Executive, Tuesday 3 December 2013 at 5.30pm

Get York Building Phase 3 - Infrastructure Investment Plan For Growth

Agreed Executive 1 paper

Executive agreed this item on Tuesday 3 December 2013. Below is the council's own wording, with the papers it was decided on.

Item76

Resolved

i ) That Cabinet agree to earmark £10m from the Economic Infrastructure Fund for York Central, with £0.5m allocated immediately to advance the scheme in respect of support/technical work, and the remaining £9.5m subject to a more detailed report back to Cabinet in early 2014. ii) That a further detailed report be presented to Cabinet, early in 2014, setting out the full financial implications, risks, technical details, aspects of phased development and the mechanisms/legal relationship between CYC and network rail for a profit-sharing approach. Reason: i ) To facilitate the development of the York Central site by closing the final viability hurdle. ii) To give certainty to Network Rail that CYC is committed to this expenditure in principle. iii) To ensure that there is a level of detail agreed about project outputs/outcomes before monies are expended. iv) To allow preparatory work to commence. i) That Cabinet agree to earmark £10m from the Economic Infrastructure Fund for York Central, with £0.5m allocated immediately to advance the scheme in respect of support/technical work, and the remaining £9.5m subject to a more detailed report back to Cabinet in early 2014. 1. ii) That a further detailed report be presented to Cabinet, early in 2014, setting out the full financial implications, risks, technical details, aspects of phased development and the mechanisms/legal relationship between CYC and network rail for a profit-sharing approach. 2. Reason: i) To facilitate the development of the York Central site by closing the final viability hurdle. ii) To give certainty to Network Rail that CYC is committed to this expenditure in principle. iii) To ensure that there is a level of detail agreed about project outputs/outcomes before monies are expended. iv) To allow preparatory work to commence.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1. This report proposes to “earmark” £10m, from the Economic Investment Fund (EIF), for York Central. This will send a very strong and positive signal to our partners about our commitment to development on the site. The detail of how the full allocation will be used, along with full assessment of risk will be subject to a further report.

2. The report sets out why EIF investment in York Central infrastructure is essential to allow development to proceed.

3. The report builds on “Get York Building – Phase 1& 2” reports, approved by Cabinet in February and July 2013 that set out how we would progressively stimulate development activity. This investment proposal for York Central builds on this approach.

4. The proposal to earmark monies that will see new homes and business space on York Central directly supports the council priorities to Create Jobs and Grow the Economy and is complementary to “Get York Moving and “Protect the Environment” principles.

5. A subsequent technical report will set out the granular detail of how the £10m will be spent. The focus of this proposal is clearly the creation of a new access onto the site.

6. The scale of development will be 26 hectares within a site 35 hectares overall. It is of major importance to the city and taking a phased approach will allow development to proceed. Moreover, these proposals will also address some key issues in terms of;

a) The impact of growth – How the site fits within the emerging local plan transport strategy that supports a sustainable approach to growth in housing, business and retail, and in particular desired improvements to the station, interchange and walking/cycling connectivity to the city. b) Resources are in place to deliver – CYC’s investment covers “fees” and “works” ensuring we retain control of and can ensure certainty of delivery. c) Maximising the “planning gain” process – Although a partnership approach will be adopted, this will not reduce the need to secure the best legacy solution both on the site and its impact on the environment (sustainability, transportation, quality of housing/ business offer). d) Getting a return on investment – The viability gap has been progressively reduced, in commercial terms, from over £100m to a level that CYC proposes to address by enabling access. This will be a partnership approach with Network Rail and CYC will seek a return on this investment (ROI) via a profit-share mechanism. e) Supporting the supply chain – Investment in development is a catalyst to create new jobs and stimulate the growth of the local supply chain. The next report will set out how our work with educational establishments, developers, contractors and national agencies will seek to stimulate job creation. Demand for unskilled, semi-skilled, technical, professional and managerial resources for all development in the city will be addressed in a uniform and timely manner.

Background

Why invest in York Central now?

7. A previous approach to the market in Spring 2009 was unsuccessful due to the prevailing economic situation and very significant infrastructure investment gap at that time.

8. Investment in new development, using EIF or other CYC borrowed monies is financially and economically sustainable. This is based on progressive receipt of income from Council Tax and Business Rates, as well as the socio-economic benefits of addressing financial poverty and unemployment. This is in line with national policy which is seeking to boost short and long term growth through investment in infrastructure. It is also in line with the council’s agreed approach to delivering its key ambitions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Get York Building Phase 3: Infrastructure Investment Plan For GrowthReport 116 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, apologies
LC
Councillor Linsay Cunningham-CrossCommittee Member, present
DL
Councillor David LeveneCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present
CS
Councillor Chris StewardAttendee, in attendance
CF
Councillor Christina FunnellAttendee, in attendance

On this subject at York

Search all
  1. Get York Building Phase 3 - Infrastructure Investment Plan For GrowthThis decision
  2. Tree Canopy Target Update and York Green StreetsDecided
  3. York Tree Canopy TargetApproved
  4. York's Tree Canopy Expansion TargetApproved
  5. Lidgett House, 27 Lidgett Grove, York, YO26 5NE (17/01393/FUL)Approved
  6. Lidgett House, 27 Lidgett Grove, York, YO26 5NE (15/01924/OUT)Refused

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies