That Cabinet: i) Note the provisional Local Government Finance Settlement figures; ii) Agree to the Leader, on the advice of the Director of Customer & Business Support Services, deciding on how to proceed with the council’s involvement in the LCR business rates pool. iii) Delegate approval of the annual NNDR1(National Non Domestic Rates) form to the Director of Customer & Business Support Services. REASON: i) To inform financial planning decisions for the 2013/14 and 2014/15 budgets. ii) So that the council’s income from the business rates retention scheme is maximised. iii) So that process for Council Tax and business rates are aligned and so that the council can submit business rates figures to Central Government as and when requested. That Cabinet: i) Note the provisional Local Government Finance Settlement figures; ii) Agree to the Leader, on the advice of the Director of Customer & Business Support Services, deciding on how to proceed with the council’s involvement in the LCR business rates pool. 1. iii) Delegate approval of the annual NNDR1 (National Non Domestic Rates) form to the Director of Customer & Business Support Services. 2. REASON: i) To inform financial planning decisions for the 2013/14 and 2014/15 budgets. ii) So that the council’s income from the business rates retention scheme is maximised. iii) So that process for Council Tax and business rates are aligned and so that the council can submit business rates figures to Central Government as and when requested.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Cabinet Member for Corporate Services
Local Government Finance Settlement Update
Purpose of Report 1. This report provides a high level analysis of the Local Government Finance Settlement, announced on 19 December 2012. It also provides an update on the status of Leeds City Region (LCR) pool.
Local Government Finance Settlement 2. The provisional Local Government Finance settlement for 2013/14 was announced on 19 December 2012. This is the first settlement that reflects the changes enacted in the 2011 Localism Bill including the localisation of business rates and Council Tax support.
3. The new funding system is predicated on a number of key themes: i) The majority of the Local Government national expenditure control total comprises a business rates aggregate which equates to the anticipated amount of rates collected for a given year, and a smaller portion of other funding such as the Early Intervention Grant and Council Tax Support. ii) The business rates aggregate is split in half, with 50% funding the localised rate retention scheme and the other 50% being combined with the other funding to fund a new Revenue Support Grant (RSG). iii) In order to transfer to the new system, each council is given a start up funding assessment, the equivalent of what they would have received under the old needs based Formula Grant system. iv) This is split between a baseline funding level and an RSG allocation directly proportionate to the national split determined in ii). v) An individual business rates baseline is also provided which equates to the council’s proportionate share of the national total rates collected, after Government have taken their 50% share. vi) Where a council’s individual business rates baseline is less than their baseline funding, they will receive a top up payment to ensure they are not unfairly penalised. vii) Where a council’s individual business rates baseline is higher than their baseline funding level, they need to pay a tariff. viii) The Government wants to ensure that no local authority makes disproportionate gains so for any growth, Government keep 50% and the remaining amount will be subject to a levy which will be paid into a central pot. ix) Equally, the Government doesn’t want any local authority to lose too much money should a local major economic shock occur, so the central pot collected from levies will fund safety net payments. x) All business rates figures will be uplifted annually by RPI.
4. Taking this into account, the provisional settlement provided the council with a series of key figures for 2013/14. i) A start up funding assessment of £58.1m. This corresponds to a loss of £4.0m compared to the Formula Grant funding received in 2012/13 (10.3%). ii) The start up funding assessment comprises of a £23.2m baseline funding level and a £34.9m Revenue Support Grant (RSG), a 40:60 split. iii) An individual business rates baseline of £45.1m. iv) This results in the council having to pay a tariff to Central Government of £21.9m. v) As York is a tariff authority, a levy rate of 49% has been allocated on any new growth. This means that for every £1 of growth in the city, only 25.5p will be retained locally.
5. Initial figures released for 2014/15 suggest that the RSG allocation will reduce in between £5m and £6m, or a loss of 14-16%. Whilst no details were announced for any financial settlements beyond 2014/15, the clear indications are that the grant support to local authorities will continue to be reduced in coming years.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.