That Cabinet agree to: (i) Note the 2014/15 revised budget of £76.319m as set out at paragraph 5 and Table 1 of the report. (ii) Note the restated capital programme for 2014/15 – 2018/19 as set out at paragraph 28, Table 2 and detailed in Annex A of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme. That Cabinet agree to: (i) Note the 2014/15 revised budget of £76.319m as set out at paragraph 5 and Table 1 of the report. (ii) Note the restated capital programme for 2014/15 – 2018/19 as set out at paragraph 28, Table 2 and detailed in Annex A of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 27 February 2014. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
4. A decrease of £6.912m is detailed in this monitor resulting in a revised capital programme of £76.319m. £6.767m of the decrease is attributable to re-profiling to budgets to future years. The net decrease of £145k is attributable to a reduction in government grants available.
5. Table 1 outlines the variances reported against each portfolio area. Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m CSES Children’s 12.221 10.202 (2.019) Services, Education & Skills H&WB Adult Social 1.013 1.013 0.000 Services and Public Health CANS Communities 4.333 5.973 1.640 Culture & Public Realm CANS Housing & 17.483 17.292 (0.181) Community Safety CES Highways & Waste 7.460 7.460 0.000
CES Transport 9.042 9.042 0.000
CES Economic 0.058 0.058 0.000 Development CES Community 10.482 6.026 (4.456) Stadium CBSS Asset Management 2.548 2.548 0.000
CBSS West Offices - 0.533 0.533 0.000 Admin Accom CBSS IT Development 2.284 2.284 0.000 Plan CBSS Misc(Contingency ) 0.558 0.483 (0.075)
CBSS Economic 15.216 13.405 (1.811) Infrastructure Fund Total 83.231 76.319 (6.912)
Table 1 Capital Programme Forecast Outturn 2014/15
6. To the mid point in August there was £13.458m of capital spend representing 17.6% of the revised monitor 1 budget.
Analysis
7. A summary of the key exceptions and implications on the capital programme are highlighted below. CSES – Children Services, Education and Skills
8. Two amendments are made to the Children’s services capital programme as part of this report. The first is a reduction in budget of £19k per annum. This is as a result of two primary schools converting to academies in 2013/14 and the subsequent amount of Devolved Formula Capital received for these two schools being reduced. As these amounts were previously included in the budget they need to be removed.
9. The second change is in relation to the Basic Need programme of works. Within the main Basic Need programme the schemes that are currently in progress are the provision of an additional classroom at Skelton Primary School at an estimated cost of £180k (also incorporating some roof repairs and toilet refurbishment funded from maintenance at a cost of £50k), and an additional classroom at Badger Hill Primary School at a cost of £230k. Both these schemes are on site and are scheduled for completion by September 2014. The schemes are in response to already identified demand pressures being experienced by these schools.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.