CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Executive, Thursday 30 August 2018 at 5.30pm

Disposal of Ashbank - No. 1 Shipton Road, York

Approved Executive 4 papers

Executive approved this item on Thursday 30 August 2018. Below is the council's own wording, with the papers it was decided on.

Item31

Resolved

( i ) That the sale of Ashbank to Anchor Housing Trust (Anchor), as the highest net financial bidder, be approved. (ii) That Bidder 1 be retained as a reserve bidder and that, should Anchor fail to complete the purchase of Ashbank in a timely manner, authority be delegated to the Director of Economy & Place to agree its disposal to the reserve bidder in their place. Reason: To achieve the best financial consideration for the disposal of this surplus asset and enable development on a currently vacant property. ( i ) That the sale of Ashbank to Anchor Housing Trust (Anchor), as the highest net financial bidder, be approved. (ii) That Bidder 1 be retained as a reserve bidder and that, should Anchor fail to complete the purchase of Ashbank in a timely manner, authority be delegated to the Director of Economy & Place to agree its disposal to the reserve bidder in their place. Reason: To achieve the best financial consideration for the disposal of this surplus asset and enable development on a currently vacant property.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 6 pages

Summary

1. This report seeks an Executive decision to dispose of the former council office at Ashbank, 1 Shipton Road to the highest financial bidder.

Recommendations

2. The Executive is asked to

a) Approve the sale of Ashbank to Anchor Housing Trust (Anchor) as the highest net financial bidder.

b) To retain Bid 1 as a reserve bidder, should Anchor Housing Trust fail to complete the purchase of Ashbank in a timely manner. That authority be delegated to the Director of Economy and Place to agree the disposal to the reserve bidder in their place.

Reason: To achieve the best financial consideration for the disposal of this surplus asset and enable development on a currently vacant property.

Background

3. The property is a former Council office building, which was vacated in April 2013 when the new Council office accommodation was opened at West Offices. A plan of the site is included at annex 1. 4. The buildings are comprised of a late Victorian detached house fronting Shipton Road with 1970’s side extensions. To the rear are sunken gardens and a gravelled car park. The site area extends to 0.8 acres.

5. On 22nd November 2005 the Executive approved the sale of Ashbank as part of the Administrative Accommodation Project – Business Case. The anticipated disposal value was £1,250,000. However, this valuation was predicated upon the demolition of the existing building and therefore the development of an unencumbered site.

6. The property was vacated in April 2013 and work commenced to prepare the property for sale. Early engagement with planning colleagues soon identified that the existing villa and sunken garden could not be demolished and needed to be retained. This meant that there was no access to the rear of the site. This brings significant limitations on the development potential of the site, which impacted upon the potential sale value.

7. In order to maximise the potential value of the site, a planning permission was agreed in Sept 2013 for a residential conversion and a development to the rear. In September 2014, following extensive negotiations, an option agreement was entered into with Anchor Housing Trust who own the neighbouring property called ‘Barleyfields’. This “Option” enables the Council to exercise the right of access in return for a share of the resulting uplift in value. The right will be passed on to the new owner on completion of the sale. The option provides a right of access, which increases the capital value of Ashbank.

8. In the Autumn of 2017 the site was marketed and attracted bids from six developers. Three of these bids were unconditional, meaning they were not dependent and subject to, for example, securing planning permission. The highest bid (conditional upon planning) was £1.8 million from Anchor and as such Anchor were identified as preferred bidder.

9. The £1.8 million bid from Anchor was provided subject to planning and Anchor had based their bid on a 4 storey independent living scheme for older people. However when Anchor sought pre application advice on their development proposal they were asked to reconsider their scheme and reduce the height of the proposed development.

10. Anchor subsequently submitted a revised bid based on a smaller scheme. This bid was not received until the beginning of June 2018 and was lower than their initial one. In view of this it was decided to give the under bidders the opportunity to resubmit revised offers with a closing date of 6th July 2018. 11. A full list of the offers received, are set out in the summary attached at annex 2. A full list of bidders is set out in confidential annex 4. Annex 2 sets out the bids and indicates both the gross value of the offers and then the net value once the cost of exercising the option agreement has been deducted.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Ashbank site planAppendix 1 1 pages Download
PDF
Summary of BidsAppendix 2 1 pages Download
PDF
Ashbank: One Planet Impact AssessmentAppendix 3 6 pages Download
PDF
Disposal of Ashbank: No. 1 Shipton Road, YorkReport 6 pages DownloadRead as text

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies