City of York Council
Executive, Thursday 18 July 2024 at 4.30pm

Acomb Front Street – Phase 2 Update (18:20)

Approved Executive 4 papers

Executive approved this item on Thursday 18 July 2024. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

i. Approved the high-level principles set out for the phase 2 scheme design as detailed in Table 3, reconfirming Executive’s agreement to allocate £570k of UKSPF monies to Acomb and instruct officers to finalise project designs and costings on this basis. Reason: In October 2023, it was agreed that an update on Phase 2 would come back to Executive for their consideration following public engagement. Phase 2 timescales are tight because delivery against UKSPF spend deadlines is extremely challenging (March 25). This progress report brings forward as much as detail possible for Executive to agree the high-level principles, thus allowing the scheme design and costings to be finalised in time for a planned start on site by the end of September 2024. ii. Delegated authority to approve the recommendations on the final costed scheme design be to the Executive Member for Economy & Culture, to be made at a public decision session in September 2024. Reason: Delivery against UKSPF spend deadlines is extremely challenging (March 25). This progress report brings forward as much as detail possible for Executive to agree the high-level principles, however additional work is still required to finalise designs and costings. It is crucial the learnings and analysis generated from the quantum of engagement responses are reflected in the final designs, and thereby addresses community concerns/ future aspirations. iii. Given the tight spending timescales of the UKSPF funding, agree a number of practical next steps to enable officers to commence further necessary preparatory work ahead of final scheme design/costing decisions being made in September 2024, namely: (a) that work be progressed on the scope, design and procurement of seating/planting, wayfinding/signage and the local ‘place-making/identity’ elements of Phase 2 e.g. public art/mural(s), and that alternative funding options for this work also be investigated, and to delegate authority to the Director of Housing, Economy & Regeneration (in consultation with the Head of Procurement and the Director of Governance) to take such steps as are necessary to procure, award and enter into the resulting contracts. Reason: Reason, to allow necessary preparatory work to progress and to reduce risks around the tight UKSPF delivery timescales for these elements of the project. (b) approved commencement of work to enable the statutory consultation for two new Traffic Regulation Orders (TRO’s) required for the proposed new disabled parking area at York Road layby and 20mph speed restriction in main shopping area of Front Street, and to delegate authority to approve the implementation of the TRO’s to the Executive Member for Economy & Culture ( in consultation with the Executive Member for Transport) when considering the final scheme in September 2024. Reason: Statutory Consultation for a Traffic Regulation Order is required to engage with local traders and businesses to identify any risks or mitigations required to the proposals. There is a 6–7- week lead time with this consultation, commencement of this work prior to consideration of final design in September avoids delay to construction programme and implementation. (c) asked officers to commence discussions with Make it York ... i. Approved the high-level principles set out for the phase 2 scheme design as detailed in Table 3, reconfirming Executive’s agreement to allocate £570k of UKSPF monies to Acomb and instruct officers to finalise project designs and costings on this basis. Reason: In October 2023, it was agreed that an update on Phase 2 would come back to Executive for their consideration following public engagement. Phase 2 timescales are tight because delivery against UKSPF spend deadlines is extremely challenging (March 25). This progress report brings forward as much as detail possible for Executive to agree the high-level principles, thus allowing the scheme design and costings to be finalised in time for a planned start on site by the end of September 2024. ii. Delegated authority to approve the recommendations on the final costed scheme design be to the Executive Member for Economy & Culture, to be made at a public decision session in September 2024. Reason: Delivery against UKSPF spend deadlines is extremely challenging (March 25). This progress report brings forward as much as detail possible for Executive to agree the high-level principles, however additional work is still required to finalise designs and costings. It is crucial the learnings and analysis generated from the quantum of engagement responses are reflected in the final designs, and thereby addresses community concerns/ future aspirations. iii. Given the tight spending timescales of the UKSPF funding, agree a number of practical next steps to enable officers to commence further necessary preparatory work ahead of final scheme design/costing decisions being made in September 2024, namely: (a) that work be progressed on the scope, design and procurement of seating/planting, wayfinding/signage and the local ‘place-making/identity’ elements of Phase 2 e.g. public art/mural(s), and that alternative funding options for this work also be investigated, and to delegate authority to the Director of Housing, Economy & Regeneration ... view the full minutes text for item 18.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Acomb Front Street: Phase 2 Update (18:20)Report 294 KB Copy on its way
PDF
Executive Summary Engagement FeedbackAppendix A 2 MB Copy on its way
PDF
Survey Questionnaire AFSAppendix B 2 MB Copy on its way
PDF
AFS EIA2-Template-2021Appendix C 335 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. Acomb Front Street – Phase 2 Update (18:20)This decision
  2. The Determination of an Application by Punch Taverns Limited for Variation of a Premises Licence [Section 35 (3)(a)] in respect of The Marcia Grey, 24 Front Street, Acomb, York, YO24 3BZ (CYC-009010) (11:09am)Decided
  3. Decision Report: Acomb Front Street - Phase 2 Design and Costings (10:08am)Approved
  4. Acomb Front Street Phase 2 Update (5.34 pm)Decided
  5. Acomb Front Street Phase 2 - open public engagement on costed designs and ideas for the scheme (10:32am)Approved
  6. Future of Acomb Front Street - Enhancing Economic Growth for Secondary Shopping AreasApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies