Executive, Thursday 14 January 2021 at 5.30pm

Street Works – Changing from Noticing to a Permitting Scheme

Approved Executive 11 papers

Executive approved this item on Thursday 14 January 2021. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

(i) That Option A be approved and the proposed permit scheme, fee levels and implementation set out in Annexes A, B and F to the report be adopted. (ii) That authority be delegated to the Corporate Director of Housing, Economy & Place, in consultation with the S151 Officer and the Director of Governance or her delegated officers, to implement future changes to the scheme and associated fees. Reasons: · To improve City of York Council’s ability to manage applications to work on its road network, including the ability to refuse applications, enabling the council to better meet its Network Management Duty; · to reduce disruption on the road network and delays for all road users; and · to encourage a greater emphasis on safety on street and road works sites through an enhanced site inspection regime. (i) That Option A be approved and the proposed permit scheme, fee levels and implementation set out in Annexes A, B and F to the report be adopted. (ii) That authority be delegated to the Corporate Director of Housing, Economy & Place, in consultation with the S151 Officer and the Director of Governance or her delegated officers, to implement future changes to the scheme and associated fees. Reasons: · To improve City of York Council’s ability to manage applications to work on its road network, including the ability to refuse applications, enabling the council to better meet its Network Management Duty; · to reduce disruption on the road network and delays for all road users; and · to encourage a greater emphasis on safety on street and road works sites through an enhanced site inspection regime.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1. The aim of this report is to seek approval from the Executive to introduce a permit scheme to govern all utility and highway works activities within City of York Council’s highway network. The introduction of a permit scheme will: a. Support a more pro-active approach to managing street and road works, including the ability to refuse applications;

b. Reduce disruption and delays on the road network;

c. Provide additional funding to support the Street Works function, improving street and road works coordination and safety (as the authority will be able to charge utilities to cover the costs of permits, although authorities may not use their permit schemes to generate surplus revenue);

d. Enable City of York Council to comply with the Department for Transport’s repeated requests that all highway authorities in England move to a permit scheme (letters to City of York Council were dated November 2020 and July 2018).

Recommendations

2. This report recommends the adoption of the permit scheme presented (Option A). Executive are asked to:

Approve the proposed permit scheme and fee levels and its implementation (the Scheme is provided in Annex A, fee levels in Annex B and the proposed team structure in Annex F) and delegate authority to the Corporate Director for Economy and Place to implement future changes to the scheme and associated fees (in consultation with the s151 Officer and the Director of Governance or her delegated officers)

Reason: • To improve CYC’s ability to manage applications to work on its road network, including the ability to refuse applications, enabling the Council to better meet its Network Management Duty; • To reduce disruption on the road network and delays for all road users; and • To encourage a greater emphasis on safety on street and road works sites through an enhanced site inspection regime.

Background 3. The aim of this report is to seek approval from the Executive to introduce a permit scheme to govern all utility and highway works activities within City of York Council’s (CYC) highway network. 4. This report follows feasibility work undertaken in 2019 and a statutory consultation on a proposed permit scheme, in compliance with Regulation 3 of the Traffic Management Permit Scheme (England) Regulations 2007, conducted, which started in August 2020 and closed on 15th October 2020.

5. This report presents an assessment of City of York Council’s options to manage street and road works and makes recommendations for the introduction of a permit scheme to be considered by City of York Council’s Executive in January 2021. 6. If a decision is taken to introduce a permit scheme, the Street Works team will aim to implement this change by April 2021.

7. The implementation of a permit scheme will: • Support a more pro-active approach to managing street and road works, by enabling the authority to better manage applications to work on its road network, including the ability to refuse applications where required; • Reduce disruption and delays on the road network; • Provide additional funding to support the Street Works function, improving street and road works coordination and safety; • Enable City of York Council to respond positively to the letters from the Transport Minister for Roads, Buses and Places, dated November 2020 and the previous letter from the Secretary of State for Transport dated July 2018. Both letters sought the implementation of permit schemes by all highway authorities in England. In November 2020, the DfT indicated that 49 of the local highway authorities in England were now operating or intending to start the operation of a permit scheme (there are 153 local highway authorities in England1).

Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Draft Permit SchemeAppendix A 1.2 MB Download
PDF
Fee LevelsAppendix B 749 KB Download
PDF
Consultation summaryAppendix C 728 KB Download
PDF
ChecklistAppendix D 641 KB Download
PDF
Cost Benefit Analysis SummaryAppendix E 828 KB Download
PDF
Street Works: Changing from Noticing to a Permitting SchemeReport 320 KB DownloadRead as text
PDF
View as HTML (87./2) 183 KBAppendix 183 KB Copy on its way
PDF
View as HTML (87./3) 34 KBAppendix 34 KB Copy on its way
PDF
View as HTML (87./4) 87 KBAppendix 87 KB Copy on its way
PDF
View as HTML (87./5) 42 KBAppendix 42 KB Copy on its way
PDF
View item 87. as HTML 52 KBReport 52 KB Copy on its way

At this meeting

Whole meeting

Who was there

10 of 10 attended
KA
Councillor Keith AspdenChair, present
NA
Councillor Nigel AyreCommittee Member, present
DC
Councillor Denise CraghillCommittee Member, present
IC
Councillor Ian CuthbertsonCommittee Member, present
AD
Councillor Andy D'AgorneCommittee Member, present
KO
Councillor Keith OrrellCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
DS
Councillor Darryl SmalleyCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present
PW
Councillor Paula WiddowsonCommittee Member, present

On this subject at York

Search all
  1. Street Works – Changing from Noticing to a Permitting SchemeThis decision
  2. York Dance Works, 11 Redeness Street, York [18/01935/FULM]Approved
  3. Streetworks PermitsApproved
  4. Works (Vacant), Carmelite Street, York (12/00327/FULM)Approved
  5. Works (Vacant) Carmelite Street, York (08/01906/FULM)Approved
  6. Former Waterworks Engine House, Museum Street, York (08/00115/FUL)Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies