City of York Council
Executive, Thursday 16 March 2017 at 5.30pm

Additional Primary School Places for Micklegate

Agreed Executive 6 papers

Executive agreed this item on Thursday 16 March 2017. Below is the council's own wording, with the papers it was decided on.

Item129

Resolved

That the Executive agree to approve: (i) The expenditure of an estimated £225k of Basic Need funding to enable Scarcroft Primary School to increase by 0.5 form of entry (15 pupils per year group) to a 2 form of entry (60 pupils per year group). The funding will cover the cost of making internal refurbishment to the school building to add additional classroom space and other required facilities. (ii) £26k of additional expenditure from Basic Need funding to increase the amount of playing area on the school site (removal of car park spaces). (iii) £1m of basic need funding for a full size multi use games area (MUGA) to be located on the Millthorpe Secondary School site with additional parking spaces. The South Bank Multi Academy Trust has agreed to consult with the local community to determine the most appropriate place to locate these additional facilities on the school site. The Academy Trust has also agreed that during the school day the MUGA would be available for use by a number of schools in the area including Scarcroft Primary. Reason: To enable the council to meet its statutory duties to provide sufficient school places, it supports the proposed changes to Scarcroft Primary school’s building and the need to create additional outdoor play space. As from the 1 April 2016 Scarcroft Primary School became part of the South Bank Multi Academy Trust. This means that although the council remains responsible for ensuring there are enough school places in its area it will be the South Bank Multi-Academy Trust Board who have requested approval for the increase in the size of the school through the Regional Schools Commissioner. That the Executive agree to: (i) The expenditure of an estimated £225k of Basic Need funding to enable Scarcroft Primary School to increase by 0.5 form of entry (15 pupils per year group) to a 2 form of entry (60 pupils per year group). The funding will cover the cost of making internal refurbishment to the school building to add additional classroom space and other required facilities. (ii) £26k of additional expenditure from Basic Need funding to increase the amount of playing area on the school site (removal of car park spaces). (iii) £1m of basic need funding for a full size multi use games area (MUGA) to be located on the Millthorpe Secondary School site with additional parking spaces. The South Bank Multi Academy Trust has agreed to consult with the local community to determine the most appropriate place to locate these additional facilities on the school site. The Academy Trust has also agreed that during the school day the MUGA would be available for use by a number of schools in the area including Scarcroft Primary. 1 Reason: To enable the council to meet its statutory duties to provide sufficient school places, it supports the proposed changes to Scarcroft Primary school’s building and the need to create additional outdoor play space. As from the 1 April 2016 Scarcroft Primary School became part of the South Bank Multi Academy Trust. This means that although the council remains responsible for ensuring there are enough school places in its area it will be the South Bank Multi-Academy Trust Board who have requested approval for the increase in the size of the school through the Regional Schools Commissioner.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 8 pages

Summary

1. This paper will provide information on the cost of changes required at Scarcroft Primary School (part of the South Bank Multi Academy Trust) to allow them to accommodate an increase in pupil numbers. The paper also provides feedback following a consultation to consider options available to increase outdoor playing space at the same school in order to attempt to accommodate government requirements for sufficient playing areas.

2. The budget for this project was originally set at £2.5m. As a result of the two consultations which have taken place and the subsequent changes made it is now projected that the funding required will be £1.25m.

Recommendations

3. Members are asked to approve the expenditure of an estimated £225k of Basic Need funding to enable Scarcroft Primary School to increase by 0.5 form of entry (15 pupils per year group) to a 2 form of entry (60 pupils per year group). The funding will cover the cost of making internal refurbishment to the school building to add additional classroom space and other required facilities.

4. Members are also recommended to approve £26k of additional expenditure from Basic Need funding to increase the amount of playing area on the school site (removal of car park spaces). 5. Members are also recommended to approve £1m of basic need funding for a full size multi use games area (MUGA) to be located on the Millthorpe Secondary School site with additional parking spaces. The South Bank Multi Academy Trust has agreed to consult with the local community to determine the most appropriate place to locate these additional facilities on the school site. The Academy Trust has also agreed that during the school day the MUGA would be available for use by a number of schools in the area including Scarcroft Primary.

Reason: To enable the council to meet its statutory duties to provide sufficient school places, it supports the proposed changes to Scarcroft Primary school’s building and the need to create additional outdoor play space. As from the 1 April 2016 Scarcroft Primary School became part of the South Bank Multi Academy Trust. This means that although the council remains responsible for ensuring there are enough school places in its area it will be the South Bank Multi-Academy Trust Board who have requested approval for the increase in the size of the school through the Regional Schools Commissioner.

Background

6. This paper provides an update to previous papers that were considered by the Executive on the17 March (Annex A) and 19 May 2016 (Annex B) on this matter. In March, the Executive was asked to consider the expansion of Scarcroft Primary School. At their meeting in May, the Executive agreed in principle, following widespread consultation with the community, that the expansion should take place on the current site of the school in preference to expanding onto a different site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Additional Primary School Places for MicklegateReport 8 pages DownloadRead as text
PDF
Executive Micklegate March 2016Appendix A 11 pages Download
PDF
Executive MIcklegate May 2016Appendix B 8 pages Download
PDF
Micklegate Consultation DocumentAppendix C 4 pages Download
PDF
Micklegate Ward MinutesAppendix D 9 pages Download
PDF
CIAAppendix E 8 pages Download

At this meeting

Whole meeting

On this subject at York

Search all
  1. Additional Primary School Places for MicklegateThis decision
  2. Provision of additional temporary classrooms at Acomb Primary School due to increased pupil numbersApproved
  3. Additional Primary School Places for MicklegateApproved
  4. Additional Primary School Places for SouthbankAgreed
  5. Additional Primary School Places for SouthbankDeferred

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies