Directorate of Place Transport Capital Programme - 2022/23 Monitor 1 Report
ApprovedExecutive6 papers
Decision Session - Executive Member for Transport - Expired approved this item on Tuesday 18 October 2022. Below is the council's own wording, with the papers it was decided on.
i. Approved the amendments to the 2022/23 Directorate of Place Transport Capital Programme. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver sch emes identified in the council’s Transport Programme, including the Active Travel Programme. i. Approved the amendments to the 2022/23 Directorate of Place Transport Capital Programme. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver sch emes identified in the council’s Transport Programme, including the Active Travel Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 13 pages
Summary
1. The purpose of this report is to set out progress to date on schemes in the 2022/23 Transport Capital Programme, and propose adjustments to scheme allocations to align with the latest cost estimates and delivery projections.
Recommendations
2. The Executive Member is asked to:
1) Approve the amendments to the 2022/23 Directorate of Place Transport Capital Programme.
Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme, including the Active Travel Programme.
Background
3. Following approval at Budget Council on 17 February 2022, the Transport Capital Budget for 2022/23 was confirmed at £22,926k. The budget was then amended to £40,043k in July 2022 when the Executive Member was presented with the Consolidated Transport Capital Programme, which included all schemes and funding carried forward from 2021/22, and additional grant funding received from the Active Travel Fund programme and the Zero Emission Bus Regional Area (ZEBRA) programme. 4. The approved budget includes funding from the Local Transport Plan (LTP) grant, developer funding, council resources, and grants for individual schemes. The grant funding includes significant funding from various external sources, including the Active Travel Tranche 2 grant, the West Yorkshire Transport Fund, the Transforming Cities Fund, funding for new electric buses from the Zero Emission Bus Regional Area grant, and funding from the Department for Transport for the Outer Ring Road Dualling scheme.
5. The following report sets out progress on schemes and advises the Executive Member of amendments that need to be made to scheme budgets. Full details of the current and proposed budgets are shown in Annex 1 to this report, and full details of the programme are shown in Annex 2.
6. It should be noted that costs for some schemes have increased compared to the initial cost estimates. This is due to the high level of inflation and other issues affecting the economy at present, meaning the cost of construction materials has increased since the initial cost estimates were prepared.
2022/23 Major Schemes
7. The allocations within the Major Schemes block will deliver a significant programme of improvements to the city’s infrastructure. Funding for these schemes has been secured from several external funding sources, with contributions from the council’s capital budgets agreed to support these projects.
8. A planning application for dualling the York Outer Ring Road (A1237) has been submitted and is now going through the determination period. The project team have now turned their attention to acquiring land, developing the business case, and completing the detailed design for the scheme. Commencement of works on site is programmed for summer 2023, but there are a number of milestones to achieve before funding is released for the construction of the scheme.
9. Following a review of the expected works and costs, it is proposed to slip £1,043k of the York Station Gateway funding allocation to 2023/24 due to the lower expected costs in 2022/23. The utility diversion works started on site in January 2022, and the highways works are expected to begin in spring 2023, with completion currently programmed for autumn 2025. A development agreement was signed between the council and London North Eastern Railway (LNER) for the station works, and design for these works is now being progressed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.