Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability noted this item on Thursday 20 March 2014. Below is the council's own wording, with the papers it was decided on.
(i) That the review of 2013/14 and proposals for 2014/15 be noted. (ii) That the allocation of budgets for 2014/15, as detailed in the report, be approved. (iii) That the implementation of the proposed programme be approved. Reason: To ensure delivery of highway maintenance services in an efficient and cost effective manner. (i) That the review of 2013/14 and proposals for 2014/15 be noted. (ii) That the allocation of budgets for 2014/15, as detailed in the report, be approved. (iii) That the implementation of the proposed programme be approved. Reason: To ensure delivery of highway maintenance services in an efficient and cost effective manner.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability, 14 pages
Decision Session - Cabinet Member for 20 March 2014 Environmental Services
Report of the Assistant Director (Highways, Waste and Fleet)
Annual Highway Maintenance Report Summary 1. This report provides a review of the service performance in highway maintenance over the last year. The report examines issues arising and proposes programmes of work to be undertaken in the financial year 2014/15. Background
2. The highway maintenance service covers a wide range of activities. It is delivered by a number of in-house teams, working in conjunction with external service providers. The Highway Maintenance Services (HMS) team in City and Environmental Services (CES) has overall management responsibilities for the highway assets. The team determines works programmes for members to consider and arranges for smaller scale routine maintenance works to be carried out on a priority basis. The Civils team in HMS carries out most of the work activities with the exception of street lighting which is provided by a separate in-house team in the same service group. 3. Larger LTP/CYC capital and revenue schemes are designed and managed by the design team in HMS. Works are procured through the Specialist Surfacing Framework Agreement in conjunction with other authorities in the Tees Valley Alliance. Minor works are carried out by the Civils team within HMS and through 2013/14 the team also acted as Principal Contractor on all larger schemes. This arrangement was found to be a success and has been adopted for future years. 4. Communities and Neighbourhoods Services, Public Realm team act as the corporate manager for grass cutting and for amenity and landscaped areas requiring maintenance. Review of 2013/14 and Proposals for 2014/15 Adoptions
5. Over the past year the highway network has increased by 4.2 kilometres of carriageway and 6.0 kilometres of footway due to adoptions and new development.
Drainage 6. Members allocated £200k for high priority drainage works in 2013/14. Working with the Flood Risk Management team a number of areas were identified for investigation and remedial works, prioritised in accordance with the criteria previously approved by members (City Strategy EMAP 2 June 2008) as detailed below:
• Locations where flooding affects, or is quite likely to affect, property • Locations adjacent to well used footways • Locations adjacent to footways near elderly person's homes • Locations where standing water are at a critical location for vehicle braking or turning • Locations where flooding problems are frequent and have been persistent for some years • Locations where flooding is particularly extensive
7. These include several of the locations previously identified as suffering persistent ponding problems, together with other new locations where problems occurred as a result of heavy rainfall events. Many of the flooding areas require joint investigation with other Risk Management Authorities, mainly the Internal Drainage Boards and Yorkshire Water Services, to establish ownership and liabilities.
8. The proposed drainage allocation of £200k in 2014/15 will enable this maintenance of drainage assets to continue, assisting in the management of surface water flood risk, as recommended in the Surface Water Management Plan approved by Cabinet in 2012. The allocation is part of 5 year capital rolling programme totalling £1m. 9. The customised drainage network developed within the Exor Highway Management System is enabling highway drainage assets to be recorded electronically, and increase the efficiency of investigation and maintenance works in the future. Future development will look to include the use of mobile GIS enabled devices to record on-site investigations directly to the system, which could also be used during flood emergency situations for live updates to Silver Command.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.