Resolved
That the application be deferred. Reason: In order that the issues raised by the applicant’s Counsel be satisfactorily addressed.
Planning Main deferred this item on Thursday 15 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the application be deferred. Reason: In order that the issues raised by the applicant’s Counsel be satisfactorily addressed.
COMMITTEE REPORT
Date: 15 November 2018 Ward: Rural West York Team: Major and Parish: Hessay Parish Council Commercial Team
Reference: 17/00670/FUL Application at: Land Adjacent Sewage Works At Hessay Industrial Estate New Road Hessay York For: Erection of asphalt plant with associated infrastructure By: Anthea Tate Application Type: Full Application Target Date: 15 November 2018 Recommendation: Refuse
1.0PROPOSAL
1.1Hessay Industrial Estate comprises a medium sized employment site of some long standing occupying a former MOD depot on land within the general extent of the York Green Belt to the north of Hessay village. The wider site was given planning permission in 1999 for a mix of B1/B2 and B8 uses. Planning permission is sought for erection of a coated aggregates manufacturing plant situated within a building incorporating a mixing tower with associated chimney to be located at the western edge of the site. The proposal has subsequently been amended to include a detailed scheme of off-site highway works to attempt to address concerns in respect of both the access to the Industrial Estate and the nearby junction of the A59 with New Lane approaching the site.
1.2The site has a planning permission for erection of a fuel storage depot ref:- 10/00861/FUL dating to 2010 which was not implemented and has subsequently expired. A previous proposal incorporating an asphalt plant linked with the reinstatement of the rail head within a materially larger section of the site was submitted in 1999 but subsequently withdrawn.
1.3The total application site comprises some 7,200 sq metres in area which sets it within Schedule 2 of the 2017 Town and Country Planning (Environmental Impact Assessment) Regulations for which the application has been screened. A further Screening Direction has been made by the Secretary of State for Communities and Local Government which identifies the potential for significant environmental effects in respect of noise impacts and impacts upon the setting of Designated Heritage Assets. A formal EIA covering these issues has been subsequently submitted and consulted upon on 26th June 2018.
1.4Subsequent to the proposal being submitted amended details have been supplied to address concerns in respect of impacts of increased traffic flows on the adjacent highway network notably the junction of New Lane Hessay with the A59 directly to the north. Further consideration of the proposals has been deferred from consideration at Application Reference Number: 17/00670/FUL Item No: 4a the 17th August 2017 Committee to enable the detailed design and feasibility of the proposed off-site highway works to be established.
2.0POLICY CONTEXT
See Section 4 below.
3.0CONSULTATIONS
INTERNAL:-
Public Protection:-
3.1Raise no objection in principle to the scheme as amended subject to the imposition of detailed conditions in respect of controlling noise from later working along with the potential for light pollution. It is also recommended that any permission be conditioned to secure remediation in the event of potential land contamination.
Highway Network Management:-
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Land Adjacent Sewage Works at Hessay Industrial Estate Site PlanPlan | 1 pages | Download |
PDF |
Land Adjacent Sewage Works at Hessay Industrial Estate [17/00670/FUL]Report | 20 pages | DownloadRead as text |
Follow Planning Main at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 May 2022 | MinutesThat subject to the addition of Cllrs Melly and Ayre to the list of apologies, the minutes of the last meeting held o... | Approved | Open |
| 7 Apr 2022 | Minutesi. That the minutes of the meeting held on 3 February 2022 be approved and then signed by the chair as a correct reco... | Approved | Open |
| 3 Mar 2022 | MinutesThat the minutes of the last meeting held on 3 February 2022 be approved at the next meeting. | Approved | Open |
| 3 Mar 2022 | Lindum Group Limited, York Road, Elvington, York YO41 4EP [21/01709/REMM]That the application be approved subject to the conditions listed in the report and the addition of an informative in... | Approved | Open |
| 3 Feb 2022 | MinutesThat, subject to the amendment stated above, the minutes of the last meeting held on 6 January 2022 be approved and s... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.