That Cabinet agree to: ( i ) The demolition of the existing Ordnance Lane hostel to be replaced with a new modular build hostel, with the remainder of the site to be used for new council housing . (ii) The commencement of the proposed procurement for the replacement of Ordnance Lane Hostel. Reason: ( i ) To replace existing poor quality temporary homeless accommodation that is no longer fit for purpose with a high quality new build hostel, and much needed new council housing. (ii) To allow a new modular build hostel to be built that will minimise the disruption to the provision of temporary homeless services. That Cabinet agree to: (i) The demolition of the existing Ordnance Lane hostel to be replaced with a new modular build hostel, with the remainder of the site to be used for new council housing . (ii) The commencement of the proposed procurement for the replacement of Ordnance Lane Hostel. 1. Reason: (i) To replace existing poor quality temporary homeless accommodation that is no longer fit for purpose with a high quality new build hostel, and much needed new council housing. (ii) To allow a new modular build hostel to be built that will minimise the disruption to the provision of temporary homeless services.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Cabinet Member for Homes & Safer Communities
The Replacement of Ordnance Lane Homeless Hostel Summary 1. The following report outlines the options for the replacement of the existing temporary homeless hostel at Ordnance Lane, with a recommendation to demolish the existing and construct a new modular build hostel and new council housing on the same site. Background 2. Since 2007/8 the council has prioritised improvements to its homeless services including a new Housing Options service, increasing resources towards homelessness prevention, and new accommodation based services. As part of this programme of improvement the delivery of new homeless hostels has been a strategic priority. In 2008 a 39 bed direct access Arclight Hostel opened, followed in 2009 by the 22 unit Peasholme resettlement centre, both delivering an integrated package of accommodation, training and support for homeless adults. In 2012, following a successful pilot, a foyer scheme offering integrated services for young homeless people opened. This was a key tenet of the council’s 2011-2015 Housing Strategy and 2008-2013 Homelessness Strategy, which identified the provision of a young persons direct access resettlement centre as the missing link in the city’s homelessness service. The first tier self-contained accommodation is the primary stage for young people going through resettlement with support, incorporating all statutory and non-statutory services that work with young people. 3. The final stage in the homeless accommodation improvement strategy is the re-provision of the Ordnance Lane homeless hostel. The site currently houses 32 units of temporary accommodation, spread across four separate buildings. The hostels are of poor quality, difficult to manage, and have an immediate need for urgent and significant reinvestment. The challenges of managing and controlling the various access points in to the buildings are presenting an increasing security risk to both staff and customers. The accommodation also presents significant restrictions to people with disabilities or mobility problems. There are steps to all buildings, there are no options for the inclusion of lifts, and doorways cannot be widened to allow wheelchair access. Requirements 4. There are a number of key requirements of any re-provision, as outlined below:
39 unit hostel (see Para 5) Units should be a mixture of one and two bedroom (two beds would need a living room) with basic cooking facilities and preferably en-suite facilities. Some shared bathrooms can be tolerated. Office facilities to accommodate up to ten staff, and common rooms for training and meeting purposes The site or building needs to be located on the east side of the city, preferably within walking distance of the town centre for ease of access to other services For security reasons will need to be able to have one access point to control traffic in and out of the building Training kitchen Disabled access with units on ground floor Some outdoor space for children’s play Car parking for residents
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.