That Cabinet agree to approve the following in relation to this scheme: i) Submission of the Full Approval Application to the Department for Transport. ii) An increase in the local contribution to the scheme of up to £750k from the Economic Infrastructure Fund and a re-profile of the Capital Programme where necessary. iii) Commencement of advance site clearance. iv) Commencement of advance utility diversions. v) Delegation of the acceptance of the Most Economically Advantageous Tender to the Director of City and Environmental Services in consultation with the Cabinet Member for Transport, Planning and Sustainability. REASON: To enable the delivery of the Access York project to programme. That Cabinet agree to approve the following in relation to this scheme: i) Submission of the Full Approval Application to the Department for Transport. 1. ii) An increase in the local contribution to the scheme of up to £750k from the Economic Infrastructure Fund and a re-profile of the Capital Programme where necessary. 2. iii) Commencement of advance site clearance. iv) Commencement of advance utility diversions. 3. v) Delegation of the acceptance of the Most Economically Advantageous Tender to the Director of City and Environmental Services in consultation with the Cabinet Member for Transport, Planning and Sustainability. 4. REASON: To enable the delivery of the Access York project to programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. Phase 1 of the Access York project to enhance the Park & Ride network is critical for the future economic prosperity and environmental wellbeing of the city. The receipt of tenders for the main construction works is a key milestone in the delivery of the project. This report requests that Cabinet approves the submission of the Access York Full Approval application to the Department for Transport (DfT). 2. Tenders have been received which are within the overall project budget allocation but at a level which is not considered to provide an adequate contingency allowance. It is recommended that minor adjustments are made to the project and funding is increased to cover this issue. A maximum funding increase of up to £750k from the Economic Infrastructure Fund is recommended. Subject to final clarification of the tender values it is anticipated that it will be possible to reduce the proposed funding increase significantly.
3. The report also recommends that Cabinet approves the advance site clearance and utility work to ensure that the project progresses to programme. Background 4. The existing Park & Ride service has insufficient capacity to keep pace with York’s buoyant and growing economy. The full Access York Phase 1 project involves:
• the construction of 2 new Park & Ride sites at Askham Bar and A59 near Poppleton, • a major upgrade to the A59/A1237 Outer Ring Road roundabout, • associated bus priority measures, • procurement of the Park & Ride operator. 5. The scheme has Programme Entry status in the DfTs Major Scheme programme which indicates that funds have been allocated to the scheme subject to Full Approval being granted.
6. The current overall funding provision is indicated in the following table
Funding Source £k Total Local Contribution 6,605 DfT Contribution 15,317 Total 21,922
7. A variety of sources have been identified to contribute to the £6.6m local funding of the scheme including: Local Transport Plan, Land Sales, Land Value, Developer Contributions, Economic Infrastructure Fund and Prudential Borrowing. The proposed funding sources were approved by the Council prior to the submission of the Best and Final bid in September 2011 and are identified in the Council’s current Capital Programme.
8. The receipt of tenders for the construction works is a key milestone in the delivery of the scheme and enables the Full Approval Application to be finalised and submitted to the DfT.
9. The necessary land has been purchased and the main sites have planning consent. The main construction works can commence immediately DfT funding is confirmed. Subject to Full Approval being received in March 2013 completion is programmed for April 2014.
10. This report identifies a number of key decisions which the Cabinet needs to make so that the project can progress to the required programme.
Submission of the Full Approval Application to the Department for Transport
11. Full Approval from the DfT is required before the contract for the works can be accepted and grants received. The Full Approval Application has to be made on the basis of tendered values to confirm costs. The submission must be authorised by the s151 Officer for the Council confirming that the match funding is available. The submission document must identify any significant changes to the project (scope, benefits etc.) since the Best and Final Bid submission in September 2011.
12. It would be beneficial for budget management and programme delivery purposes if approval is received before the end of the 12/13 financial year. For the works to commence in March 2013 the full approval submission must be submitted by the end of January at the latest as the DfT need at least 6 weeks to respond.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.