City of York Council
Executive, Thursday 20 May 2021 at 5.30pm

School Capital Works - Internal Capital Works at Applefields Special School and Danesgate Pupil Referral Unit

Approved Executive 2 papers

Executive approved this item on Thursday 20 May 2021. Below is the council's own wording, with the papers it was decided on.

Item134

Resolved

(i) That works to complete classroom adaptations at Applefields School by September 2021 and the provision of essential administrative space by September 2022 (Option 3) be approved, and that authority be delegated to the Corporate Director of People (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to procure, award and enter into the resulting construction contracts. Reason: To provide sufficient special school places for children and young people with special educational needs and/or disabilities. (ii) That works to carry out adaptations at Danesgate by September 2022 (Option 3) be approved, and that authority be delegated to the Corporate Director of People (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to procure, award and enter into the resulting construction contracts. Reason: To improve in-city provision for children and young people with SEMH. (i) That works to complete classroom adaptations at Applefields School by September 2021 and the provision of essential administrative space by September 2022 (Option 3) be approved, and that authority be delegated to the Corporate Director of People (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to procure, award and enter into the resulting construction contracts. Reason: To provide sufficient special school places for children and young people with special educational needs and/or disabilities. (ii) That works to carry out adaptations at Danesgate by September 2022 (Option 3) be approved, and that authority be delegated to the Corporate Director of People (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to procure, award and enter into the resulting construction contracts. Reason: To improve in-city provision for children and young people with SEMH.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 14 pages

Summary

1. The report provides details about the programme of capital works needed to address the sufficiency of appropriate specialist school places for children and young people with special educational needs and disabilities. The Executive is asked to approve capital works at Applefields Special School and The Danesgate Community. At Applefields School the works are needed to accommodate a growth in pupil numbers from September 2021. At Danesgate capital works are needed to make adaptations to ensure that the site better meets the needs of children and young people with a primary need of social, emotional and mental health (SEMH). Recommendations – Applefields and Danesgate 2. The Executive is asked to consider:

1) Approval of works to complete classroom adaptations at Applefields School by September 2021. The capital scheme also involves the provision of essential administrative space by September 2022. The Executive is asked to delegate to the Director of People (in consultation with the Director of Governance or her delegated officers) the authority to take such steps as are necessary to procure, award and enter into the resulting construction contracts.

Reason: to provide sufficient special school places for children and young people with special educational needs and/or disabilities. 2) Approval of works to carry out adaptations at Danesgate by September 2022 and to delegate to the Director of People (in consultation with the Director of Governance or her delegated officers) the authority to take such steps as are necessary to procure, award and enter into the resulting construction contracts.

Reason: to improve in-city provision for children and young people with SEMH.

3. The Executive is recommended to approve Applefields - option3, and Danesgate - option 3.

General Background – Applefields and Danesgate 4. As outlined in the report taken to Executive on the 29th November 2018 approval was given to use Special Needs Capital Grant funding to improve SEMH provision at Danesgate. The Special Needs Capital Grant is provided by central government to support the sufficiency of provision for children and young people with special educational needs and/or disabilities (SEND). 5. This paper focuses on two schemes to address the sufficiency of provision for children and young people with SEND. In York we have identified a need to further develop SEMH provision at both Applefields Secondary Special School and at Danesgate. These schemes are currently at detailed design and tender stages and a budget estimate has been established for both schemes.

Background - Applefields

6. As shown in the table below, pupil numbers over the last 4 years have increased. This is in line with the overall growth in numbers of secondary aged pupils. The school are set to see a further increase in pupil numbers from a roll of 178 to 196 in the 2021/22 academic year.

Total Numbers on roll Expected (NOR) NOR 2017-18

2018-19

2019-20

2020-21

2021-22

144 154 165 180 196 7. This growth has seen an increasing number of young people with highly complex needs such as profound and multiple learning difficulties (PMLD), autism and those with the highest level of social and emotional need. To meet these needs the school requires additional space and staff support.

Total pupils PMLD autism SLD/MLD – Enhanced Satellite/ specific Main site Orchard 20-21 180 17 31 71 24 37 21-22 196 22 39 68 27 40

8. The total pupil intake in Year 7 for 2020-21 was 34 and it is projected to be 38 for September 2021, 14 of whom are from mainstream primaries. This compares to 20 pupils leaving the school in July 2021.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
School Capital Works: Internal Capital Works at Applefields Special School and Danesgate Pupil Referral UnitReport 14 pages DownloadRead as text
PDF
View item 134. as HTML 121 KBReport 121 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. School Capital Works - Internal Capital Works at Applefields Special School and Danesgate Pupil Referral UnitThis decision
  2. School Capital Works at Millthorpe and Manor Schools to Accommodate the Expected Demand for Pupils Places from within the Schools' Catchment Area by September 2022Approved
  3. School Capital Maintenance Programme 2020/2021Noted
  4. The Provision of School Places and Allocation of School Capital Budgets 2019-2023 to Address Secondary Place PressuresNoted
  5. Education, Children and Young People's Capital Programme: Proposed School Maintenance Schemes and SEND Facilities Expansion and Improvement Schemes 2019/20Noted
  6. Education, Children & Young People's Capital Programme: Proposed School Maintenance Schemes and Basic Need Programme 2018/19Noted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies