(i) That the risks set out in paragraphs 5 and 6 of the report be noted. (ii) That the directorate risk reporting agenda, as set out at paragraph 3 of the report, be approved. (iii) That, when the risk monitor report was considered at future meetings, copies of the detailed risk register be emailed to Members. 1 REASONS: (i) To provide assurance that risks to the council are continuously reviewed and updated. (ii) To ensure that directorates bring forward updated risk reports providing assurance that risk is being properly managed through 2012/13. (iii) To enable Members to give full consideration to the issues.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. The purpose of this paper is to present to Audit & Governance Committee (A&G) the current position of the risks associated with the Key Corporate Risks (KCRs) as at the end of February 2011.
Background
2. The High and Critical KCRs are reported to A&G four times a year and at least twice a year to Corporate Management Team (CMT) as part of the council’s overall governance arrangements. The KCRs along with directorate level risks are also regularly reviewed at Directorate Management Teams (DMT’s).
Monitor Four
3. As approved earlier this financial year (A&G 26 July 2011) in addition to providing the headline High and Critically ranked KCRs each quarter the monitor now also provides directorates the opportunity to present an overview of their own High and Critical risks. This is has been delivered on a rolling programme throughout the year. CBSS & OCE delivered their risk reports in September 2011 and CANS & CS in December 2011. The final directorates risk report (ACE) would have come to this meeting but has been deferred until A&G in July due to the current Ofsted inspection. The suggested full year programme for 2012/13 is set out below: A&G Committee Directorate . Date 25 July 2012 - Office of the Chief Executive + ACE
27 September 2012 - Customer & Business Support Services 12 December 2012 - Community & Neighbourhoods/City Strategy
13 February 2013 Adults Children & Education 4. T here has been a reduction by one in the number of Critical KCRs since Monitor 3 2011/12. The risk relating to the Capital Programme (Failure to obtain funding for Access York Phase 1) has been reduced to Medium and an update by the risk owner is set out below:
KCR 0016 Capital Programme
Failure to obtain funding for Access York Phase 1
'The delivery risk for Access York Phase 1has been reduced from critical because provisional funding for the project was confirmed by the Government and the City Council in November 2011. The final funding approval for the project is dependent on the tenders for the project being received below the budget allocation. This is not expected to be until November 2012. Other key risks including planning consent and land purchase have been resolved satisfactorily.
If Final Approval is obtained for the Access York Phase 1 scheme it is anticipated that the project would be completed and the Park & Ride sites operational, by summer 2014.’
5. There are now just two critical risks corporately and the up to date risk owners comments are set out below: KCR 0019 Safeguarding
Safeguarding (Eoin Rush)
“In common with every other local authority this risk remains a constant. The controls in place are regularly reviewed and updated in line with emerging national guidance. Measures to review and strengthen the controls in place to manage this risk in the next quarter include, implementation of our local action plan in response to peer review, following the unannounced inspection of our contact, referral and assessment service, implementation of a new supervision policy for all children’s social care workers involved in child protection activity and improved case file auditing arrangements. The service will also be responding to the findings of the Ofsted safeguarding and looked after children inspection conducted in March 2012”
KCR 0022 Financial Pressures
Reduction in Revenue Budgets (Keith Best)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.