Capital Budget 2019/20 to 2023/24 (formerly Capital Programme 2019/20 and 2023/24)

Agreed Executive 3 papers

Executive agreed this item on Thursday 14 February 2019. Below is the council's own wording, with the papers it was decided on.

Item115

Resolved

Recommended: That Council: (i) Agree to the revised capital programme of £579.762m reflecting a net overall increase of £185.898m , as set out in table 13 at paragraph 92 of the report and in Annex A, key elements of which include: · New schemes funded by prudential borrowing totalling £28.960m as set out in table 3 and summarised in table 13. · New schemes funded by a combination of Prudential borrowing and external funds of £28.7m, as set out in table 4 and summarised in table 13; · Extension to existing schemes of £7.372m funded by prudential borrowing, as set out in table 5 and summarised in table 13; · Extension of prudential borrowing funded Rolling Programme schemes totalling £6.903m, as set out in table 6 and summarised in table 13; · Extension of externally funded Rolling Programme schemes totalling £7.941m, as set out in table 7 and summarised in table 13; · An increase in HRA funded schemes totalling £106.022m, funded from a combination of HRA balances / Right to Buy receipts, as set out in table 8 and summarised in table 13. (ii) Note that the total increase in council borrowing as a result of new schemes being recommended for approval, the details of which are considered within this report and the Financial Strategy report, is £46.385m. (iii) Approve the full re-stated programme, as set out in table 13 and summarised in Annex B, totalling £579.762m and covering the financial years 2019/20 to 2023/24. Reason: In accordance with the statutory requirement to set a capital budget for the forthcoming financial year.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1. This report sets out the Capital Strategy for 2019/20 to 2023/24, and in particular sets out new capital schemes.

2. The Council Plan for 2015-19 was formally approved by Full Council on Thursday 8 October 2015 following consultation with residents, businesses and staff, based on our statutory responsibilities and the priorities of our administration. The plan is built around three key priorities:

 a prosperous city for all - where local businesses can thrive and residents have good quality jobs, housing and opportunities  a focus on frontline services - to ensure all residents, particularly the least advantaged, can access reliable services and community facilities  a council that listens to residents - to ensure it delivers the services they want and works in partnership with local communities

3. As set out within this report and the Revenue Strategy report also on this agenda, the budget reflects significant investment in a number of critical areas, with a focus on frontline services such as highways, housing, schools, drainage and street lighting, alongside investment in developing the economy of York through major regeneration schemes. This report sets out £185.898m of new investment over the 5 year period, of which £33.491m is externally funded, £106.022m is met from the Housing Revenue Account, with £46.385m to be funded by Council Borrowing. The Council Key priority areas of investment include:

 Housing - new investment of £106.022m over the next 5 years, £96.450m of which relates to the Local Authority Homes New Build Project  Transport schemes – Increased investment of £35.055m over the next 5 years including areas such as the Clean Air Zone, York Outer Ring Road Dualling (£28m) and the Local transport plan road safety scheme.  Highways - Increased investment of £13.777m over the next 5 years  Guildhall – Increased investment of £7.372m  Information Technology Development – Increased investment of £2.470m  Schools Building, Mechanical & Electrical work – Increased investment of £5.970m  Disabled Facilities Grants – Increased investment of £5.019m  Libraries – Increased investment of £4.3m

4. It should be noted that a number of other major schemes not considered in detail within this report will be brought forward as individual reports to Members, including the York Castle Museum Delivery Phase, York Castle Gateway, Guildhall, City Centre Access Measures and York Central, as set out at paragraphs 93 – 110.

Recommendations

5. The Executive is requested to recommend that Council:  Agree to the revised capital programme of £579.762m that reflects a net overall increase of £185.898m (as set out in paragraph 89 table 13and in Annex A). Key elements of this include: o New Schemes funded by Prudential borrowing totalling £28.960m as set out in tables 3 and summarised in table 13 o New Schemes funded by a combination of both Prudential borrowing and external funds of £28.7m as set out in table 4 and summarised in table 13; o Extension to existing schemes of £7.372m funded by Prudential borrowing as set out in table 5 and summarised in table 13; o Extension of prudential borrowing funded Rolling Programme schemes totalling £6.903m as set out in table 5 and summarised in table 13; o Extension of externally funded Rolling Programme schemes totalling £7.941m as set out in table 6 and summarised in table 13; o An increase in HRA funded schemes totalling £106.022m funded from a combination HRA balances/Right to Buy receipts as set out in table 7 and summarised in table 13

 Note the total increase in Council borrowing as a result of new schemes being recommended for approval is £46.385m the details of which are considered within this report and the financial strategy report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget 2019/20 to 2023/24 (formerly Capital Programme 2019/20 and 2023/24)Report 487 KB DownloadRead as text
PDF
Incl Guildhall: Annex A CRAM Forms 1920Appendix 317 KB Download
PDF
Incl Guildhall Annex B Capital Programme 1920: 2324Appendix 131 KB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
IG
Councillor Ian GilliesChair, present
KA
Councillor Keith AspdenCommittee Member, present
NA
Councillor Nigel AyreCommittee Member, present
JB
Councillor Jenny BrooksCommittee Member, apologies
PD
Councillor Peter DewCommittee Member, apologies (on leave)
KM
Councillor Keith MyersCommittee Member, apologies
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. Capital Budget 2019/20 to 2023/24 (formerly Capital Programme 2019/20 and 2023/24)This decision
  2. Capital Budget 2026/27 to 2030/31Agreed
  3. Capital Budget 2025/26 to 2029/30 (17:41)Agreed
  4. Capital Budget 2024/25 to 2028/29Agreed
  5. Capital Budget 2023/24 to 2027/28 (18:40)Agreed
  6. Directorate of Place 2022/23 Transport Capital Programme – Budget ReportApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open