Highway Maintenance - Advanced Design on Programmes for 2012-2013

Noted Planning 4 papers

Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability noted this item on Wednesday 23 November 2011. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

That the Cabinet Member: ( i )Noted the results of the 2011 condition surveys on the city’s roads and footways. (ii)Approved the split in funding between footways and roads on a 40/60 basis. (iii)Approved the provisional programme of work listed in Annex 2 and 3 of the report. REASON: To ensure the Highway Maintenance budget is expended in the most cost effective way based on the Council’s assessed priorities and approved policies. That the Cabinet Member: ( i )Noted the results of the 2011 condition surveys on the city’s roads and footways. (ii)Approved the split in funding between footways and roads on a 40/60 basis. (iii)Approved the provisional programme of work listed in Annex 2 and 3 of the report. REASON: To ensure the Highway Maintenance budget is expended in the most cost effective way based on the Council’s assessed priorities and approved policies.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability

Decision Session – Cabinet Member for 23 November 2011 Communities and Neighbourhood Services

Report of the Assistant Director (Environment)

HIGHWAY MAINTENANCE, ADVANCED DESIGN ON PROGRAMMES FOR 2012-2013 Summary 1. This report outlines the preparation of the provisional highway maintenance surfacing programme. It recommends and seeks approval to begin advanced design for a list of schemes in each category of work.

Background 2. The continued pressure on Council budgets for 2012/13 makes it difficult at this moment in time to determine the level of funding to be allocated for highway maintenance surfacing next year. For the purpose of this report an initial capital allocation of £2.8m (2011/12 £3.3m) has been assumed

3. With the approval of the advanced programme we can begin to carry out designs for some of the schemes and minimise any delay at the start of the year. This approach has proved very successful over many years and it is proposed to continue with this arrangement. 4. It is a requirement under the Traffic Management Act (TMA) 2008 to serve a minimum three months notice of intention to carry out major works. Surveys

5. In order to produce the programmes of highway works for next year information is drawn from a number of sources:

• Visual safety survey of all our roads and footways. • Detailed condition survey of all our roads and footways

• UK PMS visual and machine surveys of all roads and approximately 22% of the footway network. 6. As in previous years a full coarse visual condition survey of all our roads and footways was undertaken in June and July. This allowed us to grade them into three categories, grade 1 (good), grade 2 (average), and grade 3 (poor). This identifies streets which need to be looked at more closely with regards to future planned maintenance schemes. 7. The results of the 2011 visual survey of the highway network are shown in Annex 1. The survey results will be made available on YorkMap following this Decision Session and a computer link will be sent to all members. 8. The overall footways and roads show a slight deterioration over the last 12 months however their condition over the last 5 years remains stable. Unfortunately the severe winter weather over the last two years has had a detrimental effect on the condition of the network but has been offset in part by the additional CYC and government funding. 9. In August and September of 2011 a detailed condition survey was undertaken of all the following highways:

• Streets identified as grade 3 by the 2011 annual condition survey

• Streets where the UK PMS survey showed that sections of them breached national intervention levels

• Requests by Members

• Requests by residents

• Recommendations of the Council's Safety and Area Highway Reactive Inspectors along with other officers of the Council

10. Each road and footway is assessed and given a ranking (score) based on engineering criteria and experience, with a treatment solution determined. 11. Machine surveys to identify the skid resistance value and other highway defects of all principal roads and other classified roads are undertaken on an annual basis.

12. With all this condition information we are in a good position to identify where we should direct our maintenance activities and develop the programmes of work.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
231111 HM Report Annex 1Appendix 68 KB Download
PDF
231111 HM Report Annex 2Appendix 46 KB Download
PDF
231111 HM Report Annex 3Appendix 46 KB Download
PDF
Highway Maintenance: Advanced Design on Programmes for 2012-2013Report 109 KB DownloadRead as text

At this meeting

Whole meeting
14MinutesApproved
15Highway Maintenance - Advanced Design on Programmes for 2012-2013This decision
16Annual Report – Parking Services 02010/11Agreed

Who was there

1 of 2 attended
JL
Councillor Janet LookerCabinet Member, present
MW
Councillor Mark WartersAttendee, in attendance

On this subject at York

Search all
  1. Highway Maintenance - Advanced Design on Programmes for 2012-2013This decision
  2. Highways Maintenance, Capital Programme & Major Development Highways Impacts Update, Scheduling & Planning Report [19.13]Decided
  3. Highway Maintenance Delivery Report for 2017/18Noted
  4. Highway Maintenance, Advance Programme for 2015-16Agreed
  5. Annual Highway Maintenance ReportNoted
  6. Annual Highway Maintenance ReportNoted

More from York Decision Session - Cabinet Member for Environmental Services, Planning and Sustainability

All decisions
MeetingDecisionOutcome
11 Dec 2014 MinutesThat the minutes of the Decision Sessions – Cabinet Member Environmental Services, Planning and Sustainability held o... Approved Open
11 Dec 2014 Request for an Article 4 Direction relating to The Punch Bowl public house, Lowther Street, YorkThat a decision on whether or not to make an Article 4 Direction in respect of the Punch Bowl public house, 134 Lowth... Deferred Open
30 Oct 2014 MinutesThat the minutes of the Decision Session held on 8 th March 2014 be approved and signed by the Cabinet Member for Tra... Approved Open
30 Oct 2014 A Draft Framework for York's Third Air Quality Action Plan (AQAP) 2014 to 2020.That the Cabinet Members’ approved Option A and approved the draft framework for the Third Air Quality Action Plan (A... Approved Open
13 Oct 2014 Proposed Upper and Nether Poppleton Neighbourhood PlanThat the Cabinet Member: i. Approved the Upper and Nether Poppleton Neighbourhood Plan application including the prop... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies