CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Executive, Thursday 21 April 2022 at 5.30pm

York Central Enterprise Zone Funding Agreement

Agreed Executive 4 papers

Executive agreed this item on Thursday 21 April 2022. Below is the council's own wording, with the papers it was decided on.

Item117

Resolved

(i) That authority be delegated to the Chief Finance Officer, in consultation with the Director of Governance or her delegated officers, to enter into an Enterprise Zone (EZ) funding agreement with Homes England to reimburse infrastructure costs to enable the delivery of York Central. (ii) That the previously approved £35m capital budget funded from future EZ receipts be allocated as a contribution to the enabling infrastructure, to be used after all other grant funding has been exhausted. (iii) That up to £2.7m of previously approved CYC borrowing be allocated to fund the Technical Assurance work to enable the highways infrastructure to be adopted. (iv) That up to £500k of previously approved CYC borrowing be allocated to deliver the Jubilee Terrace to Scarborough Bridge Riverside Path improvement scheme. (v) That up to £250k of EZ revenue receipts be allocated to fund inward investment activity in the council’s economic development team, specifically to promote York Central and to attract occupiers. (vi) That authority be delegated to the Director of Transport, Environment & Planning to agree technical assurance arrangements for the adoption of the highways infrastructure for York Central as set out in the report. (vii) That authority be delegated to the Director of Transport, Environment & Planning (in consultation with the Director of Governance or her delegated officers) to enter into S278/38 Agreements with York Central landowners. (viii) That authority be delegated to the Director of Transport, Environment & Planning (in consultation with the Director of Governance or her delegated officers) to enter into the Bridge Agreements with Network Rail and Homes England. (ix) That authority be delegated to the Director of Transport, Environment & Planning, in consultation with the Executive Member for Transport, to certify the discharge of conditions to permit the Stopping Up of Leeman Road. (x) That approval be given to dispose of the former Canteen Building on Chancery Rise to Network Rail in order to facilitate the removal of their operational uses from the York Central site, and delegate to the Director of Housing Economy and Place to agree the final value, following an independent valuation exercise. Reason: To ensure the delivery of York Central and to provide funding for enabling infrastructure including a new access route to York Central, and to support the commercial development of the scheme to generate EZ income to fund that infrastructure. (i) That authority be delegated to the Chief Finance Officer, in consultation with the Director of Governance or her delegated officers, to enter into an Enterprise Zone (EZ) funding agreement with Homes England to reimburse infrastructure costs to enable the delivery of York Central. (ii) That the previously approved £35m capital budget funded from future EZ receipts be allocated as a contribution to the enabling infrastructure, to be used after all other grant funding has been exhausted. (iii) That up to £2.7m of previously approved CYC borrowing be allocated to fund the Technical Assurance work to enable the highways infrastructure to be adopted. (iv) That up to £500k of previously approved CYC borrowing be allocated to deliver the Jubilee Terrace to Scarborough Bridge Riverside Path improvement scheme. (v) That up to £250k of EZ revenue receipts be allocated to fund inward investment activity in the council’s economic development team, specifically to promote York Central and to attract occupiers. (vi) That authority be delegated to the Director of Transport, Environment & Planning to agree technical assurance arrangements for the adoption of the highways infrastructure for York Central as set out in the report. (vii) That authority be delegated to the Director of Transport, Environment & Planning (in consultation with the Director of Governance or her delegated officers) to enter into S278/38 Agreements with York Central landowners. (viii) That authority be delegated to the Director of Transport, Environment & Planning (in consultation with the Director of Governance or her ... view the full minutes text for item 117.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Site PlanAppendix 1 1 pages Download
PDF
Land At Holgate RoadAppendix 2 1 pages Download
PDF
View item 117. as HTML 229 KBReport 229 KB Copy on its way
PDF
York Central Enterprise Zone Funding AgreementReport 27 pages Download

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Central Enterprise Zone Funding AgreementThis decision
  2. York Central Mayoral Development Zone (5:02pm)Agreed
  3. York Central Land Disposal (5:20pm)Approved
  4. York Central Mayoral Development Zone (17:54)Decided
  5. York Central Update (5.38 pm)Noted
  6. York Central Update (5.38 pm)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies