City of York Council

Traffic Systems Asset Renewal Plan

Approved Executive 1 paper

Decision Session - Executive Member for Transport - Expired approved this item on Thursday 12 November 2015. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

That the Executive Member: ( i )Approved the commencement of the Traffic Asset Renewal Programme as outlined in the report. Reason: To ensure the City traffic signals equipment is up to date and the costs and risks to the Council of maintaining an increasingly aged asset are mitigated. (ii) Approved the continuation of the current programme of provision of new detector equipment. Reason: To ensure effective and reliable detection equipment is provided at traffic signal junctions in York for the benefit of road users. That the Executive Member: ( i )Approved the commencement of the Traffic Asset Renewal Programme as outlined in the report. Reason: To ensure the City traffic signals equipment is up to date and the costs and risks to the Council of maintaining an increasingly aged asset are mitigated. (ii) Approved the continuation of the current programme of provision of new detector equipment. Reason: To ensure effective and reliable detection equipment is provided at traffic signal junctions in York for the benefit of road users.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 15 pages

Summary

1. This report presents a plan for structured renewals of traffic signals across the city, which a recent asset condition assessment has shown are in need of significant investment.

2. The city has 122 traffic signal installations including 54 signalised pedestrian crossings. The recent condition survey has indicated that there is a significant backlog in the maintenance of the equipment. This report proposes a programme of renewals to ensure that the backlog is addressed and the traffic signals continue to operate to the level required. Recommendations

3. The Cabinet Member is requested to :

i. Approve the commencement of the Traffic Signal Asset Renewal Programme as outlined in this report

Reason: To ensure the City traffic signals equipment is up to date and the costs and risks to the Council of maintaining an increasingly aged asset are mitigated.

ii. Approve the continuation of the current programme of provision of new detector equipment. Reason: To ensure effective and reliable detection equipment is provided at traffic signal junctions in York for the benefit of road users. Background

Traffic signals asset renewal 4. The equipment present at York’s traffic signal sites is ageing and in many cases has either reached end of life, or is in poor condition. This situation has arisen because for many years maintenance has been arranged on a ‘repair and maintenance’ basis and the focus has been on repairing and operating the equipment we have. Although York’s traffic signals are safe and generally reliable, activities have focussed on repairing faults and dealing with immediate issues rather than taking a structured approach to addressing underlying asset condition. 5. Although this approach has served the City well in the past and has kept the revenue commitment required to maintain signals down to acceptable levels, a point has now been reached at which a more structured methodology is needed. It is considered that significant capital investment is now needed to renew the asset base and protect against the risk of increasing unreliability and rising maintenance costs. 6. This proposal is to adopt a more formal risk based approach to asset maintenance and to structure the replacement of life-expired on-street equipment into a single programme funded from LTP capital funds. This will be based on work completed in summer 2015 that produced a detailed asset database for traffic signals, which examined the age and condition of every signal site in the City. This approach will ultimately lead to reduced ongoing revenue requirements in the future, through reduced maintenance risk and higher levels of standardisation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Traffic Systems Asset Renewal PlanReport 15 pages DownloadRead as text

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies