(i) That the progress made in implementing internal audit agreed actions, as detailed in paragraphs 5-11 of the report, be noted. (ii) That the changes made to the escalation procedure in agreement with the Assistant Director, Financial Services be noted. REASON: To enable Members to fulfil their role in providing independent assurance on the Council’s control environment.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. This is the regular six monthly report to the committee setting out progress made by council departments in implementing actions agreed as part of internal audit work. The report also includes details of revisions to the escalation process.
Background 2. Where weaknesses in systems are found by internal audit the auditors discuss and agree a set of actions to address the problem with the responsible manager. The agreed actions include target dates for issues to be dealt with. The auditors carry out follow up work to check the issue has been resolved, once these target dates are reached. The follow up work is carried out through a combination of questionnaires completed by responsible managers, risk assessment, and by further detailed review by the auditors where necessary. Where managers have not taken the action they agreed to, issues are escalated to more senior managers, and ultimately may be referred to the Audit and Governance Committee.
3. A summary of the findings from follow up work is presented to this committee twice a year. The current report covers agreed actions with target dates up to 29 February 2012.
Consultation 4. Details of the findings of follow up work are discussed with the relevant service managers and chief officers. Follow up of internal audit agreed actions 5. A total of 140 actions have been followed up since the last report to this committee in September 2011. A summary of the priority of these actions is included in figure 1, below. Figure 1: actions followed up as part of the current review Number of actions Priority of actions* followed up 1 2 2 22 3 116 Total 140 * The priorities run from 1 (high risk issue) to 3 (lower risk)
6. Figure 2 below provides an analysis of the actions which have been followed up, by directorate.
Figure 2: actions followed up by directorate Number of actions followed up by directorate Priority of Chief City actions CANS ACE CBSS Executives Strategy 1 (High) 0 0 1 0 1 2 0 6 3 4 9 (Medium) 3 (Low) 0 8 26 59 23 Total 0 14 30 63 33
7. Of the 140 agreed actions 82 (59%) had been satisfactorily implemented and 13 (9%) were no longer needed1.
8. In a further 43 cases (31%) the action had not been implemented by the target date, but a revised date was agreed. This is done where the delay in addressing an issue will not lead to unacceptable exposure to risk and where, for example, the delays are unavoidable (eg due to unexpected difficulties or where actions are dependent on new systems being implemented). The majority of these actions (39) are progressing satisfactorily and the remaining four are being explored further to establish whether any further audit involvement is needed. Figure 3 below show the priority of these actions.
Figure 3: priorities of actions with revised implementation dates Number of actions with a Priority of actions revised implementation date 1 (High) 2
1 For example because of other changes to procedures or because the service has ended or changed significantly. 2 (Medium) 7 3 (Low) 34 Total 43
9. In two cases (1%) action has not been taken to address the issue raised and the issues have been escalated to senior managers. One of these issues has been outstanding since the last report to this committee in September 2011. However, based on discussions with officers it is anticipated that this will be resolved within the next couple of months, without further escalation. The second action has only recently been escalated.
10. There are 48 actions where a final report has been issued but the completion date for the action has not yet passed and therefore no follow up has yet been carried out.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.