Directorate of Economy & Place Transport Capital Programme - 2018/19 Monitor 2 Report

Approved Executive 5 papers

Decision Session - Executive Member for Transport - Expired approved this item on Thursday 20 December 2018. Below is the council's own wording, with the papers it was decided on.

Item60

Resolved

i) That the amendments to the 2018/19 Economy & Place Transport Capital Programme be approved. ii) That the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive, be noted. iii) That the proposed improvements to cycle routes on the approaches to the new Scarborough Bridge footbridge be approved (with the St. Mary’s ramp allocation increased to £45k) to allow the schemes to be implemented as part of the footbridge replacement scheme. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme. i) That the amendments to the 2018/19 Economy & Place Transport Capital Programme be approved. ii) That the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive, be noted. iii) That the proposed improvements to cycle routes on the approaches to the new Scarborough Bridge footbridge be approved (with the St. Mary’s ramp allocation increased to £45k) to allow the schemes to be implemented as part of the footbridge replacement scheme. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 8 pages

Decision Session – Executive Member for 20 December 2018 Transport and Planning

Report of the Corporate Director of Economy & Place

Directorate of Economy & Place Transport Capital Programme – 2018/19 Monitor 2 Report

Summary 1. This report sets out progress to date on schemes in the 2018/19 Economy & Place Transport Capital Programme, and proposes adjustments to scheme allocations to align with the latest cost estimates and delivery projections.

Recommendations 2. The Executive Member is asked to:

i. Approve the amendments to the 2018/19 Economy & Place Transport Capital Programme. ii. Note the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive. iii. Approve the proposed improvements to cycle routes on the approaches to the new Scarborough Bridge footbridge, to allow the schemes to be implemented as part of the footbridge replacement scheme.

Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme. Background

3. The Economy & Place Transport Capital Programme budget for 2018/19 was confirmed as £35,345k at Budget Council on 22 February 2018. The budget was then increased to £37,882k in July 2018 when the Executive Member was presented with the Consolidated Capital Programme, which included all schemes and funding that had carried over from 2017/18. Further amendments were made at the Monitor 1 report in October 2018.

4. Following these amendments, the current budget for the 2018/19 Transport Capital Programme is £23,024k, which includes funding from the Local Transport Plan (LTP) grant, grant funding from the government’s Office of Low Emission Vehicles, developer funding, and council resources including the Built Environment Fund.

5. The budget also includes funding from various external sources following successful bids by the council, including the Low Emission Bus Scheme grant, the West Yorkshire City Connect grant, the National Productivity Investment Fund, and the West Yorkshire Transport Fund.

6. The current spend and commitments to 30 November 31 October 2018 is £11,944k, which is in line with the expected spend profile, as the majority of expenditure is programmed for the final quarter of 2018/19.

2018/19 Major Schemes

7. Work started on the Scarborough Bridge footbridge replacement scheme in October. Work to construct the ramps and embankment is ongoing, and the new footbridge will be installed in February 2019. It is proposed to reduce the allocation for this scheme to £3,600k and slip the remaining funding to 2019/20 to fund the improvements to pedestrian and cycle facilities on each side of the new footbridge. A summary of the proposed route improvement schemes is included in Annex 4 to this report.

8. It is proposed to reduce the allocation for the Smarter Travel Evolution Programme to £475k in 2018/19 and slip the remaining funding to 2019/20, as the majority of the planned improvements to on-street technology and communications equipment will be carried out in 2019/20.

9. The main works for the A1237/ Wetherby Road Roundabout upgrade scheme are now substantially complete, following the completion of the resurfacing work in November 2018, and the remaining landscaping and drainage works will be completed by early 2019. Site clearance for the construction of the A1237/ Monks Cross roundabout will commence in January 2019 with the main construction work starting later in the spring. The later start date for the main works means that the funding requirement will need to be re-profiled. It is proposed to slip £775k of funding for this scheme to 2019/20.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Appendix 2Appendix 2 1 pages Download
PDF
Appendix 3Appendix 3 1 pages Download
PDF
Appendix 4Appendix 4 2 pages Download
PDF
Directorate of Economy & Place Transport Capital Programme: 2018/19 Monitor 2 ReportReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. Directorate of Economy & Place Transport Capital Programme - 2018/19 Monitor 2 ReportThis decision
  2. Directorate of Economy & Place Transport Capital Programme - 2020/21 Consolidated ReportApproved
  3. Directorate of Economy & Place Transport Capital Programme - 2019/20 Monitor 2 ReportApproved
  4. Directorate of Economy & Place Transport Capital Programme - 2019/20 Monitor 1 ReportApproved
  5. Directorate of Economy & Place Transport Capital Programme - 2019/20 Consolidated ReportApproved
  6. Directorate of Economy & Place 2019/20 Transport Capital ProgrammeApproved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies