City and Environmental Services Capital Programme - 2015/16 Monitor 1 Report
ApprovedExecutive3 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 12 November 2015. Below is the council's own wording, with the papers it was decided on.
That the Executive Member: i. Approved the virement of funds within the Highways and Transport Budgets. ii. Approved the amendments to the 2015/16 CES Capital Programme set out in Annexes 1 and 2. Reason: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 8 pages
Summary
1. The purpose of this report is to set out progress to date on schemes in the 2015/16 CES Capital Programme, including budget spend to the end of September 2015.
2. The report proposes adjustments to scheme allocations to align with the latest cost estimates and delivery projections.
Recommendations
3. The Cabinet Member is requested to:
i. Approve the virement of funds within the Highways and Transport Budgets. ii. Approve the amendments to the 2015/16 CES Capital Programme set out in Annexes 1 and 2. Reason: To enable the effective management and monitoring of the council‟s capital programme.
Background
4. The CES Transport Capital Programme budget for 2015/16 was confirmed as £5,292k at Full Council on 26 February 2015, and details of the programme were presented to the Executive Member at the March Decision Session meeting. The programme was finalised on 10 September 2015 when the Cabinet Member was presented with the Consolidated Capital Programme, which included all schemes and funding that had carried over from 2014/15.
5. The programme includes the Integrated Transport and CES Maintenance budgets, and includes £1,570k of Local Transport Plan funding, plus other funding from the Better Bus Area Fund grant, developer contributions, council resources, and funding from the Department for Transport for the A19 Pinchpoint scheme.
6. Table below shows the current approved capital programme.
Table 1: Current Approved 2015/16 Capital Programme
Gross Budget £1,000s Planning & Transport Budget 5,292 Variations approved at Consolidated Report 2,113 Current Approved CES Capital Programme 7,405
7. As stated in the 2015/16 Capital Programme Consolidated Report, the level of funding available in 2015/16 is significantly lower than in 2014/15, due to additional funding from the Department of Transport for the Access York scheme in the 2014/15 capital programme.
8. The current spend and commitments to the end of September 2015 are £2,188k, which represents some 30% of the current budget. This is in line with that anticipated due to the majority of the expenditure programmed towards the latter part of the year.
Key Issues
9. At this stage of the year, feasibility and outline design is underway for most of the schemes in the CES Capital Programme, which has allowed more accurate cost estimates to be prepared.
10. A review of the current programme has been carried out, which has identified a number of schemes where the allocations need to be amended to reflect minor alteration, scheme progress and updated cost estimates.
Due to a combination of efficiencies made in the delivery of Phase 1 of the A19 Pinch Point Scheme and a revision of the requirements for subsequent Phases the level of risk has been significantly reduced allowing the level of contingency funding to be reduced. This has allowed £350K LTP funding to be reallocated across the Capital Programme. Proposals for this funding reallocation are given below.
11. A separate report is also being presented at today‟s meeting which details proposals for a “Traffic Signals Asset Renewals and Detection Equipment Plan" that identifies a backlog of maintenance issues following a recent condition survey. Subject to the report being approved it is proposed to re- allocate £100k from the 2015/16 LTP for the initial stages of the project to enable the prompt commencement of the programme. This will primarily be around civil engineering activities such as ducting and the work will be coordinated with other maintenance works to ensure the most cost effectively delivery.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.