Recommended: That Council be asked to confirm: (i) The City Council is supportive of the County Councils recommendation to proceed to Financial Close for the Long Term Waste Treatment Service contract given the revised environmental and financial assessments carried out and detailed in this report given the positive long term benefits; subject to the final terms within the Value for Money Envelope set out at paragraph 146 of the report. (ii) That delegated authority be given to the Director of Customer and Business Support Services (acting in consultation with the Director of City and Environmental Services and the Assistant Director (Governance & ICT) to amend the Joint Waste Management Agreement and to agree any other documents necessary to give effect to this project. (iii) That the Director of Customer andBusiness Support Services , is authorised to issue the certificates under the Local Government (Contracts) Act 1997 to confirm the City Council’s powers to enter into the contracts referred to above; (iv) That an indemnity be given by the City Council to the Director of Customer andBusiness Support Services, against any claim that may arise out of or in connection with the issue of the certificates under the Local Government (Contracts) Act 1997. (v) That all the Executive Decisions recommended above will not be implemented unless and until Full City Council agrees to the recommendation to proceed to Financial Close and Financial Close can be delivered within the Value for Money Envelope set out at paragraph 146 of the report. Reason: In order for Full Council to determine whether to enter into a long term waste management contract.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
the progress of the Long Term Waste Service Contract with AmeyCespa for provision of a waste treatment service at Allerton Quarry, Knaresborough
funding for the project in the context of the Government withdrawal of PFI credit support for the project 21 February 2013 and other changes
The report also asks Cabinet to consider whether the long term waste treatment project should progress to Financial Close within the approved affordability envelope.
2. The City Council resolved at its meeting in December 2010 to enter into a Joint Waste Management Agreement with North Yorkshire County Council (NYCC) which supported NYCC in entering into a contract (the Contract) with AmeyCespa (Allerton Waste Recovery Park Interim SPV Ltd) for the provision of a Long Term Waste Management Service. The primary objective of the Contract is to deliver a long term sustainable alternative to landfill for the treatment of residual municipal waste. The Contract required AmeyCespa to secure a planning consent for a waste recovery facility (AWRP) at Allerton Quarry before confirming the final cost of the service to the Council. A Satisfactory Planning Permission has been secured and the final cost of the service has been provided to the Councils for consideration. The County Council is therefore required to confirm its agreement to proceed with the Contract and the City Council is required to confirm its agreement to proceed with the Joint Waste Management Agreement.
3. The proposed technology and commercial offer open to the Councils remains essentially the same as described in 2010. Proceeding with the contract allows the Councils to complete delivery of its waste management strategy and provide a long term sustainable service for the management of residual waste. The proposed long term service contract will enable the Councils within York and North Yorkshire to achieve an average household waste recycling and composting rate in excess of 50%, whilst ensuring that a minimum of 95% of residual municipal waste collected in the area is diverted from landfill.
4. The technologies employed will recover value from residual waste through additional recycling and the production of electricity for export to the National Grid equivalent to the domestic needs of a town the size of Knaresborough. Ignoring the longer term potential to recover heat from AWRP, the greenhouse gas benefits compared to landfilling the waste to be processed at AWRP are also significant and are broadly equivalent to the removal of 12,000 average cars from the highway network. Proceeding with the contract therefore enables the management of residual municipal waste in York and North Yorkshire to be moved up the waste hierarchy into a ‘recovery’ process.
5. The financial and economic benefits of proceeding with the long term contract are also relevant considerations. AWRP will add approximately £220m (at 2014/15 prices) to the York and North Yorkshire economy over the life of the Contract through the creation of new jobs, both during construction and throughout the Contract period.
6. The decision to proceed with the Contract must have significant regard to the long term financial cost or saving to the Councils. The costs of both the long term contract and the alternative have changed since 2010 but the long term contract continues to show significant financial benefit. The Contract no longer benefits from PFI credits but this report shows that the Councils can expect the Contract to provide a combined net benefit of £169 million over the life of the Contract (equivalent to £31million in Net Present Value terms) excluding any allowance for the residual value of AWRP to the Councils after 25 years. The cost of the long term service contract is also within the Council’s available budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.