City of York Council
Executive, Thursday 22 April 2021 at 5.30pm

York Central and York Station Gateway Update

Noted Executive 6 papers

Executive noted this item on Thursday 22 April 2021. Below is the council's own wording, with the papers it was decided on.

Item124

Resolved

(i) That the revised infrastructure delivery arrangements, and the subsequent reduction of the capital allocation for York Central to £41.7m to reflect the direct award of £77.1m MHCLG funding and £23.5m WYTF funding direct to Homes England, be noted. (ii) That it be noted that Homes England has agreed to reimburse City of York Council £3.836m of the costs incurred in preparing the site access proposals, Master Plan and initial design work, planning applications and the completion of site preparation works from the capital grant awarded to Homes England by MHCLG, and that this money will be retained to support York Central going forward. (iii) That approval be given to procure Consultancy Design Services, Cost Consultancy and Project Assurance for the York Station Gateway scheme, and that authority be delegated to the Corporate Director of Place (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to procure, award and enter into the resulting contracts. (iv) That the proposed arrangements for the York Central Partnership be approved. (v) That the procurement of technical services to support the process of adoption of the York Central highways infrastructure be agreed and that authority be delegated to the Corporate Director of Place (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to procure, award and enter into the resulting contracts. (vi) That the acquisition of land adjoining Scarborough Bridge to ensure the future availability and improvement of the riverside path be approved, at a cost of £150k from the York Central enabling budget. (vii) That further funding of £900k be committed from the York Central enabling budget to continue to support delivery of the project. This will fund the CYC project team and legal, consultancy support costs to ensure CYC has the capacity to fulfil its Enterprise Zone obligations, prepare the EZ investment business case, seek further investment funding for project enhancements and provide input to the York Central Design panel, support the Leader’s strategic role on the project, and continue to support the partnership’s community engagement and communications work. (viii) That a further report be brought forward on the delivery of remaining infrastructure packages, the future use of Enterprise Zone funding and the use of future Section106 monies. Reason: To enable the successful delivery of the York Central and York Station Gateway schemes. (i) That the revised infrastructure delivery arrangements, and the subsequent reduction of the capital allocation for York Central to £41.7m to reflect the direct award of £77.1m MHCLG funding and £23.5m WYTF funding direct to Homes England, be noted. (ii) That it be noted that Homes England has agreed to reimburse City of York Council £3.836m of the costs incurred in preparing the site access proposals, Master Plan and initial design work, planning applications and the completion of site preparation works from the capital grant awarded to Homes England by MHCLG, and that this money will be retained to support York Central going forward. (iii) That approval be given to procure Consultancy Design Services, Cost Consultancy and Project Assurance for the York Station Gateway scheme, and that authority be delegated to the Corporate Director of Place (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to procure, award and enter into the resulting contracts. (iv) That the proposed arrangements for the York Central Partnership be approved. (v) That the procurement of technical services to support the process of adoption of the York Central highways infrastructure be agreed and that authority be delegated to the Corporate Director of Place (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to procure, award and enter into the resulting contracts. (vi) That the acquisition of land adjoining Scarborough Bridge ... view the full minutes text for item 124.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Site PlanAppendix 1 1 pages Download
PDF
Appendix 2Appendix 2 5 pages Download
PDF
Appendix 3Appendix 3 1 pages Download
PDF
View as HTML (124./3) 45 KBAppendix 45 KB Copy on its way
PDF
View item 124. as HTML 191 KBReport 191 KB Copy on its way
PDF
York Central and York Station Gateway UpdateReport 26 pages Download

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Central and York Station Gateway UpdateThis decision
  2. York Central Mayoral Development Zone (5:02pm)Agreed
  3. York Central Land Disposal (5:20pm)Approved
  4. York Central Mayoral Development Zone (17:54)Decided
  5. York Central Update (5.38 pm)Noted
  6. York Central Update (5.38 pm)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies