City of York Council
Executive, Thursday 14 February 2019 at 5.30pm

The Guildhall Redevelopment Tender Evaluation & Project Business Plan Appraisal

Noted Executive 5 papers

Executive noted this item on Thursday 14 February 2019. Below is the council's own wording, with the papers it was decided on.

Item105

Resolved

( i ) That the additional construction costs necessary to address the structural instability of the Guildhall and to access the riverside site, as set out in paragraph 21 of the report, be noted. (ii) That the additional costs arising due to inflation and contingency, as set out in paragraph 21, be noted. (iii) That the 250 additional jobs with a Gross Value Added economic impact (GVA) of £117m over 5 years be noted. (iv) That the redevelopment of the Guildhall at an additional cost of £7.372m, funded from prudential borrowing identified in the 2019/20 capital budget report, be approved. (v) That the updated business case for the scheme be approved. (vi) That it be agreed to proceed to the award of a contract to Bidder B as the construction contractor for the Guildhall project and to delegate authority to the Director of Economy & Place, in consultation with the Assistant Director of Legal & Governance or his delegated officers, to take such steps as are necessary to enter into the contract and, subject to contract, to commence the construction works. (vii) That approval be given to seek tenants for the commercial space to maximise income to the council and that authority be delegated to the Director of Economy & Place, in consultation with the Executive Leader (incorporating Finance & Performance) to agree the length of the lease(s). Reason: To ensure the future viability and effective re-use of the Guildhall as one of the city’s most significant historic buildings. ( i ) That the additional construction costs necessary to address the structural instability of the Guildhall and to access the riverside site, as set out in paragraph 21 of the report, be noted. (ii) That the additional costs arising due to inflation and contingency, as set out in paragraph 21, be noted. (iii) That the 250 additional jobs with a Gross Value Added economic impact (GVA) of £117m over 5 years be noted. (iv) That the redevelopment of the Guildhall at an additional cost of £7.372m, funded from prudential borrowing identified in the 2019/20 capital budget report, be approved. (v) That the updated business case for the scheme be approved. (vi) That it be agreed to proceed to the award of a contract to Bidder B as the construction contractor for the Guildhall project and to delegate authority to the Director of Economy & Place, in consultation with the Assistant Director of Legal & Governance or his delegated officers, to take such steps as are necessary to enter into the contract and, ... view the full minutes text for item 105.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1. The Guildhall is one of the city’s most prestigious and historically significant assets and was for many years the centre of the council’s democratic, civic and managerial activity in the city. When the council consolidated its office provision into West Offices in 2013, the council initiated a review of the future of the Guildhall, with a clear commitment to giving the building a new and sustainable lease of life for the benefit of the city and its residents.

2. The Guildhall has suffered from decades of underinvestment. The last significant investment was to repair the Guildhall following the World War II bombing in 1942, during the Baedeker raids. The restoration was completed in 1960 but, without further investment, a backlog of major repairs and maintenance issues have accrued. Detailed investigations have also revealed further underlying structural defects which, if not addressed, will eventually lead to the disintegration of parts of the Guildhall. This process of decline needs immediate attention to protect such an important heritage building.

3. This report sets out the conclusion of the complex process of review, assessment, analysis, specification, design, costing and procurement, in order to give the Guildhall a secure future and deliver 250 additional jobs with a GVA (Gross Value Added - economic growth impact) of £117m over 5 years. The restoration will bring the historic Guildhall back into active commercial and civic use and open it up to the public.

4. The report outlines a comprehensive scheme to refurbish and redevelop the Guildhall complex and generate income of c£848k per annum. The scheme will secure its long-term future as office and business space with democratic, civic and community space, supported by a cafe, new public riverside space and a riverside restaurant. The proposals include significant structural works to address the stability of the North Annex tower, replacement roofs for the Guildhall and the council chamber and complete renewal of services. The installation of a River Water Source Heat pump will bring significant environmental benefits and reduced running costs. The new and refurbished accommodation will offer new opportunities to support local businesses and increase public access to this historic building.

5. The commercial focus of the scheme will reflect the original use of the Guildhall, supporting local business growth and entrepreneurs. The report sets out proposals for a Guildhall offering:

 Essential works to address the structural failures to the north tower to avoid collapse and replacement of roofs, all to strict conservation standards.  High quality office and business space to support our economy.  Bringing the medieval Guildhall space into more active public use with significantly improved facilities and amenities, including under floor heating, improved access / circulation, adjacent foyer space, cloaks / toilets provision and a cafe/bar, with an increase to its licensed capacity.  Publicly accessible riverside space  A high quality riverside restaurant  Ongoing use for democratic and civic events

6. The paper sets out a comprehensive update of the business case for the scheme in the context of consideration of alternative options and also sets out the results of the recently completed procurement of a construction company to undertake the extensive restoration and construction works to the Guildhall. Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GH site planAppendix 1 258 KB Download
PDF
Images of DamageAppendix 2 4.2 MB Download
PDF
Guildhalll Annex 5- Options asessment long listAppendix 251 KB Download
PDF
The Guildhall Redevelopment Tender Evaluation & Project Business Plan AppraisalReport 200 KB DownloadRead as text
PDF
Appendix 3Appendix 3 5.9 MB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
IG
Councillor Ian GilliesChair, present
KA
Councillor Keith AspdenCommittee Member, present
NA
Councillor Nigel AyreCommittee Member, present
JB
Councillor Jenny BrooksCommittee Member, apologies
PD
Councillor Peter DewCommittee Member, apologies (on leave)
KM
Councillor Keith MyersCommittee Member, apologies
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies