held technology gave the opportunity to identify those sections of a street where the condition was variable along its length. Previously it was not possible to record differing condition grades and a more general assessment was given for the whole street. This modification will give an accurate measure of the length of each condition grade for both the footway and carriageway network.

7. Changes in the survey method over the last 2 years mean that direct comparisons of recorded condition are not reliable. However, the results of the 2010 survey indicate an improvement in the overall condition of the roads and footpaths in York. The footways and unclassified roads show a steady improvement over the last 5 years, whilst the condition of the non principal (B and C) classified roads has remained steady. The proportion of principal (A) roads recorded in poor condition increased from last year, though the survey was carried out before the A19 (south) was resurfaced. This improvement in overall condition follows 2 years of significant additional investment in the road and footway network, together with an additional programme of large scale patching to repair the damage caused by last years severe winter weather.

8. The results of the 2010 visual survey of the highway network are shown in Annex 1. The survey results will be made available on YorkMap following this Decision Session and a computer link will be sent to all members. The exact format for the survey in future years is under consideration in conjunction with national guidance and asset valuation financial reporting requirements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Maintenance, Advanced design on programmes for 2011/12Report 141 KB DownloadRead as text

At this meeting

Whole meeting
32MinutesDecided
34Highway Maintenance, Advanced design on programmes for 2011/12This decision
35Update on Area Based Approach to Installing Energy Efficiency Measures.Noted

Who was there

1 of 8 attended
AR
Councillor Ann Reid MBECabinet Member, present
PC
Paul CarterOfficer, expected
BM
Barbara MatthewsOfficer, expected
AB
Andy BinnerOfficer, expected
GD
Geoff DerhamOfficer, expected
SM
Stephen MouldsOfficer, expected
PM
Paul MorrisonOfficer, expected
SB
Sally BurnsOfficer, expected

On this subject at York

Search all
  1. Highway Maintenance, Advanced design on programmes for 2011/12This decision
  2. Highways Maintenance, Capital Programme & Major Development Highways Impacts Update, Scheduling & Planning Report [19.13]Decided
  3. Highway Maintenance Delivery Report for 2017/18Noted
  4. Highway Maintenance, Advance Programme for 2015-16Agreed
  5. Annual Highway Maintenance ReportNoted
  6. Annual Highway Maintenance ReportNoted

More from York Decision Session - Executive Member for Neighbourhoods and Housing.

All decisions
MeetingDecisionOutcome
15 Mar 2011 MinutesThat the minutes of the meeting held on 15 February be approved and signed by the Chair as a correct record. Approved Open
15 Mar 2011 Update on Private Sector Strategy.That the Executive Member noted the overall progress made to date in delivering the Private Sector Housing Strategy. ... Noted Open
15 Mar 2011 Removal of Private Sector Renewal Funding - Impact on the York Home Improvement Agency.(i)That the Executive Member noted the impact of the private sector renewal funding on service delivery both within t... Noted Open
15 Mar 2011 Achieving the Decent Homes Standard.(i)That the Executive Member noted that the Council has met the decent homes standard in line with the Governments De... Noted Open
15 Mar 2011 Decoration Voucher & Disturbance Allowance Scheme Allowances.That the Executive Member approved Options 1 & 2 as set out in the report to change the way Decorations and Disturban... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies