Resolved

(i) That the Strategic Review of City Centre Access and associated Action Plan at Annex 1 to the report be approved, including the creation of an Access Officer post. Reason: To agree a clear strategy for access to and through the city centre footstreets and approve the action plan (subject to the success of identified funding bids) to implement the improvements to access that have been developed through public and stakeholder engagement. (ii) That the City Centre Access model set out in the Strategic Review of City Centre Access be approved as a key principle in Local Transport Plan 4. Reason: To ensure the council’s strategic priorities are aligned and consistent. (iii) That the Strategic Review of Council Car Parking and associated Action Plan at Annex 2 be approved. Reason: To allow the council to define and invest strategically in its priority car parks and to inform future decisions on which car parks could be used for alternatives uses should future parking demand decline through either market conditions or policy based decisions. (iv) That it be noted that a future report on whether to re-commence the paused procurement of a contractor to build St G eorge’s Field MSCP will be brought to Executive as part of a wider delivery update on the Castle Gateway project in February 2022. Reason: To consider whether to proceed with St George’s Field MSCP in light of the outcomes of the Strategic Review of Council Car Parking, a review of the business case, and the wider progress of the masterplan. (v) That the Access Officer be asked to bring updates on the progress of implementing the Access Action Plan to the relevant portfolio holder for review. Reason: To ensure that the progress of the plan is monitored. (vi) That more opportunities be explored for blue badge parking on the edge of the footstreets . Reason: To increase the availability of blue badge parking close to the city centre where possible. (i) That the Strategic Review of City Centre Access and associated Action Plan at Annex 1 to the report be approved, including the creation of an Access Officer post. Reason: To agree a clear strategy for access to and through the city centre footstreets and approve the action plan (subject to the success of identified funding bids) to implement the improvements to access that have been developed through public and stakeholder engagement. (ii) That the City Centre Access model set out in the Strategic Review of City Centre Access be approved as a key principle in Local Transport Plan 4. Reason: To ensure the council’s strategic priorities are aligned and consistent. (iii) That the Strategic Review of Council Car Parking and associated Action Plan at Annex 2 be approved. Reason: To allow the council to define and invest strategically in its priority car parks and to inform future decisions on which car parks could be used for alternatives uses should future parking demand decline through either market conditions or policy based decisions. (iv) That it be noted that a future report on whether to re-commence the paused procurement of a contractor to build St G eorge’s Field MSCP will be brought to Executive as part of a wider delivery update on the Castle Gateway project in February ... view the full minutes text for item 53.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 24 pages

Summary

1. This report sets out the outcomes of the Strategic Review of City Centre Access and Council Car Parking that was commissioned by the Executive in November 2020. The review has been broken down in to two separate strategies which sit together as sister documents.

2. The review of access is based on extensive public and stakeholder engagement and proposes a clear strategy for how people and modes of transport travel to and through the city centre and sets out how access to and through the city centre footstreets can be improved for disabled people, delivery couriers, cyclists and residents.

3. The second review relates to council car parks and has two elements. The first is to identify where there are information gaps in car parking usage and provision that can be improved to guide future evidence based decision making in Local Transport Plan 4 about the role city wide car parking plays within our integrated transport system. The second is to create a hierarchy of council car parks to inform immediate investment decisions and how to respond should there be any future natural or policy driven decline in parking demand.

4. This cover report summarises the outcomes of both reviews and recommends that both are adopted by the council, as are the associated action plans to improve city centre access and parking, which includes the creation of an Access Officer post.

5. The decision regarding the procurement of a contractor for the new St George’s Field multi-storey car park (MSCP) will be considered as part of a future delivery report on Castle Gateway which is due to be brought to Executive in February, including consideration of the outcome of the parking review.

Recommendations

6. The Executive is asked to:

1) Approve the Strategic Review of City Centre Access and associated Action Plan (Annex 1), including the creation of an Access Officer post

Reason: To agree a clear strategy for access to and through the city centre footstreets and approve the action plan (subject to the success of identified funding bids) to implement the improvements to access that have been developed through public and stakeholder engagement

2) Approve the City Centre Access model set out in the Strategic Review of City Centre Access as a key principle in Local Transport Plan 4

Reason: To ensure the council’s strategic priorities are aligned and consistent

3) Approve the Strategic Review of Council Car Parking and associated Action Plan (Annex 2)

Reason: To allow the council to define and invest strategically in its priority car parks and to inform future decisions on which car parks could be used for alternatives uses should future parking demand decline through either market conditions or policy based decisions

4) Note that a future report on whether to re-commence the paused procurement of a contractor to build St George’s Field MSCP will be brought to Executive as part of a wider delivery update on the Castle Gateway project in February 2022

Reason: To consider whether to proceed with St George’s Field MSCP in light of the outcomes of the Strategic Review of Council Car Parking, a review of the business case, and the wider progress of the masterplan Background

7. In November 2020, Executive instructed officers to undertake a strategic review of the city centre access and parking, to be completed by summer 2021. The review was commissioned at the same time as the Executive’s decision to commence the statutory consultation on extending the geography of the pedestrianised footstreet area - this is a separate decision that will be also considered by the Executive on the same agenda.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategic Review of City Centre AccessAppendix 1 30 pages Download
PDF
Strategic Review of Council Car ParkingAppendix 2 24 pages Download
PDF
Annex 1 to the Strategic Review of Council Car ParkingAppendix 2a 50 pages Download
PDF
Equalities Impact Assessment for this ReportAppendix 3 19 pages Download
PDF
Open BriefAppendix 4 11 pages Download
PDF
Strategic Reviews of City Centre Access and Council Car ParkingReport 24 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. Strategic Reviews of City Centre Access and Council Car ParkingThis decision
  2. Called-in Item: Strategic Reviews of City Centre Access and Council Car ParkingAgreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies