Recommended: (i) That Council agree the revised capital programme of £481.980m that reflects a net overall increase of £51.158m (as set out in table 2 at paragraph 18 of the report and in Annex A), key elements of which include: a) New schemes funded by prudential borrowing totalling £1.229m as set out in Table 3; b) Extension of prudential borrowing funded Rolling Programme schemes totalling £22.286m as set out in Table 4; c) Extension of externally funded Rolling Programme schemes totalling £8.998m as set out in Table 6; d) An increase in HRA funded schemes totalling £18.645m funded from a combination HRA balances/Right to Buy receipts as set out in Table 7. (ii) That Council note that the total increase in council borrowing as a result of new schemes being recommended for approval is £23.515m, the details of which are considered within this report and the financial strategy report. (iii) That Council approve the full restated programme totalling £481.980m covering financial years 2023/24 to 2027/28, as set out in table 11 and Annex B. Reason: In accordance with the statutory requirement to set a capital budget for the forthcoming financial year.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. This report sets out the capital programme for 2023/24 to 2027/28, and in particular sets out proposals to continue the Council’s approach to prioritise investment in the economy, housing, transport and to invest to save including energy efficiency.
2. Schemes funded by borrowing have an associated revenue impact. In order to minimise the additional growth required in future years, and mindful of the Council’s current financial position in light of both the ongoing pressures in social care and the current economic uncertainty, it is proposed that any new borrowing is minimised as much as possible by reprioritising elements of the existing approved programme. Whilst it is recommended that the overall level of borrowing is not increased from that currently approved it is also recognised that there is a need to continue to invest to ensure a strong recovery
Proposed Reductions to the Capital Programme
3. The current capital programme totals £560m of which £177m is funded from prudential borrowing. In order to reduce the need for additional revenue budget to support the cost of borrowing the current capital programme has been reviewed to consider whether the funding available reflects the latest delivery.
4. As a part of this review a number of project lines are proposed to be reduced / removed which has resulted in the reduction of £2,650k from the proposed programme. A review of existing assets will also be carried out with a view to dispose of sites to the value of approx. £9m in order to support the council’s financial position. Integrated Transport (£1,570k)/ Bishophill Traffic Reduction (£230k)
5. The council has been very successful in receiving external funding for its Highways and Transport programmes. Major schemes at Tadcaster Road, Station Gateway and York Central are programmed for delivery during 2023/24 and further funding has been received for Active Travel Schemes and Bus Service Improvement Plan. In order to prioritise the delivery of schemes already approved it is proposed to remove £1.57m of CYC borrowing from the Integrated Transport line. Due to ongoing work on design options the Bishophill Traffic Reduction Scheme will be delivered from the Integrated Transport block.
Guildhall (£500k)
6. Following agreement of the final account with the Principal Contractor at the Guildhall it has been possible to reduce the reported cost by £500k which had been released from capital contingency.
York Central Holgate Park (£397k)
7. A budget of £1.55m was agreed to purchase two plots of land at York Central in 2011. The budget included the purchase of land as well as site clearance and remediation. The purchase price of £1.15m was agreed and £397k has been retained for demolition of buildings on site. The first plot of land was sold back to Network Rail and the remaining site is in negotiation for a sale. The remaining budget is no longer required and can be removed from the programme.
Public Realm and Waste Operational Equipment (£100k)
8. This budget (£268k) is a combination of the residual budget of £525k which was set aside for replacing litter bins and the Wheeled Bins in Terraced areas budget. The litter bin replacement scheme has primarily been completed and there is scope to reduce the budget by £100k and still undertake the outstanding commitments for “bags to bins”.
9. As part of this budget process over £51m of new capital funding will be added to the 5 year capital programme to continue to support the objectives outlined in the Council Plan, including a further £9m on highways schemes, £7.9m on fleet infrastructure and vehicles to deliver as many electric vehicles as possible, £17.815m on major repairs and modernisation of local authority homes. A summary of this new funding can be found at Annex A, and specific examples of capital investment include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.