City of York Council
Executive, Thursday 16 March 2017 at 5.30pm

The Development of the Guildhall Complex

Agreed Executive 6 papers

Executive agreed this item on Thursday 16 March 2017. Below is the council's own wording, with the papers it was decided on.

Item136

Resolved

That Executive agree to: (i) The detailed business case for the regeneration of the Guildhall as set out in this report. (ii) Recommend to Full Council the total capital budget of £12.780m with prudential borrowing of £8.683m to fund the construction works to develop the Guildhall complex. (iii) Accept the terms of the Local Growth Fund (LGF) grant of £ 2.347m, from the Leeds City Region Local Enterprise Partnership (LCR LEP) (iv) Make a further listed building consent application to add a second lift into the south range to enable disabled access to both sides of the complex. (v) The award of a 25 year lease to a restaurant operator for the new build north annex riverside restaurant following a competitive marketing exercise. (vi) Put in place arrangements for CYC to manage and operate the serviced office and business club, Guildhall space and to procure an operator for the cafe provision for the Guildhall complex. (vii) Procure a construction contractor and to commence the construction of the Guildhall project in accordance with the Planning and LBC approvals and business case. (viii) The Mansion House, Guildhall and Common Hall Yard Management Plan establishing how the shared elements of the scheme will facilitate the operation of the Guildhall complex and the effective occupation of the Mansion House by the Civic Party. (ix) Form a cross party working group, working with Civic and Democratic Services to make recommendations to the Executive on refining the Management Plan before completion of the development and to keep the plan under review in operation. Reason: ( i ) T o ensure the future viability and effective re-use of the Guildhall as one of the City’s most significant historic buildings, through the creation a vibrant business and civic venue, with supporting commercial development on the riverside. (ii) T o ensure that the complex is as accessible as possible for disabled users. (iii) To ensure that the income generated by the Guildhall complex will fund the regeneration costs and will attract the high levels of use necessary to secure future viability, and manage the financial risk to the council. (iv) To ensure that the Guildhall will attract the high levels of use necessary to secure the future viability of the complex; deliver wider economic benefits to the city; manage the financial risk to the council and ensure the continuing civic use of the Guildhall. (v) To ensure the regeneration of the Guildhall complex and manage the financial risk to the council of developing a historic building. (vi) To satisfy the planning conditions and to ensure that the status of the Lord Mayoralty is enhanced, with safe and effective management and use of the public space and amenity for the Civic Party in the Mansion House. (vii) To ensure that the status of the Lord Mayoralty is enhanced, with safe and effective management and use of the public space and amenity for the Civic Party in the Mansion House. That Executive agree to: (i) The detailed business case for the regeneration of the Guildhall as set out in this report. (ii) Accept the terms of the Local Growth Fund (LGF) grant of £ 2.347m, from the Leeds City Region Local Enterprise Partnership (LCR LEP). 1 (iii) Make a further listed building consent application to add a second lift into the south range to enable disabled access to both sides of the complex. 2 (iv) The award of a 25 year lease to a restaurant operator for the new build north annex riverside restaurant following a competitive marketing exercise. (v) Put in place arrangements for CYC to manage and operate the serviced office and business club, Guildhall space and to procure an operator for the cafe provision for the Guildhall complex. (vi) Procure a construction contractor and to commence the construction of the Guildhall project in accordance with the Planning and LBC approvals and business case. 3 (vii) The Mansion House, Guildhall and Common Hall Yard Management Plan to establish how the shared elements of the scheme will facilitate the operation of the Guildhall complex and the effective occupation of the Mansion House by the Civic Party. (viii) Form a cross party working group, working with Civic and Democratic Services to make recommendations to the Executive on refining the Management Plan before completion of the development and to keep the plan under review in operation. 4 Reason: ( i ) T o ensure the future viability and effective re-use of the Guildhall as one of the City’s most significant historic buildings, through the creation a vibrant business and civic venue, with supporting commercial development on the riverside. (ii) T o ensure that the complex is as accessible as possible for disabled users. (iii) To ensure that the income generated by the Guildhall complex will fund the regeneration costs and will attract the high levels of use necessary to secure future viability, and manage the financial risk to the council. (iv) To ensure that the Guildhall will attract the high levels of use necessary to secure the future viability of the complex; deliver wider economic benefits to the city; manage the financial risk to the council and ensure the continuing civic use of the Guildhall. (v) To ensure the regeneration of the Guildhall complex and manage the financial risk to the council of developing a historic building. (vi) To satisfy the planning conditions and to ensure that the status ... view the full minutes text for item 136.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 15 pages

Recommendations

3. Executive are recommended to:

I. Agree the detailed business case for the regeneration of the Guildhall as set out in this report. II. Recommend to Full Council the total capital budget of £12.780m with prudential borrowing of £8.683m to fund the construction works to develop the Guildhall complex.

Agree to accept the terms of the Local Growth Fund (LGF) grant of £2.347m, from the Leeds City Region Local Enterprise Partnership (LCR LEP)

Reason:-to ensure the future viability and effective re-use of the Guildhall as one of the City’s most significant historic buildings, through the creation a vibrant business and civic venue, with supporting commercial development on the riverside.

III. Agree to make a further listed building consent application to add a second lift into the south range to enable disabled access to both sides of the complex.

Reason: - to ensure that the complex is as accessible as possible for disabled users.

IV. Agree to the award of a 25 year lease to a restaurant operator for the new build north annex riverside restaurant following a competitive marketing exercise.

Reason:– to ensure that the income generated by the Guildhall complex will fund the regeneration costs and will attract the high levels of use necessary to secure future viability, and manage the financial risk to the council.

V. Agree to put in place arrangements for CYC to manage and operate the serviced office and business club, Guildhall space and to procure an operator for the cafe provision for the Guildhall complex.

Reason:– to ensure that the Guildhall will attract the high levels of use necessary to secure the future viability of the complex; deliver wider economic benefits to the city; manage the financial risk to the council and ensure the continuing civic use of the Guildhall.

VI. Agree to procure a construction contractor and to commence the construction of the Guildhall project in accordance with the Planning and LBC approvals and business case. Reason: – to ensure the regeneration of the Guildhall complex and manage the financial risk to the council of developing a historic building.

VII. Agree the Mansion House, Guildhall and Common Hall Yard Management Plan to establish how the shared elements of the scheme will facilitate the operation of the Guildhall complex and the effective occupation of the Mansion House by the Civic Party.

Reason: - to satisfy the planning conditions and to ensure that the status of the Lord Mayoralty is enhanced, with safe and effective management and use of the public space and amenity for the Civic Party in the Mansion House.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GH Site PlanAppendix 1 1 pages Download
PDF
Planning Pack Scheme Detail PlansAppendix 2 11 pages Download
PDF
Guildhall Business PlanAppendix 3 1 pages Download
PDF
GH serviced office income projectionsAppendix 4 3 pages Download
PDF
Draft Mansion House, GH and CH Yard Management PlanAppendix 5 4 pages Download
PDF
The Development of the Guildhall ComplexReport 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. The Development of the Guildhall ComplexThis decision
  2. The Guildhall Redevelopment Tender Evaluation & Project Business Plan AppraisalNoted
  3. The Development of the Guildhall Complex (formerly 'Guildhall Procurement Update')Approved
  4. Guildhall Development Review Introductory ReportNoted
  5. Hungate Development Site Hungate York (07/01901/REMM) [Guildhall Ward]Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies