That the application be refused. Reason: The proposed development is inappropriate within the Green Belt within the definition outlined in paragraphs 89 and 90 of the National Planning Policy Framework and therefore by definition materially harmful to its openness. The proposal runs clearly contrary to the principles of including land within the Green Belt namely the prevention of encroachment into open countryside and the safeguarding of the setting of historic towns and cities. No case for "very special circumstances" has been brought forward overcome the strong policy presumption against inappropriate development within the Green Belt and ... view the full minutes text for item 35d
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Date: 14 September 2017 Ward: Huntington/New Earswick Team: Major and Parish: Huntington Parish Commercial Team Council
Reference: 17/00954/OUTM Application at: Land Adjacent Hopgrove Roundabout Beechwood Hopgrove York For: Outline planning application with all matters reserved for erection of petrol filling station, restaurant and 50-bedroom hotel with associated access, car parking and landscaping (resubmission) By: Enita Europe Limited Application Type: Major Outline Application (13 weeks) Target Date: 25 September 2017 Recommendation: Refuse
1.0PROPOSAL
1.1Beechwood, Hopgrove Roundabout Malton Road comprises a large partially secluded area currently in pasture use circumscribed by the A64 and A1237 York Outer Ring Road . The site is well landscaped along the eastern, south western and southern edges with residential properties set within large grounds adjacent to the former Malton Road to the north. The site is accessed from the A1237 and lies within the York Green Belt as well as being partially within Flood Zone 3. Outline planning permission is sought with all matters reserved for erection of a "signed" trunk road service area comprising a petrol filling station, restaurant/cafe, 50 bedroom lodge accommodation and a range of ancillary works. The proposal represents a re-submission of an earlier proposal in 2014(ref:14/00672/OUTM)- that was withdrawn following concerns in respect of its impact upon the open character of the Green Belt, impact upon Flood Risk in the locality and impact upon a known habitat of the water vole a species protected by law.
1.2The proposal has been screened in respect of Schedule 2 the 2017 Town and Country Planning (Environmental Impact Assessment) Regulations and been found not to warrant a separate process of Environmental Impact Assessment.
1.3A holding Direction preventing the Authority from approving the proposal for a period up until 30th November 2017 was served by the Highways Agency on 30th May 2017 on the basis that insufficient information was forthcoming with the proposal to enable a sufficient assessment of its impact upon traffic levels and road safety on the nearby A64
2.0POLICY CONTEXT 2.1 Development Plan Allocation: Application Reference Number: 17/00954/OUTM Item No: Page 1 of 10 City Boundary GMS Constraints: York City Boundary 0001
DC Area Teams GMS Constraints: East Area (2) 0005
Flood zone 2 GMS Constraints: Flood zone 2
2.2Policies:
CGP15A - Development and Flood Risk
CYGB1 - Development within the Green Belt
CYGP1 - Design
CYNE6 - Species protected by law
3.0CONSULTATIONS
INTERNAL:-
3.1Public Protection (Environmental Health) raises no objection in principle to the proposal but raise some concerns with regard to the impact of noise arising from the site on the residential amenity of neighbouring properties.
3.2Highway Network Management raises concerns in respect of the lack of information submitted with the proposal in respect of the levels of traffic to be generated by the proposal and its impact upon surrounding roads.
3.3Planning and Environmental Management (Archaeology) raisse no objection to the proposal subject to any permission being conditioned to require an archaeological evaluation of the site prior to construction of the development.
3.4Planning and Environmental Management(Ecology) raises no objection to the proposal on the basis that the most recent survey information does not record the presence of water voles within the application site.
3.5Strategic Flood Risk Management was re-consulted with regard to the proposal on 17th August 2017. Views will be reported orally at the meeting;
3.7Public Protection (Trading Standards) was re-consulted with regard to the proposal on 17th August 2017. Views will be reported orally at the meeting.
EXTERNAL:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.