City of York Council
Executive, Thursday 18 November 2021 at 5.30pm

York Railway Station Gateway - Project Update and LNER Funding & Development Agreement

Noted Executive 4 papers

Executive noted this item on Thursday 18 November 2021. Below is the council's own wording, with the papers it was decided on.

Item56

Resolved

(i) That the progress made to date with the regard to the design and delivery of the York Station Gateway scheme in particular with respect to procurement of a new professional services contract, delivery of the Package 1: Enabling Works, Package 2: Highway Works, land acquisition, design, Contractor procurement, and current funding status, be noted. Reason: To confirm that the Executive has been updated on project progress as a basis for future decisions. (ii) That the updated budget and Delivery and Procurement Strategy of the scheme be approved, and authority be delegated to the Director of Place (in consultation with the s151 Officer and Director of Governance or their delegated officers) to take such steps as are necessary to procure, award and enter into the resulting contracts for Package 2: Highway Works, Package 4: Loop Road Works (and Package 3: Station Works if agreement on the Funding and Development Agreement with LNER cannot be reached). Reason: To enable arrangements to be put in place to proceed to procurement of a delivery contractor. (iii) That approval be granted to enter into a Funding and Development Agreement between the CYC and LNER for the delivery of Package 3: Station Works and that authority be delegated to the Director of Place (in consultation with the s151 Officer and Director of Governance or their delegated officers) to take such steps as are necessary to negotiate and enter into the final agreement. Reason: To progress the delivery of the station works elements of the scheme which will create space for revised taxi provision at the station and an increase in space for the public realm. (iv) That approval be granted to enter into a Funding Agreement with WYCA to formalise the merging of the West Yorkshire-Plus Transport Fund and the Transforming Cities Fund, and that authority be delegated to the Director of Place (in consultation with the s151 Officer and Director of Governance or their delegated officers) to take such steps as are necessary to negotiate and enter into the final agreement. Reason: To progress the delivery of the scheme. (v) That approval be given to draw down further funds from West Yorkshire-Plus Transport Fund and/or Transforming Cities Fund, to provide funding for LNER to progress the detailed design of the Package 3: Station Works element of the scheme (and the procurement of a delivery Contractor if agreement on the Funding and Development Agreement with LNER cannot be reached) and that authority be delegated to the Director of Place (in consultation with the s151 Officer and the Director of Governance or their delegated officers) to draw the funds down. Reason: To enable the production of detailed cost plans and to progress the station works to procurement. (i) That the progress made to date with the regard to the design and delivery of the York Station Gateway scheme in particular with respect to procurement of a new professional services contract, delivery of the Package 1: Enabling Works, Package 2: Highway Works, land acquisition, design, Contractor procurement, and current funding status, be noted. Reason: To confirm that the Executive has been updated on project progress as a basis for future decisions. (ii) That the updated budget and Delivery and Procurement Strategy of the scheme be approved, and authority be delegated to the Director of Place (in consultation with the s151 Officer and Director of Governance or their delegated officers) to take such steps as are necessary to procure, award and enter into the resulting contracts for Package 2: Highway Works, Package 4: Loop Road Works (and Package 3: Station Works if agreement on the Funding and Development Agreement with LNER cannot be reached). Reason: To enable arrangements to be put in place to proceed to procurement of a delivery contractor. (iii) That approval be granted to enter into a Funding and Development Agreement between the CYC and LNER for the delivery of Package 3: Station Works and that authority be delegated to the Director of Place (in consultation with the s151 Officer and Director of Governance or their delegated officers) to take such steps as are necessary to negotiate and enter into the final agreement. Reason: To progress the delivery of the station works elements of the scheme which will create space for revised taxi provision at the station and an increase in space for the public realm. (iv) That approval be granted to enter into a Funding Agreement with WYCA to formalise ... view the full minutes text for item 56.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
YSG Delivery & Procurement StrategyAppendix 1 73 pages Download
PDF
York Station Front: Better Decision Making ToolAppendix 2 7 pages Download
PDF
View item 56. as HTML 128 KBReport 128 KB Copy on its way
PDF
York Railway Station Gateway: Project Update and LNER Funding & Development AgreementReport 17 pages Download

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Railway Station Gateway - Project Update and LNER Funding & Development AgreementThis decision
  2. Station Building, Railway Station, Station Road, York YO24 1AY [19/00542/LBC]Approved
  3. York Railway Station Gateway – Funding and DeliveryApproved
  4. National Railway Museum, Leeman Road, York YO26 4XD (14/02862/FULM)Approved
  5. Traffic Arrangements at York Railway StationAgreed
  6. Reports on Traffic Management at York Railway Station and York North WestNoted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies