Decision Session - Executive Member for Children Young People and Education noted this item on Tuesday 17 December 2019. Below is the council's own wording, with the papers it was decided on.
That; i. The resources available in the Children, Education & Communities Capital Programme for maintenance and building work at schools be noted. ii. The 16 capital maintenance schemes between £100,000 and £500,000 be approved. iii. The approval of expenditure on individual schemes be delegated to Officer level. Reason: In order to maximise the programme of maintenance within the maintained school estate, dealing with the most urgent issues for 2020/21. That; i. The resources available in the Children, Education & Communities Capital Programme for maintenance and building work at schools be noted. ii. The 16 capital maintenance schemes between £100,000 and £500,000 be approved. iii. The approval of expenditure on individual schemes be delegated to Officer level. Reason: In order to maximise the programme of maintenance within the maintained school estate, dealing with the most urgent issues for 2020/21.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Children Young People and Education, 7 pages
Summary
1. The purpose of this report is to seek approval for 16 proposed capital maintenance schemes with estimated budgets between £100,000 and £500,000.
Recommendations
2. The Executive Member is asked to:
Note the resources available in the CEC Capital Programme for maintenance and building work at schools.
Approve the 16 capital maintenance schemes between £100,000 and £500,000.
Delegate approval of expenditure on individual schemes to Officer level.
Reason:
To maximise the programme of maintenance within the maintained school estate, dealing with the most urgent issues for 2020/21.
Background
3. The LA has a statutory duty under the 1996 Education Act to ensure a sufficient supply of good/outstanding school places in its local area, that the schools can continue to operate and educate children city-wide and as many maintenance issues are addressed as possible each financial year.
4. To ensure this duty is carried out urgent maintenance work has been identified, a programme has been developed and is planned to be delivered within the timescales dictated by the type of work required and school holidays. This means that the majority of the work needs to be ready to go out to tender in February and March 2020.
5. Approval of the 2020/21 capital maintenance programme needs to be in line with the above timescale and the design development process should begin during December 2019.
6. Approval of seven schemes under £100k was given by Directorate Management Team on 28th November 2019.
Consultation
7. All of the maintenance schemes considered in this report have been, or will be, subject to extensive consultation with governing bodies, key partner agencies, local councillors and residents in the locality of the individual schemes during development, when and where appropriate.
Options
8. Option 1: Do Nothing The schemes identified in the capital programme are all essential works. To do nothing increases the risk of school closures and associated risks from depleting condition, health and safety and regulatory issues not being met.
9. Option 2: Prioritise Schemes and use additional funding sources to top up budget
Schemes have been scored and prioritised, any schemes that do not go ahead in 2020/21 will need to be delayed into a future year. The amount of capital maintenance received from Central Government is not sufficient to address all the urgent issues that need to be resolved in schools therefore the use of other funding sources to top up Capital Maintenance such as Section 106, CRAM and Basic Need allows more schemes to go ahead.
Analysis
10. Capital Maintenance grant funding is allocated annually to local authorities by the Department for Education (DfE) for the improvement of Local Authority maintained school buildings and children’s centres. The 2019/20 grant for City of York is £842k. The 2020/21 allocations have not been announced, but based on the 2019/20 allocation we are estimating a figure of £700k.
11. The actual Capital Maintenance grant funding available in 2020/21 is estimated at £1,169k. This figure includes the £700k grant plus an assumed underspend of £469k on 2019/20 schemes which has been re- profiled into 2020/21 at Capital Monitor 3.
12. The other two major funding streams in the programme that are available to fund maintenance work in schools are the Schools Essential Building Work, and Schools Essential Mechanical and Electrical work. The amounts in the programme for 2020/21 within these two streams are £1.828m and £2.298m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Children Young People and Education at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.