Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability noted this item on Tuesday 20 March 2012. Below is the council's own wording, with the papers it was decided on.
That the Cabinet Member for Communities and Neighbourhood Services: (i) Noted the review of 2011/12 and proposals for 2012/13. (ii) Approved the allocation of budgets for 2012/13. (iii) Approved the implementation of the proposed programme. (iv) Approved the provisional list of schemes for 2013/14 with the ability to advance any works in conjunction with other Council projects. (v) Noted the comments made at the meeting by Councillor Warters . REASON: To ensure delivery of highway maintenance services in an efficient and cost effective manner. That the Cabinet Member for Communities and Neighbourhood Services: (i) Noted the review of 2011/12 and proposals for 2012/13. (ii) Approved the allocation of budgets for 2012/13. (iii) Approved the implementation of the proposed programme. (iv) Approved the provisional list of schemes for 2013/14 with the ability to advance any works in conjunction with other Council projects. (v) Noted the comments made at the meeting by Councillor Warters. 1 REASON: To ensure delivery of highway maintenance services in an efficient and cost effective manner.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability
Decision Session – Cabinet Member for 20 March 2012 Communities and Neighbourhood Services
Report of the Assistant Director (Environment)
Annual Highway Maintenance Report Summary 1. This report provides a review of the service performance in highway maintenance over the last year. The report examines issues arising and proposes programmes of work to be undertaken in the financial year 2012/13 and a provisional list for 2013/14. Background
2. The highway maintenance service covers a wide range of activities. It is delivered by a number of in-house teams, working in conjunction with external service providers. The Highway Maintenance Services (HMS) team in Communities and Neighbourhood Services (CANS) has overall management responsibilities for the highway assets; it determines works programmes for Members to consider and arranges for smaller scale routine maintenance works to be carried out on a priority basis. The Civils team in HMS carries out most of the work activities with the exception of street lighting which are provided by external contractors Amey Local Government (Amey LG). It is proposed from April 2012 to bring in-house the bus shelter maintenance which was previously carried out by Stoneplan.
3. Larger LTP/CYC capital and revenue schemes are designed and managed by the Design team in HMS. Works are procured through the Specialist Surfacing Framework Agreement in conjunction with other authorities in the Tees Valley Alliance. Minor works are carried out by the Civils team within HMS and through 2011/12 the team also acted as Principal Contractor on all larger schemes. This arrangement was found to be a success and has been extended into 2012/13.
4. Communities and Neighbourhoods, Street Scene team act as the corporate manager for grass cutting across the council and for amenity and landscaped areas requiring maintenance. Review of 2011/12 and Proposals for 2012/13 Adoptions
5. Over the past year the highway network has increased by 1.4 kilometres of carriageway and 2.1 kilometres of footway due to adoptions and new development.
Drainage
6. Members allocated £55k for high priority drainage works in 2011/12. This enabled area-wide investigation and remedial works to continue in several of the locations previously identified as suffering persistent ponding problems. The area-wide approach is more effective than reactive response to individual enquiries, with all repairs carried out with a view to assisting future maintenance and reducing the recurrence of problems.
7. The proposed drainage allocation of £165k in 2012/13 will give the opportunity to resolve some of the long term highway flooding problems. HMS will be working with the Flood Risk Management team within City Strategy to identify, prioritise and resolve flooding issues within the highway.
Street Lighting
8. The street lighting contracts currently with Amey LG is in the second year of a three year contract extension and are cohabiting with the Council at Hazel Court.
9. The current energy supply contract is procured through arrangements with YPO. The consortium procures energy on behalf of a number of authorities from greener more environmentally friendly sources whilst reducing the financial impact from a fluctuating market.
10. Following the previous years sample structural testing of metal street lighting columns the decision was taken to test all of the remaining stock during 2011/12. The results of this showed 6.0% at risk of immediate failure and a further 2.3% requiring likely attention within a year. All structurally failed columns have been removed to comply with the authorities legal obligations towards public safety.
11. Four schemes: Burton Stone Lane, Old Orchard, Alcuin Avenue and Cherry Orchard were undertaken in 2011/12 to replace columns removed as a consequence of the structural testing. These locations were subject of a new street lighting design which resulted in a reduction in energy usage whilst still improving the lighting quality in the street.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.