City of York Council
Executive, Thursday 23 July 2020 at 5.30pm

York Central Update

Agreed Executive 3 papers

Executive agreed this item on Thursday 23 July 2020. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

(i) That further funding of £1.96m be committed to cover City of York Council (CYC) project team and consultancy support costs, undertake further essential survey works, and fund an early enabling infrastructure works contract to April / May 2021. (ii) That authority be delegated: a) to the Interim Head of Paid Service, in consultation with the Executive Leader, to take such steps as are necessary to deliver the package of early site enabling works and b) to the Director of Economy & Place, in consultation with the Director of Goverance , to taken such steps as are necessary to enter into the resulting funding agreement. (iii) That authority be delegated to the Interim Head of Paid Service, in consultation with the Executive Leader, to take such steps as are necessary to agree the grant terms with MHCLG for £77.1m of infrastructure funding and to enter into the resulting funding agreement. (iv) That approval be given to procure the further project support consultancy services necessary to for the delivery phase, and that the authority to take such steps as are necessary to procure, award and enter into the resulting contracts be delegated to the Director of Economy & Place, in consultation with the Director of Governance. Reason: To ensure that appropriate progress can be made on project development, focusing on delivery readiness for the first phase of the York Central enabling infrastructure. (v) That approval be given to dispose of the land at Alliance House / Chancery Rise to Network Rail (NR), to facilitate the relocation of rail infrastructure maintenance facilities from the York Central site, with NR to reimburse the council for expenditure incurred by the council in connection with its ownership since 2016, totalling £426,967; the disposal price to be £1 (the same price for which it was purchased by the council from NR in 2016), and to include a restrictive covenant to limit the future use of the land to the purpose agreed in this disposal. Reason: To ensure that York Central is cleared of operational rail activity and made available for redevelopment. (i) That further funding of £1.96m be committed to cover City of York Council (CYC) project team and consultancy support costs, undertake further essential survey works, and fund an early enabling infrastructure works contract to April / May 2021. (ii) That authority be delegated: a) to the Interim Head of Paid Service, in consultation with the Executive Leader, to take such steps as are necessary to deliver the package of early site enabling works and b) to the Director of Economy & Place, in consultation with the Director of Goverance , to taken such steps as are necessary to enter into the resulting funding agreement. (iii) That authority be delegated to the Interim Head of Paid Service, in consultation with the Executive Leader, to take such steps as are necessary to agree the grant terms with MHCLG for £77.1m of infrastructure funding and to enter into the resulting funding agreement. (iv) That approval be given to procure the further project support consultancy services necessary to for the delivery phase, and that the authority to take such steps as are necessary to procure, award and enter into the resulting contracts be delegated to the Director of Economy & Place, in consultation with the Director of Governance. Reason: To ensure that appropriate ... view the full minutes text for item 11.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 15 pages

Summary

1. The delivery of York Central is a city wide priority. Regeneration of this brownfield site will bring significant economic growth space and new housing, in this central, sustainable location. The importance of York Central is highlighted in the Local Plan, and in the Strategic Economic Plans of both regional Local Enterprise Partnerships. York Central will also play a pivotal role in the city wide economic recovery from the Covid 19 pandemic. 2. The council has continued its commitment to York Central all through the Covid 19 lock down and response phase, and has maintained the level of resources allocated to the project due to its strategic importance to long term economic recovery. The delivery of York Central is still a priority objective within our economic strategy and will provide the location for new economic growth space and facilitate the future development of new sustainable business sectors to augment the existing economy.

3. In the March 2020 budget the council received the long awaited news that the Ministry of Housing Communities and Local Government (MHCLG) had agreed to award £77.1m to fund the enabling infrastructure for the site. This is a hugely positive breakthrough that will finally unlock the site.

4. After decades of stalled delivery, the crucial enabling infrastructure works can finally now commence. Ultimately York Central will become a thriving addition to the existing city centre with; new business space, new homes a re-modelled railway station and a transformed National Railway Museum. Movement through the site will benefit from pedestrian and cycle priority with dedicated / segregated routes along the main west to east axis. This route will be well served by Park and Ride / local bus services with an inbound priority Bus Lane. Encompassing all of this, and perhaps most important of all, the new park and urban realm will deliver high quality amenity space for the benefit of all our residents, workers and visitors. Designed to meet best practice standards the landscaping will deliver significant new tree planting and have Sustainable Urban Drainage (SUDs) and biodiversity considerations at its heart. 5. This report provides an update on progress to deliver the scheme, and sets out proposals for proceeding with further development activity to maintain the positive momentum and ensure readiness for delivery whilst we await the confirmation of the conditions of the grant funding.

Recommendations

6. Executive is asked :-

i. To commit further funding of £1.96m to cover CYC project team and consultancy support costs, undertake further essential survey works, and to fund an early enabling infrastructure works contract to April / May 2021. ii. To delegate to the Interim Head of Paid Service in consultation with the Leader the acceptance of the £1.53 million YNYER grant to deliver the package of early site enabling works and to delegate to the Director of Economy and Place, in consultation with the Director of Governance, the authority to take such steps as are necessary to enter into the resulting funding agreement. iii. To delegate to the Interim Head of Paid Service in consultation with the Leader the authority to take such steps as are necessary to agree the grant terms with MHCLG for £77.1m of infrastructure funding and to enter into the resulting funding agreement. iv. To approve the procurement of the further project support consultancy services necessary for the delivery phase, and to delegate to the Director of Economy and Place, in consultation with the Director of Governance, the authority to take such steps as are necessary to procure, award and enter into the resulting contracts.

Reason: To ensure that appropriate project development progress can be maintained, focussing on delivery readiness for the first phase of the York Central enabling infrastructure

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site PlanAppendix 1 1 pages Download
PDF
Chancery Rise LandAppendix 2 1 pages Download
PDF
York Central UpdateReport 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Central UpdateThis decision
  2. York Central Mayoral Development Zone (5:02pm)Agreed
  3. York Central Land Disposal (5:20pm)Approved
  4. York Central Mayoral Development Zone (17:54)Decided
  5. York Central Update (5.38 pm)Noted
  6. York Central Update (5.38 pm)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies