That Cabinet agree to: (i) Approve the use of £200k capital contingency for the works on the Councils existing Elderly Persons Homes to ensure they pass Care Quality Commission inspection. (ii) Note the 2014/15 revised budget of £72.555m as set out in paragraph 5 and Table 1 of the report. (iii) Note the restated capital programme for 2014/15 – 2018/19 as set out in paragraph 50, Table 2 and detailed in Annex A. Reason: To enable the effective management and monitoring of the Council’s capital programme That Cabinet agree to: (i) Approve the use of £200k capital contingency for the works on the Councils existing Elderly Persons Homes to ensure they pass Care Quality Commission inspection. (ii) Note the 2014/15 revised budget of £72.555m as set out in paragraph 5 and Table 1 of the report. (iii) Note the restated capital programme for 2014/15 – 2018/19 as set out in paragraph 50, Table 2 and detailed in Annex A. 1. Reason: To enable the effective management and monitoring of the Council’s capital programme
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 27 February 2014. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
4. A decrease of £3.764m is detailed in this monitor resulting in a revised capital programme of £72.555m. £4.273m of the decrease is attributable to re-profiling to budgets to future years. Offsetting this is a net increase of £509k attributable to an increase in government grants available. The Councils borrowing need across the 5 year programme is not changed as a result of these changes.
5. Table 1 outlines the variances reported against each portfolio area. Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m CSES Children’s 10.202 10.202 0.000 Services, Education & Skills H&WB Adult Social 1.013 0.835 (0.178) Services and Public Health CANS Communities 5.973 5.449 (0.524) Culture & Public Realm CANS Housing & 17.292 17.392 0.100 Community Safety
CES Highways & Waste 7.460 7.591 0.131
CES Transport 9.042 9.149 0.107
CES Economic 0.058 0.058 0.000 Development CES Community 6.026 3.026 (3.000) Stadium CBSS Asset Management 2.548 2.198 (0.350)
CBSS West Offices - 0.533 0.533 0.000 Admin Accom CBSS IT Development 2.284 2.284 0.000 Plan CBSS Misc(Contingency ) 0.383 0.183 (0.300)
CBSS Economic 13.405 13.665 0.250 Infrastructure Fund Total 76.319 72.555 (3.764)
Table 1 Capital Programme Forecast Outturn 2014/15
6. To the mid point in October there was £23.9m of capital spend representing 33% of the revised monitor 2 budget.
Key Schemes
7. Fulford School Expansion Phase 1 (£1,250k 14/15) of this planned three year scheme was carried out over the summer and comprised groundwork and infrastructure upgrades in preparation for the expansion of the school.
8. Carr Junior Expansion (£610k 14/15) project providing a three classroom extension to the existing building to enable the school to accommodate future demand through the increase in capacity of 80 additional places. The final stages of the project will be completed at October half term.
9. Universal Infant Free School Meals (£379k 14/15) approximately £260k has been spent or committed to assist primary schools to expand the provision of meals. A number of schools have been equipped with new Combi-ovens, and in addition a number of hot cupboards have been purchased to expand serving provision.
10. Huntington Secondary School New Block (£985k 14/15) scheme provided a seven classroom modular building to replace the existing Biology Block and 2 Temporary Classroom Units, which were at the end of their useful lives.
11. Basic Need Programme (£2,376k 14/15) including an additional classroom provided at Skelton Primary School at an estimated cost of £180k (also incorporating some roof repairs and toilet refurbishment funded from maintenance at a cost of £50k), and at Badger Hill Primary School at a cost of £230k. Both these schemes were completed by September.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.