That Cabinet approve the sale of Site A and purchase of Site C, as shown at Annex A of the report for the capital receipt as set out in Confidential Annex B. Reason: To support corporate priorities with respect to jobs and economic growth, to enable the York Central project to progress and to provide capital receipts to fund the Council’s capital programme . That Cabinet approve the sale of Site A and purchase of Site C, as shown at Annex A of the report for the capital receipt as set out in Confidential Annex B. 1. Reason: To support corporate priorities with respect to jobs and economic growth, to enable the York Central project to progress and to provide capital receipts to fund the Council’s capital programme .
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
2. In July 2012 City of York Council acquired Sites A and B as shown on the Site Plan at Annex A from the Homes and Community Agency for a price as detailed in confidential Annex B 3. The reason for this strategic purchase was to assist with bringing forward developments on the York Central site. Negotiations have been taking place with Network Rail and other parties over the last 12 months and because City of York Council have been a strategic landholder they have been closely involved in these discussions. 4. This sale is a critical aspect to achieving this ambition to see York Central developed, not only does it release land to allow the final viability issues to be addressed, being the access onto site, it also allows network rail to consolidate its operational and employment activities with other operators on the “5-Acre site”. 5. This report is complementary to the Get York Building Phase 3 - Infrastructure Investment plan for growth report for York Central in that it will, subject to cabinet approval, see an investment of up to £10m from the Economic Infrastructure Fund (EIF) to create the access into it. The land transaction in this report is the enabler to achieve this, it provides land for network rail to consolidate operational, maintenance and thus employment activities on the “5- acre site” and in return provides a parcel of land for CYC to create the access into the site. 6. Clearly the sale itself is advantageous for CYC as there is an increase in value since purchase, CYC secures additional land to develop, thus it represents very good value for money for CYC. In parallel are massive economic drivers that come with the development of York Central, these are detailed in the Get York Building Report and summarised below; a) The total overall impact of the site on completion will be over 8,000 FTE (direct and indirect impacts through supply chains).
b) Circa £599m increase per annum GVA (direct and indirect impacts)
c) Development of the site is likely to require approx 6,700 construction jobs over its life. 7. These negotiations have resulted in identification of a phased programme of site release, allowing incremental but comprehensive development of the York Central site. A masterplan and supplementary planning guidance to test and inform this approach will be produced over the coming months. A separate report to Cabinet sets out the emerging details of this approach, and outlines options for the Council to invest in the facilitation and acceleration of site delivery. Early phases of this emerging programme relate to rail consolidation and rationalisation, freeing land for subsequent redevelopment, whilst ensuring York’s position as a 21st Century hub for operational rail employment.
The Proposal
8 Negotiations with Network Rail have resulted in the following proposal • City of York Council sell the freehold of Site A (2.1 hectares) to Network Rail (in order to enable early phases of rail consolidation and rationalisation).
• City of York Council purchase the freehold of Site C (1.1 hectares) from Network Rail
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.