Decision Session - Executive Member for Neighbourhoods and Housing. noted this item on Tuesday 15 March 2011. Below is the council's own wording, with the papers it was decided on.
That the Executive Member: (i) Noted the review of the 2010/11 and the proposals for 2011/12. (ii) Approved the allocation of budgets for 2011/12. (iii)Approved the implementation of the proposed programme. (iv) Approved the reserve list of schemes. (v) Approved the additional £823k capital and revenue scheme programme. (vi) Noted that the Executive would be asked to approve the use of £657k from contingencies. (vii) Approved the use of preformed speed cushions that are bolted to the roads surface and other such industry wide innovations that will improve City road surfaces. REASON: To ensure delivery of highway maintenance services in an efficient and cost effective manner. That the Executive Member: (i) Noted the review of the 2010/11 and the proposals for 2011/12. (ii) Approved the allocation of budgets for 2011/12. (iii)Approved the implementation of the proposed programme. (iv) Approved the reserve list of schemes. (v) Approved the additional £823k capital and revenue scheme programme. (vi) Noted that the Executive would be asked to approve the use of £657k from contingencies. (vii) Approved the use of preformed speed cushions that are bolted to the roads surface and other such industry wide innovations that will improve City road surfaces. REASON: To ensure delivery of highway maintenance services in an efficient and cost effective manner.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Neighbourhoods and Housing.
Decision Session – Executive Member for 15 March 2011 Neighbourhoods and Housing Report of the Director of Communities and Neighbourhoods
Annual Highway Maintenance Report
Summary 1. This report provides a review of the service performance in highway maintenance over the last year, it examines issues arising and proposes programmes of work to be undertaken in the financial year 2011/12.
Background 2. The highway maintenance service covers a wide range of activities. It is delivered by a number of in-house teams, working in conjunction with external service providers. The Highway Maintenance Services (HMS) team in Neighbourhood Services (NS) has overall management responsibilities for the highway assets, it determines works programmes for Members to consider and arranges for smaller scale routine maintenance works to be carried out on a priority basis. The Civil’s team in HMS carries out most of the work activities, with the exception of street lighting and bus shelter maintenance, which are provided by external contractors Amey Local Government (Amey LG) and Stoneplan.
3. Larger LTP/CYC capital and revenue schemes are designed and managed by the Design team in HMS. The term contract that existed previously with Tarmac expired during this financial year and we are now procuring work through the Specialist Surfacing Framework Agreement alongside other authorities in the Tees Valley Alliance. Minor works are still carried out by the Civils team within HMS but for the coming year the Civils team will also act as Principal Contractor on all larger schemes using contractors procured using the framework.
4. Communities and Neighbourhoods, Street Scene team act as the corporate manager for grass cutting across the council and for amenity and landscaped areas requiring maintenance. Review of 2010/11 and Proposals for 2011/12 Adoptions
5. Over the past year the highway network has increased by 0.5 kilometres of carriageway and 0.5 kilometres of footway due to adoptions and new development.
Customer Satisfaction
6. The annual Residents Opinion Survey was replaced by the Place Survey in 2009/10, which does not include the question concerning the overall condition of roads and pavements. A replacement question has been included in the latest Talkabout survey, with the following combined results:
07/08 outturn 08/09 outturn 09/10 outturn Satisfaction with 50% 50% 50% roads and pavements
Drainage
7. From the results of the latest surveys the drainage of water from footpaths and roads continues to show one of the highest levels of customer dissatisfaction within the highway maintenance service.
8. Members allocated £200k for high priority drainage works in 2010/11. This enabled significant resources to be employed tackling drainage problems within particular areas, rather than reactive response to individual enquiries.
9. Problem areas were identified from customer and member enquiries, and officers’ local knowledge with those areas being prioritised in accordance with the criteria approved by members (City Strategy EMAP 2 June 2008):
• Locations where flooding affects, or is quite likely to affect, property
• Locations adjacent to well used footways
• Locations adjacent to footways near elderly person's homes
• Locations where standing water is at a critical location for braking or turning
• Locations where flooding problems are frequent and have been persistent for some years
• Locations where flooding is particularly extensive
10. The priority list was reassessed through the year and amended where necessary to reflect changing circumstances. Each location was investigated, and remedial works carried out as necessary to improve the effectiveness of the whole drainage system. All repairs have been carried out with a view to assisting future maintenance and thus reducing the recurrence of problems.
11. At the time of writing this report the programme of scheduled gully cleaning is on target for completion of all wards by the end of March.
Street Lighting
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Neighbourhoods and Housing. at York and we tell you when its next papers are published, before the meeting rather than after it.
Update on Private Sector Strategy.That the Executive Member noted the overall progress made to date in delivering the Private Sector Housing Strategy. ...
Achieving the Decent Homes Standard.(i)That the Executive Member noted that the Council has met the decent homes standard in line with the Governments De...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.