Executive, Thursday 24 October 2019 at 5.30pm

York Central Update

Approved Executive 2 papers

Executive approved this item on Thursday 24 October 2019. Below is the council's own wording, with the papers it was decided on.

Item55

Resolved

( i ) That Option 1 be approved and £2.275m be committed to progress work on the first phase of infrastructure, up to determination of the RMA, RIBA stage 4 design, with a refined fixed construction cost and submission of the WYTF+ final business case. (ii) That a £1.58m LGF grant be accepted from the North Yorkshire & East Riding (YNYER) Local Economic Partnership (LEP) and £695k be drawn down from the agreed York Central CYC capital budget, to fund this work. Reason: To ensure that appropriate project development progress is maintained towards delivery readiness on the York Central project in preparation for the determination of external grant funding being confirmed. ( i ) That Option 1 be approved and £2.275m be committed to progress work on the first phase of infrastructure, up to determination of the RMA, RIBA stage 4 design, with a refined fixed construction cost and submission of the WYTF+ final business case. (ii) That a £1.58m LGF grant be accepted from the North Yorkshire & East Riding (YNYER) Local Economic Partnership (LEP) and £695k be drawn down from the agreed York Central CYC capital budget, to fund this work. Reason: To ensure that appropriate project development progress is maintained towards delivery readiness on the York Central project in preparation for the determination of external grant funding being confirmed.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 12 pages

Summary

1. The delivery of York Central is a city wide priority. Regeneration of this brownfield site will bring significant economic growth space and new housing, in this central, sustainable location. The importance of York Central is highlighted in the Local Plan, and in the Strategic Economic Plans of both regional Local Enterprise Partnerships. 2. In July 2019 Executive made the commitment to undertake further project development activity, working with the York Central Partnership, to ensure the scheme maintains momentum and is ready to progress into delivery phases when decisions on external grant funding are confirmed. The funding agreed by Executive enabled the appointment of a construction partner to undertake Early Contractor Involvement in developing construction detail for the phase 1 infrastructure.

3. This report provides an update on activity over the period, and sets out options for proceeding with further development activity to maintain momentum and progress towards delivery whilst the announcement of grant funding decisions is still pending.

Recommendations

4. Executive is asked :-

i. To agree Option 1 to commit £2.275m to progress work on the first phase of infrastructure up to determination of the RMA, RIBA stage 4 design with a refined fixed construction cost and submission of the WYTF+ final business case ii. To accept a £1.58m LGF grant from the North Yorkshire & East Riding (YNYER) Local Economic Partnership ( LEP) and drawdown of £695k from the agreed York Central CYC capital budget to fund this work iii. If the YNYER LEP funding is not available then to agree Option 2 to draw down funding of £746k from the agreed York Central capital budget to fund further work through to the determination of the RMA only. Reason: - To ensure that appropriate project development progress can be maintained towards delivery readiness on the York Central project in readiness for the determination of external grant funding being confirmed.

Background

5. York Central is one of the largest brownfield sites in northern England, see plan at Annex 1. The 45ha development site will deliver; up to 2500 new homes, and the potential for 6500 jobs in grade A commercial office space. An enhanced National Railway Museum and the creation of new public spaces and community facilities directly linked to an improved Railway Station are also key project outcomes

6. The council has been instrumental in breaking the deadlock of decades and bringing York Central forward for development. The council has worked positively with partners to ensure that the development will deliver benefits to the people of York, and these will continue to be shaped by extensive public engagement. As the principal conduit for infrastructure funding and through its statutory roles as Local Planning Authority (LPA) and Highways Authority (HA) the council has significant influence and control over key future decisions and will continue to represent the views of the people of York in all partnership discussions. 7. Extensive community engagement was undertaken ahead of the planning process which showed significant support for the scheme despite its many challenges. Previous attempts by the market to bring a scheme forward on this site have floundered and, given the unique risk profile of the site, it will require public sector leadership to bring the site forward for development.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site PlanAppendix 1 1 pages Download
PDF
York Central UpdateReport 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Central UpdateThis decision
  2. York Central Mayoral Development Zone (5:02pm)Agreed
  3. York Central Land Disposal (5:20pm)Approved
  4. York Central Mayoral Development Zone (17:54)Decided
  5. York Central Update (5.38 pm)Noted
  6. York Central Update (5.38 pm)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies