Directorate of Economy & Place Transport Capital Programme - 2018/19 Monitor 1 Report
ApprovedExecutive4 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 25 October 2018. Below is the council's own wording, with the papers it was decided on.
( i ) That the amendments to the 2018/19 Economy & Place Transport Capital Programme be approved. (ii) That the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive, be noted Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme. (i) That the amendments to the 2018/19 Economy & Place Transport Capital Programme be approved. (ii) That the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive, be noted Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 7 pages
Recommendations
2. The Executive Member is asked to: 1) Approve the amendments to the 2018/19 Economy & Place Transport Capital Programme.
2) Note the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive.
Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Background
3. The Economy & Place Transport Capital Programme budget for 2018/19 was confirmed as £35,345k at Budget Council on 22 February 2018. The budget was then increased to £37,882k in July 2018 when the Executive Member was presented with the Consolidated Capital Programme, which included all schemes and funding that had carried over from 2017/18.
4. Following amendments approved at the Corporate Monitor 1 report to the 30 August Executive meeting, the budget for the 2018/19 Transport Capital Programme was reduced to £23,886k, which includes funding from the Local Transport Plan (LTP) grant, the Better Bus Area grant, grant funding from the government’s Office of Low Emission Vehicles, and council resources including the Built Environment Fund.
5. The budget also includes funding from various external sources following successful bids by the council, including the Low Emission Bus Scheme grant, the West Yorkshire City Connect grant, the National Productivity Investment Fund, and the West Yorkshire Transport Fund.
6. The current spend and commitments to 31 August 2018 is £8,451k, which is in line with the expected spend profile, as the majority of expenditure is programmed for the later part of 2018/19.
2018/19 Major Schemes
7. The allocation for the Low Emission Bus Scheme includes £200k match funding from the council for infrastructure improvements at the Park & Ride sites for the new electric buses. As this funding is not required in 2018/19, it is proposed to reduce the allocation for this scheme to £3.3m and include the match funding in the 2019/20 Transport Capital Programme.
8. The following changes to the allocations for the Outer Ring Road Upgrades and York Central Access schemes were approved at the Corporate Capital Programme Monitor 1 report to 30 August Executive. These schemes are funded through the West Yorkshire Transport Fund.
9. The allocation for the Outer Ring Road Upgrades scheme has been reduced to £5,875k, and £3,573k funding has been slipped to 2019/20. This will allow completion of the Wetherby Road roundabout upgrade scheme in 2018/19, the start of work on the Monks Cross roundabout upgrade scheme in early 2019, and fund feasibility and initial design work on the remaining roundabout upgrades in 2018/19.
10. The allocation for the York Central Access scheme has been reduced to £2,169k, and £10,518k funding has been slipped to 2019/20. The outline planning application for the site has now been submitted, and the new access road will be constructed in 2019/20. 2018/19 Transport Schemes 11. A review of the current programme has identified schemes where the allocations need to be amended to reflect scheme progress and updated cost estimates.
12. The allocation for Park & Ride Upgrades has been increased to fund additional work to improve fencing and security at Poppleton Bar, as part of the scheme to install height barriers at the car parks within the Park & Ride sites.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.