Executive, Thursday 30 August 2018 at 5.30pm

York Central Update - Western Access

Agreed Executive 2 papers

Executive agreed this item on Thursday 30 August 2018. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

( i ) That the route of the York Central Access road, bridge and spine road be agreed as set out in Annex 3, and that detailed planning applications for these be submitted in the autumn. (ii) That approval be given to repossess the land reserved in the Millennium Green lease, to facilitate the access road onto York Central. (iii) That a long lease be granted of a plot of replacement land on the other side of the Holgate Beck, to provide long term replacement for the reserved land and to undertake minor improvement works to this land as agreed with the Millennium Green Trust (MGT). (iv) That a licence be obtained from the MGT permitting use of the area of land required to facilitate the construction of the bridge and that this land be landscaped prior to returning it to the MGT on completion of the works. (v) That approval be given to offer MGT temporary use of alternative City of York Council owned land adjacent to the Millennium Green during the period of the licence. (vi) That a compensatory payment of £375k be made to the MGT, to reflect the disturbance to the Millennium Green and enable the trustees to provide for the long term maintenance to the Millennium Green, of which £300k will be conditional upon planning permission. (vii) That further support to a maximum of £25k be provided to the MGT for their legal and technical support costs. (viii) That embankment land to the west of Severus Bridge be appropriated for the use of the Highway, in order to provide an additional pedestrian and cycle deck across the railway. (ix) That approval be given to undertake detailed design work for the key site infrastructure outlined in the report, including the access bridge and the spine road, and the National Railway Museum (NRM) rail link. (x) That further funding be sought from the West Yorkshire Combined Authority (WYCA) and York, North Yorkshire & East Riding (YNYER) Local Enterprise Partnerships (LEPs) to fund the detailed design of the first phase infrastructure through to construction commencement. (xi) That a further £2,390k funding from the Economic Infrastructure Fund (EIF)be committed to fund the project through to March 2019. (xii) That, in the eventuality that WCYA or YNYER grant funding is forthcoming, the grant be used to reduce the level of EIF support required. (xiii) That a further report be received in November with a detailed financial plan for the delivery of York Central, including analysis of potential Enterprise Zone backed council borrowing, in order to establish a budget for delivery of York Central infrastructure. (xiv) That a further report be received in January 2019 which will: a) set out a partnership agreement with the York Central Partnership to formalise the relationship and the financial agreement between the partners and b) seek approval to draw down funds and commence construction of the access road and bridge. Reason: To ensure the early delivery of a new access route to York Central ... ( i ) That the route of the York Central Access road, bridge and spine road be agreed as set out in Annex 3, and that detailed planning applications for these be submitted in the autumn. (ii) That approval be given to repossess the land reserved in the Millennium Green lease, to facilitate the access road onto York Central. (iii) That a long lease be granted of a plot of replacement land on the other side of the Holgate Beck, to provide long term replacement for the reserved land and to undertake minor improvement works to this land as agreed with the Millennium Green Trust (MGT). (iv) That a licence be obtained from the MGT permitting use of the area of land required to facilitate the construction of the bridge and that this land be landscaped prior to returning it to the MGT on completion of the works. (v) That approval be given to offer MGT temporary use of alternative City of York Council owned land adjacent to the Millennium Green during the period of the licence. (vi) That a compensatory payment of £375k be made to the MGT, to reflect the disturbance to the Millennium Green and enable the trustees to provide for the long term maintenance to the Millennium Green, of which £300k will be conditional upon planning permission. (vii) That further support to a maximum of £25k be provided to the MGT for their legal and technical support costs. (viii) That embankment land to the west of Severus Bridge be appropriated for the use of the Highway, ... view the full minutes text for item 30.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 15 pages

Recommendations

6. Executive is asked :-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Executive Annexes 1-3 -compressedAppendix 4 pages Download
PDF
York Central Update: Western AccessReport 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Central Update - Western AccessThis decision
  2. York Central Mayoral Development Zone (5:02pm)Agreed
  3. York Central Land Disposal (5:20pm)Approved
  4. York Central Mayoral Development Zone (17:54)Decided
  5. York Central Update (5.38 pm)Noted
  6. York Central Update (5.38 pm)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies