That the proposed Economy and Place Transport Capital Programme for 2019-20 be approved. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme. That the proposed Economy and Place Transport Capital Programme for 2019-20 be approved. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 8 pages
Decision Session - Executive Member for 14 March 2019 Transport and Planning
Report of the Corporate Director of Economy & Place
Directorate of Economy & Place 2019/20 Transport Capital Programme
Summary 1. This report sets out the Economy & Place Transport Capital Programme as agreed by Council on 28 February 2019.
2. It provides further detail on the split of funding for the Local Transport Plan.
Recommendations 3. The Executive Member is asked to approve the proposed programme for 2019/20.
Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Background 4. Following approval at Full Council on 28 February 2019, the Transport Capital Budget for 2019/20 has been confirmed as £56,856k. Details of the budget are shown in Annex 1 to this report.
5. The approved budget includes funding from the Local Transport Plan (LTP) grant, the Clean Bus Technology grant, the Better Bus Fund, grant funding from the government’s Office of Low Emission Vehicles (OLEV), and council resources including the Built Environment Fund. 6. The budget also includes significant funding from various external sources following successful bids by the council, including Department for Transport, West Yorkshire City Connect Grant, the York & North Yorkshire Local Enterprise Partnership (LEP), the National Productivity Investment Fund, and the West Yorkshire Transport Fund.
7. The allocations within the Major Schemes block will deliver a significant programme of improvements to the city’s infrastructure. Funding for these schemes has been secured from several external funding sources, with contributions from the council’s capital budgets as agreed at Full Council in February 2019.
8. The City Centre Access & Security scheme will provide permanent measures to improve security in the City Centre Priority 1 area (Parliament Street and Coney Street), following the installation of temporary measures (removable bollards and other vehicle restrictions) in autumn 2018. It is expected that the first phase will be installed in summer 2019, with the remainder of the work planned for January-March 2020.
9. The council agreed to implement a Clean Air Zone in York following the report to 17 January 2019 Executive, and have allocated £1.64m of council funding to establish a grant fund for bus operators. This grant fund will allow operators retro-fit equipment to bus exhausts to meet Euro VI standards for air quality.
10. The funding for Scarborough Bridge Footbridge scheme is allocated for improvements to pedestrian and cycle facilities on the approaches to the new footbridge, as agreed in the 2018/19 Monitor 2 report to the December 2018 Decision Session. Work has been carried out in 2018/19 to develop schemes for implementation in 2019/20, including improvements for cyclists crossing Bootham and continuing along St Mary’s/ Marygate Lane to access the riverside paths.
11. The Smarter Travel Evolution Programme (STEP) is funded by the National Productivity Investment Fund, and aims to implement real- time monitoring and associated infrastructure to allow York to prepare for future transport measures such as connected and autonomous vehicles. 12. The programme of upgrades to Outer Ring Road roundabouts will continue in 2019/20, with work expected to start on site at the Monks Cross Roundabout in April 2019. Feasibility work has been carried out in 2018/19 on the proposed upgrades at the Clifton Moor and Wigginton Road Roundabouts, and is being progressed through public consultation which will be followed by detailed design in early 2019, with work expected to start on site in autumn/ winter 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.