Directorate of Place 2021/22 Transport Capital Programme – Monitor 2 Report
ApprovedExecutive5 papers
Decision Session - Executive Member for Transport - Expired approved this item on Tuesday 18 January 2022. Below is the council's own wording, with the papers it was decided on.
i. That the Chief Operating Officer be recommended to approve the amendments to the 2021/22 Directorate of Place Transport Capital Programme. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme. i. That the Chief Operating Officer be recommended to approve the amendments to the 2021/22 Directorate of Place Transport Capital Programme. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired
Summary
1. This report sets out progress to date on schemes in the 2021/22 Transport Capital Programme, and proposes adjustments to scheme allocations to align with the latest cost estimates and delivery projections.
Recommendations
2. The Executive Member is asked to:
1) Approve the amendments to the 2021/22 Directorate of Place Transport Capital Programme.
Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Background
3. Following approval at Budget Council on 25 February 2021, the Transport Capital Budget for 2021/22 was confirmed at £44,241k. The budget was then amended to £22,095k in June 2021 when the Executive Member was presented with the Consolidated Transport Capital Programme, which included all schemes and funding carried forward from 2020/21, and adjusted the spend profile for the Outer Ring Road and York Station Gateway major schemes. Further amendments to the programme were made at the Monitor 1 Budget report in October 2021. 4. Following these amendments, the current budget for the 2021/22 Transport Capital Programme is £21,879k. This includes funding from the Local Transport Plan (LTP) grant and council resources, and significant funding from various external sources, including grant funding from the European Regional Development Fund (ERDF) for the completion of the Hyper Hubs project, the National Productivity Investment Fund, the West Yorkshire Transport Fund, the Transforming Cities Fund, and funding from the Department for Transport for the Outer Ring Road Dualling scheme. Details of the separate funding allocations are provided in Annex 1 with the funding sources for individual schemes identified in Annex 2.
5. There are several schemes in the programme where progress was delayed in 2020/21 due to the impact of the Covid-19 pandemic, as Transport Service resources were focused on the emergency Covid measures and developing and implementing the Emergency Active Travel schemes, and staff in the Highways section were redeployed to Waste Services to ensure essential services could continue throughout the pandemic. These schemes have been included in the 2021/22 transport capital programme, and feasibility and design has been carried out to develop schemes for implementation. Additional resources have been brought in to address the delays and progress the necessary detailed feasibility work for the Active Travel Programme. See Para 37-41.
2021/22 Major Schemes 6. The allocations within the Major Schemes block will deliver a significant programme of improvements to the city’s infrastructure. Funding for these schemes has been secured from several external funding sources, with contributions from the council’s capital budgets agreed to support these projects.
7. Following public consultation on the Outer Ring Road scheme in 2020/21, some concerns were raised, chiefly about the quality of cycling and walking facilities. Subsequently amendments were made to the scheme to address these concerns, and the revised proposals were presented to CYC Executive in September 2021. The Executive accepted the proposals, subject to the consideration of potential further amendments, and a planning application for the scheme is now being progressed and will be submitted in early 2022. 8. In parallel, work is ongoing to acquire land, develop the business case and complete the detailed design for the scheme. The construction stage is expected to start in mid-2023.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.