Capital Budget 2025/26 to 2029/30 (17:41)

Agreed Executive 4 papers

Executive agreed this item on Tuesday 21 January 2025. Below is the council's own wording, with the papers it was decided on.

Item78

Resolved

i. To recommend the Council agree to the revised capital programme of £385.383m that reflects a net overall increase of £60.947m (as set out in table 2 and in Annex 1). Key elements of this include: a. New schemes funded by prudential borrowing totalling £8.150m as set out in table 3; b. Extension of prudential borrowing funded Rolling Programme schemes totalling £24.712m as set out in table 4; c. Extension of externally funded Rolling Programme schemes totalling £11.935m as set out in table 5; d. An increase in HRA funded schemes totalling £16.150m funded from a combination HRA balances/capital receipts as set out in table 6; ii. To recommend that Council noted the total increase in Council borrowing as a result of new schemes being recommended for approval is £32.862m the details of which are considered within this report and the financial strategy report. iii. To recommend that Council approve the full restated programme as summarised in Annex 2 totalling £385.383m covering financial years 2025/26 to 2029/30 as set out in table 10 and Annex 2. Reason: To ensure the Council maintains the funding for the capital programme. i. To recommend the Council agree to the revised capital programme of £385.383m that reflects a net overall increase of £60.947m (as set out in table 2 and in Annex 1). Key elements of this include: a. New schemes funded by prudential borrowing totalling £8.150m as set out in table 3; b. Extension of prudential borrowing funded Rolling Programme schemes totalling £24.712m as set out in table 4; c. Extension of externally funded Rolling Programme schemes totalling £11.935m as set out in table 5; d. An increase in HRA funded schemes totalling £16.150m funded from a combination HRA balances/capital receipts as set out in table 6; ii. To recommend that Council noted the total increase in Council borrowing as a result of new schemes being recommended for approval is £32.862m the details of which are considered within this report and the financial strategy report. iii. To recommend that Council approve the full restated programme as summarised in Annex 2 totalling £385.383m covering financial years 2025/26 to 2029/30 as set out in table 10 and Annex 2. Reason: To ensure the Council maintains the funding for the capital programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Meeting: Executive Meeting date: 21/01/2025 Report of: Debbie Mitchell, Director of Finance Portfolio of: Councillor Katie Lomas, Executive Member for Finance, Performance, Major Projects, Human Rights, Equality & Inclusion

Decision Report: Capital Budget 2025/26 to 2029/30 Subject of Report 1. This report sets out the capital programme for 2025/26 to 2029/30, and in particular sets out proposals to continue the Council’s approach to prioritise investment in the economy, housing, transport and to invest to save including energy efficiency.

Benefits and Challenges 2. Schemes funded by borrowing have an associated revenue impact. In order to minimise the additional growth required in future years, and mindful of the Council’s current financial position in light of both the ongoing pressures in social care and the current economic uncertainty, it is proposed that any new borrowing is minimised as much as possible by reprioritising elements of the existing approved programme.

3. The costs of supporting the capital programme have increased over the years as the Bank of England increased base rates from 0.25% in February 2022 to 5.25% in August 2023 and have only recently started to reduce to 4.75% in November 2024. This has resulted in increases to the cost of borrowing compared to 2022. Given the challenges outlined in the Financial Strategy report elsewhere in the agenda, only essential new investment is recommended at this time.

4. The council has been successful in identifying external funding for much of its schemes. The 5 year capital programme currently stands at £427m

Page 1 of 36 (as reported in Monitor 3) of which £166m (42%) is funded from external grants and contributions, £167m (34%) from general fund borrowing / internal resources and £94m (24%) from internal Housing Revenue Account (HRA) funding. There are further opportunities in the recently created York and North Yorkshire Mayoral Combined Authority to further increase external funding for investment in the city.

5. The Prudential Code requires Local Authorities to only undertake borrowing that is affordable within available resources. This report therefore needs to considered in line with the other budget papers on this Agenda.

Policy Basis for Decisions 6. The capital programme budget covers the period 2025/26 to 2029/30 and sets out revised investment in the capital programme over the next 5 years.

7. The level of capital investment and levels of borrowing are a key element of the overall finances of the council and key part of the Medium Term Financial Plan.

Financial Strategy Implications 8. This report outlines the five year programme for capital investment and needs to be considered alongside the other key financial reports on the agenda. The report recommends an increase in the council’s borrowing of £32.862m (the largest amount being in 2029/30).

Recommendations and Reasons 9. The Executive is requested to recommend that Council:  Agree to the revised capital programme of £385.383m that reflects a net overall increase of £60.947m (as set out in table 2 and in Annex 1). Key elements of this include: o New schemes funded by prudential borrowing totalling £8.150m as set out in table 3; o Extension of prudential borrowing funded Rolling Programme schemes totalling £24.712m as set out in table 4; o Extension of externally funded Rolling Programme schemes totalling £11.935m as set out in table 5;

Page 2 of 36 o An increase in HRA funded schemes totalling £16.150m funded from a combination HRA balances/capital receipts as set out in table 6;

 Note the total increase in Council borrowing as a result of new schemes being recommended for approval is £32.862m the details of which are considered within this report and the financial strategy report.

 Approve the full restated programme as summarised in Annex 2 totalling £385.383m covering financial years 2025/26 to 2029/30 as set out in table 10 and Annex 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital GrowthAppendix 1 79 KB Download
PDF
abbreviated capital programme including growthAppendix 2 85 KB Download
PDF
Capital Budget 2025/26 to 2029/30 (17:41)Report 573 KB DownloadRead as text
PDF
View item 78. as HTML 296 KBReport 296 KB Copy on its way

At this meeting

Whole meeting

Who was there

7 of 8 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneVice-Chair, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, present
MP
Councillor Michael PavlovicCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, present
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbCommittee Member, apologies

On this subject at York

Search all
  1. Capital Budget 2025/26 to 2029/30 (17:41)This decision
  2. Capital Budget 2026/27 to 2030/31Agreed
  3. Capital Budget 2024/25 to 2028/29Agreed
  4. Capital Budget 2023/24 to 2027/28 (18:40)Agreed
  5. Directorate of Place 2022/23 Transport Capital Programme – Budget ReportApproved
  6. Capital Budget 2022/23 to 2026/27Agreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies