Education, Children and Young People's Capital Programme: Proposed School Maintenance Schemes and SEND Facilities Expansion and Improvement Schemes 2019/20

Noted Executive 2 papers

Executive noted this item on Monday 18 March 2019. Below is the council's own wording, with the papers it was decided on.

Item128

Resolved

(i) That the resources available in the Children, Education & Communities (CEC) capital programme for maintenance and building work at schools, and for Special Educational Needs and Disability (SEND) expansion, be noted. (ii) That the two specific Maintenance schemes, at a budgeted individual cost of £250k and £300k respectively, be approved. (iii) That the Applefields SEND scheme, at a budgeted cost of £270k, be approved. (iv) That the Maintenance schemes to be developed from the estimated available resource within the 2019/20 capital programme be approved, subject to final affordability once overall funding and detailed cost estimates are available. (v) That approval of expenditure on individual schemes be delegated to appropriate Officers. Reasons: (i) To maximise the programme of maintenance within the maintained school estate, dealing with the most urgent issues for 2019/20. (ii) To enable work to be carried out at Applefields School as part of the Inclusion Review, to better provide for the education of its pupils in the forthcoming school years. ( i ) That the resources available in the Children, Education & Communities (CEC) capital programme for maintenance and building work at schools, and for Special Educational Needs and Disability (SEND) expansion, be noted. (ii) That the two specific Maintenance schemes, at a budgeted individual cost of £250k and £300k respectively, be approved. (iii) That the Applefields SEND scheme, at a budgeted cost of £270k, be approved. (iv) That the Maintenance schemes to be developed from the estimated available resource within the 2019/20 capital programme be approved, subject to final affordability once overall funding and detailed cost estimates are available. (v) That approval of expenditure on individual schemes be delegated to appropriate Officers. Reasons: ( i ) To maximise the programme of maintenance within the maintained school estate, dealing with the most urgent issues for 2019/20. (ii) To enable work to be carried out at Applefields School as part of the Inclusion Review, to better provide for the education of its pupils in the forthcoming school years.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 6 pages

Executive 18 March 2019

Report of the Corporate Director of Children, Education and Communities and the Director of Customer and Corporate Services

Education, Children and Young People’s Capital Programme: Proposed School Maintenance Schemes and SEND Facilities Expansion and Improvement Scheme 2019/20

Summary 1. The purpose of this report is to:  inform the Executive of the funding available in the school maintenance programme in the financial year 2019/20  seek approval for the proposed programme of work and the two specific schemes budgeted at £250k and £300k.

 seek approval for a specific scheme at Applefields School at a budgeted cost of £270k, to be funded from the SEND Expansion and Improvement of Facilities Scheme.

Recommendations 2. The Executive is recommended to:  note the resources available in the CEC Capital Programme for maintenance and building work at schools, and for SEND expansion.

 approve the two specific Maintenance schemes at a budgeted individual cost of £250k and £300k.

 approve the Applefields SEND scheme at a budgeted cost of £270k.

 approve the Maintenance schemes to be developed from the estimated available resource within the 2019/20 capital programme, subject to final affordability once overall funding and detailed cost estimates are available

 Members are requested to delegate approval of expenditure on individual schemes to Officer level.

Reason:

 to maximise the programme of maintenance within the maintained school estate, dealing with the most urgent issues for 2019/20

 enable work to be carried out at Applefields School as part of the Inclusion Review to better provide for the education of its pupils in the forthcoming school years.

Background 3. The current approved Education and Children’s Capital programme has a budget of £20.799m in 2019/20 (following approval of the Capital Budget 2019/20 - 2023/24 at Budget Council on 28th February 2019).

4. The individual schemes being considered in this report will be funded from four overall schemes within this programme. These are DfE Maintenance, Schools Essential Building Work, Schools Mechanical and Electrical Work, and the scheme for the Expansion and Improvement of Facilities for Pupils with SEND.

Consultation 5. All of the maintenance schemes considered in this report have been, or will be, subject to extensive consultation with governing bodies, key partner agencies, local councillors and residents in the locality of the individual schemes during development.

6. The Applefields School proposals have been discussed and agreed by the Inclusion Review Group which is a group made up of Officers and Head teachers from across the City.

Analysis Capital Maintenance and Building and Electrical Work 7. Capital Maintenance grant funding is allocated annually to local authorities by the Department for Education (DfE) for the improvement of LA maintained school buildings and children’s centres. The 2019/20 allocations have not yet been announced. 8. For Academy schools (non-maintained), the LA is not responsible for maintaining these buildings. The academies have to apply direct for funding from the Education Funding Agency.

9. The current approved maintenance programme contains a budget of £1.536m for 2019/20. This figure includes £200k for previous years scheme retentions and final costs, plus an assumed underspend of £500k on 2018/19 schemes which has been re- profiled into 2019/20 at Monitor 3.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Executive Capital Maintenance March 2019Appendix A 2 pages Download
PDF
Education, Children and Young People's Capital Programme: Proposed School Maintenance Schemes and SEND Facilities Expansion and Improvement Schemes 2019/20Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. Education, Children and Young People's Capital Programme: Proposed School Maintenance Schemes and SEND Facilities Expansion and Improvement Schemes 2019/20This decision
  2. Children, Young People and Education Executive Member Decision Session held on 14 January 2025Approved
  3. 2022/23 Third Finance & Performance Monitoring Report - Children, Education & Communities (6.04 pm)Noted
  4. REACH Progress Report to the Children, Education and Communities Policy and Scrutiny Committee (6.12 pm)Noted
  5. Quarterly Update Report of the Corporate Director of Children Services and Education [10.37]Decided
  6. 2022/23 Second Quarter Finance Monitoring Report - Children, Education & CommunitiesNoted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies